Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Entry   Status and Plans after 01:30 meeting, posted by Tobias Haas on 16 Oct 2017, 15:22 
    Reply   Status and Plans after 01:30 meeting, posted by Tobias Haas on 16 Oct 2017, 15:54 
Message ID: 402     Entry time: 16 Oct 2017, 15:22     Reply to this: 403
Author: Tobias Haas 
Location: General 
Severity: Information 
Subject: Status and Plans after 01:30 meeting 

General

  • Closing of XTD2/4/9/10 foreseen for Oct 23. Possibly XTD9/10 can be re-opened afterwards and stay open until 28 October

Instruments

  • SPB:
    • A lot of cabling work was done. Cable drag chains were installed for AGIPD to move it to another posiiton
    • Roughing pipes were installed
    • Update of KARABO to 2.1.18 was not as smooth as expected. Currently it is not operational. An operational control system is needed soon
    • M. Messerschmidt sent another message with problems early today
  • FXE
    • Final testing ongoing of Gotthardt with KARABO
    • Cable management and cable re-routing was done last week

Tunnels

  • V0 valve was replaced
  • The first vacuum section down stream from V0 was successfully closed and leak tested
  • DESY Vacuum group is currently working on the respective section upstream of V0
  • Welders are here today to work on the two pipes with leaks. They spent all morning on safety trainings
  • The gas attenuator was leak tested on the "good" side (where vacuum section is currently ok/no leaks)
  • Pumping has started on the diff pumping section by Vac
  • Many small things (mostly cabling and electronics)_ remain to be done

Diagnostics

  • Group was not represented by some infos from J. Tolkiehn
  • More tests are needed for the Diff Pumping of the Diagnostics group.
  • Diff Pumping and PES require more crates to be connected

AE

  • SPB loop 5 was cycled.
  • The issues with the turbo pumps is being worked on today (Pumps do not turn on after loop is cycled)
  • Work is ongoing on the MKS gauge controller
  • In the SASE1 tunnel the motion loop will be updated tomorrow and the vacuum loop on Wednesday 
  • At this time the SPB loop in XTD9 will also be cycled
  • FXE is asked to provide information on what works need to be done
  • SASE3 Tunnel:
    • Interlock definitions arre prepared but need to be implemented
    • Many local tests still ongoing
    • There are still problems with inconsistent/wrong device names
    • Two motions loops (mov1/mov2) mov1 contains the most important components upstream
    • EPS not expected for some time

ITDM

  • GPFS upgrade today
  • redundancy data link might be done today
  • Tomorrow: DAQ SW upgrade for LPD (Is still at KARABO 2.1.16.4)

CAS

  • Long discussion happened on what the word "mandatory" means in conjunction with the most recent KARABO release
  • CAS will look into the specific problems in SPB and FXE that have been brought up
  • H. Santos discussed the scan tool with S. Brockhauser on Saturday