SASE1 Status and SASE3 Readiness
 | 
|   Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  | 
Not logged in | 
  | 
   | 
| 
Message ID: 565
    Entry time: 19 Sep 2018, 09:58
 |  
| Author: | 
Adriano Violante  | 
 | Location: | 
General  | 
 | Severity: | 
Information  | 
 | Subject: | 
Status report after dispatch meeting 09.30  | 
 
  |  
 
 | 
SPB 
FXE 
SQS 
	- Interlock definitions - clarifications with AE ongoing.
 
	- Loop assignment changed. Next loop to be brought up is Loop 10 (probably by next week by Hazem)
 
	- Network storage for the control PCs in the control room. Discussion ongoing (data policy, accesibility...). Is being done offline and will be reported to a larger audience when clarified.
 
 
SCS 
	- Interlock definitions being finalized. Update of the loops will be done soon.
 
 
MID 
	- Loop 1 deployed and technical commissioning of the OPT hutch is ongoing. No major issues.
 
	- Loop4 needed for next week.
 
	- Request to CAS for GUI training. CY and AS have to clarify who organizes that in CAS. CY understanding is that Hugo Santos is going to do it. Will be discussed offline.
 
 
HED 
	- Rack 2.19 shows messy cabling. KS will contact UBrueggmann to understand who is responsible for the devices in the racks. 
 
 
AE 
	- This week all the modified crates for SCS and SQS will be reinstalled and loops updated by BB
 
 
ITDM 
	- The upgrade of the DAQ in FXE was postponed to the next week on request from FXE.
 
 
CAS 
	- Karabo 2.2.5. patch being released today
 
 
   |