Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 515     Entry time: 23 Apr 2018, 15:35
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 13:00 

SPB

  • Timing tool for optical laser installed
  • Sample chamber's PLC will be updated next week due to ongoing tests until monday. Pending.
  • It is not clear whether the AGIPD firmware has to be updated. To clarify with Jola when she is back. The info is important foe ITDM to plan the DAQ tests. Pending. 
  • During the last users run it happened that a valve in XTD9 was closed but the beam did not trip. It is not clear why. Will be clarified with AE. Pending.

AE

  • SASE2 EPS Loop running
  • Updating PLCs for MPS in the tunnels. The update was stopped last friday due to a problem with the on/off funcionality of some ion pumps. The problem was found and the fixing requires an update of the VAC loops whoch will be done in the next hours/days. In case the loop update is not possible due to specific requirements the problem can be bypassed in Karabo. 

 

General

On Wednesday the meeting will be held at 13:00. Starting from next monday it will go back to 9.30