Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 78
Entry time: 16 Mar 2017, 13:34
|
Author: |
Torben Falk |
Location: |
General |
Severity: |
Feedback |
Subject: |
Wiring status |
|
|
Wiring status SASE 1:
Wiring progress:
- Internal wiring of the XGM in XTD 9 is done.
- Vacuum part wiring of the XGM in XTD 9 is done (ready for local Beckhoff test).
- Gas Panel wiring of the XGM in XTD 9 is done.
- Crate wiring (ADAM & Femto crate) of the XGM in XTD 9 is done.
Upcoming work XTD 2:
- Serial connection from Beckhoff to TCP 350.
- Change cold plug cables into halogenfree cables.
Upcoming work XTD 9:
- INHIBIT connection Iseg HV crate.
- Serial connection from MTCA to RVC 300.
Upcoming work XTD 10:
- Vacuum part wiring of XGM.
- Gas Panel wiring of XGM.
- Internal wiring of XGM.
- Installing ADAM & Femto crate.
- Measure cable lengths for Imager and prepare cables.
|