Subject: Status report after dispatch meeting 09.30 

SPB

  • During operation Karabo crashed. As soon as detector is being operated the problem appears. Fixing is still ongoing.
  • 2 mirrors in D.02 are being installed.
  • Test of the mirrors movements has been performed.

FXE

  • Debug of implemented devices ongoing
  • Diamond grating in XTD9 has to be moved out of the beam way manually (no remote controls implemented due to long lead time of required beckhoff teminals). Access requested for Wednesday.
  • Vac group will check whether beckhoff terminals are available to allow the remote control of the dimaond grating

 

Vacuum

  • During the weekend the XGM in SASE3 was damaged. Details still unknown. 

AE

  •  SASE2 XGM local test ongoing
  • GAT loop update in SASE3 being done.
  • Local checks in XTD10 on Wed.

 

ITDM

  •  Slow data acquisition issue affecting imagers: solved
  • One server died over the week end. ITDM notified only today.

 

 

 