Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 294     Entry time: 19 Jun 2017, 10:17
Author: Monica Aresté 
Location: General 
Severity: Information 
Subject: Status and plans after SASE1 Readiness Meeting 

XTDs:

  • There are no major issues, commissioning works smoothly this weekend.

FXE:

  • Radiation safety measures done last Wednesday.
  • Tests with CRL are on going but there are some problems with motors since are moving only in one direction. CAS is working on that issue.
  • Loop1 need an update, support from AE necessary.
  • Interlock conditions meeting to be held today, to carry out  the test end this week.

SPB:

  • Test with loop2 continue.
  • Cables for Loop3 will be repaired today and tomorrow. Firmware already available.
  • Export for loop 7 is done, AE is working to generate the firmware. EET has two persons working in the exports for loops 4 and 12.
  • Interlock conditions already defined by SPB sometime ago.

Diagnostics:

  • External trigger for Basler cameras still not always working, CAS keep working on that.

 

Electronics:

  • Today and tomorrow working for the AGIPD, required an additional interlock part for the Vacuum.
  • First priority is is to have the Vacuum system for FXE and SPB operational at the end of June. Next two weeks AE will be mainly focus in the loops that are still missing (SPB 4, 5, 7,12) or still not running (SPB 2, 3)

 

Software:

  • Karabo version installed in a different domain, CAS is still testing ths version to ensure a smooth transition from one version to other.