SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 352
Entry time: 02 Aug 2017, 10:17
|
Author: |
Monica Aresté |
Location: |
General |
Severity: |
Information |
Subject: |
Status after 9:30 dispatch Meeting |
|
|
General
-
This Thursday the radiation test in D.05 (FXE) will be performed (from approximately 0900 to 1500), access to all areas adjacent to the hutch is only allowed by those that are assisting with the measurements.
-
Meeting on Friday is cancelled. We will meet again on Monday 7-08-2017.
FXE
- Gotthard detectors to be tested in Karabo. On going.
- Finished commissioning of OGT2_CRL and OGT1_ATT. The laser to be used in September installed and connected to electronics.
SPB
-
Problem with Smaract motors has been identified. Loop 12 updated, full test still on going.
-
Cameras trigger for the sample environment is now working. Software issues, CAS is addressing that.
-
Vacuum interlock for Loop 5 (AGIPD) is being implemented. Interlock definitions for AGIPD under discussion with AE to continue work on this loop.
-
Working in the commissioning of Loop13.
Tunnels
-
In case of fake triggering of the fast valves, there is now a procedure to open them again remotely. Please check the related entry posted by M. Dommach.
-
Two issues with photonic cameras already solved by CAS.
-
Images are displayed later, this issue will be discussed off-line with CAS.
AE
-
FXE Interlock definitions have been changed and this reflects in the update of loop 1 and 2. Done.
-
Working on Alio Stages integration for Mono in the tunnel. Developing.
-
SPB Loop 12 – Smaract motors and ELMO controllers implementation done.
-
SPB Loop 5 thre are some issues with Julabo Chiller, AE contacted the manufacturer for information.
-
SPB Loop 13 - Phase 2 cables for some modules are at different positions compared to eplans. Change request submitted to swap module postions.
-
Cables for interface to Person Interlock laid. Connections to the MPS system to be done this week.
-
Loop 8 should be the next, EET to clarify if the export is done and provide to AE.
DET
-
LPD – Synchronization is still showing problems, this is delaying the tests.
-
AGIPD – Detector being tested in Hera south. KWrona started the tests of DAQ, some minor issues arised but in general it works.
CAS
-
2.1.13 Karabo version update is being agreed with the interested parties. Implementation will be next Tuesday 8.08.2017 in the afernoon. It takes approx. 3 hrs.
-
CAS will send around a list with the tasks foreseen to be solved during the next weeks.
|