Message ID: 570     Entry time: 15 Oct 2018, 13:39
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 09.30 

SPB

  • Issue with the detector cooling pipes during the week end required intervention. Now fixed.

  • Commissioning ongoing.

  • Interlock definitions to be deployed probably tomorrow.

FXE

  • Pulse on demand capability successfully tested
  • Issue with the DAQ: crush of data aggregators. ITDM OCD has been notified and the issue is being investigated.
  • The users would request the Jungfrau detector working for friday. FXE asked for feedback about the status of the detectors integration to DET, CAS, ITDM. The feedback is needed to inform the users.

SQS

SCS

MID

  • Loop 4 is waiting for ion pumps cables to be commisisoned. as soon as the cables are there AV will inform CY and MID.

HED

XPD

VAC

AE

  • SQS/SPB interlocks will be propbably deployed tomorrow.
  • SASE3 master loop will be updated tomorrow.

ITDM

  • ITDM needs to know until when the photon commissioning in SASE2 tunnels is ongoing to update the DAQ servers. The information should come from HSinn or PRCs, who are not at the meeting. JS will try to contact them directly.  ==> HW was updated but still with the old configuration. Moving of data services to new aggregators needs discussion.

 