Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 260     Entry time: 22 May 2017, 13:31
Author: Tobias Haas 
Location: General 
Severity: Information 
Subject: Status and Plans after 09:30 Meeting 
General:
  • No break this week on Wednesday. (Wednesday breaks for XTD10 should start next week)
  • Possibility of ZZ access to XTDs on Tuesday from 0700 - 1500. Harald organises the access for vacuum and
    diagnostics. No ZZ without previous experience
  • Expect XTD9 to close next week.

XTDs:
- SR imager crashed several times on the weekend. D. Görries spent a lot of time investigating and found that
when the configuration of the camera is set to mono-8 it runs stably. This indicates that there is a network
bandwidth issue
- D. Görries also had to restart the KARABO server for the MCP. One motor was working but the other one had
hardware problem and requires an access to the tunnel
- Tests for ELMO motor on PBLMs this week by Mahadi and A. Silenzi. N. Gerassimova is on holidays but agreed to
the test
- A. Parenti would like to deploy SW with added debugging functionality for imagers

FXE
- A. Galler and W. Gawelda are not available this week
- D. Görries reports that there are still problems with controlling the vacuum, I. e. gauges, pumps, valves,
fast valve. Some are related to cabling problems that are currently being fixed
- A firmware upgrade is requested for the commissioning crate. Will be discussed in detail with AE

SPB
- Work by AE on AGIPD for this week was called off as detector consortium wants to work on the hardware
- AE will concentrate on commissioning loops 1&2 for the optics hutch
- Firmware for loops 1&2 needs to be first regenerated
- All cabling problems should be solved by tonight
- All crates can then be pushed in
- All cables should be done except for 4 or 5 in the instrument hutch

KARABO

- The bug that results in devices not updating in the GUI server still persists
- Users are requested to inform A. Silenzi as soon as they discover this behaviour

Plan for the next days
- Start with SPB optics hutch
- Update firmware of FXE commissioning crate
- Test ELmo motor in XTD9
ELOG V3.1.4-7c3fd00