Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 72     Entry time: 10 Mar 2017, 16:56
Author: Tobias Haas 
Location: General 
Severity: Information 
Subject: Tunnel Commissioning Schedule for Week 11 
Day Motion Vacuum EPS Other 
Monday Loop is up. AE continues tests on MC2 lib Loop up. AE investigates problem with ion pump controller Loop inactive  
Tuesday Loop is up. AE continues tests on MC2 lib Loop down. AE implements fix for ion pump controller Loop inactive  
Wednesday Loop down. AE adds ELMO and TECHNOSOFT Loop up for testing AE brings up loop  
Thursday Loop down. AE adds ELMO and TECHNOSOFT Loop up for testing AE brings up loop  
Friday Loop up for testing Loop up for testing Loop up for testing  

 

In addition it should be tried to have a so called "Happy Hour" every day from 0800 - 1000. During this time loops should be up if possible. Meaning that in the evening before leaving, developers bring loops back up.