Subject: Status report after dispatch meeting 13:00 

SPB

  • The power shutdown has been delayed to tomorrow and power is supposed to come back on Thursday at 12:00. Torsten Schen will send an E-mail to readiness when the power comes back on Thursday.
  • Pumps are in a safe state since they currently get external power.

AE

  • Loop 4 SQS up and running. New SASE3 loops being prepared.

ITDM

  • GPFS space issue. Meeting with the experiments on Thursday.
  • MID controls, timing and signals cables have to go through the drag chain (40 m). ITDM and AE will discuss the issue with MID to evalueate problems due to the cables length.

CAS

  • XTD6 closed tomorrow. This will generate some delay of the technical commissioning. 
  • Karabo 2.2.4. deployment schedule proposed by Hugo Santos with an entry in the ELOG this morning.