SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
|
|
|
Message ID: 402
Entry time: 16 Oct 2017, 15:22
Reply to this: 403
|
Author: |
Tobias Haas |
Location: |
General |
Severity: |
Information |
Subject: |
Status and Plans after 01:30 meeting |
|
|
General
- Closing of XTD2/4/9/10 foreseen for Oct 23. Possibly XTD9/10 can be re-opened afterwards and stay open until 28 October
Instruments
- SPB:
- A lot of cabling work was done. Cable drag chains were installed for AGIPD to move it to another posiiton
- Roughing pipes were installed
- Update of KARABO to 2.1.18 was not as smooth as expected. Currently it is not operational. An operational control system is needed soon
- M. Messerschmidt sent another message with problems early today
- FXE
- Final testing ongoing of Gotthardt with KARABO
- Cable management and cable re-routing was done last week
Tunnels
- V0 valve was replaced
- The first vacuum section down stream from V0 was successfully closed and leak tested
- DESY Vacuum group is currently working on the respective section upstream of V0
- Welders are here today to work on the two pipes with leaks. They spent all morning on safety trainings
- The gas attenuator was leak tested on the "good" side (where vacuum section is currently ok/no leaks)
- Pumping has started on the diff pumping section by Vac
- Many small things (mostly cabling and electronics)_ remain to be done
Diagnostics
- Group was not represented by some infos from J. Tolkiehn
- More tests are needed for the Diff Pumping of the Diagnostics group.
- Diff Pumping and PES require more crates to be connected
AE
- SPB loop 5 was cycled.
- The issues with the turbo pumps is being worked on today (Pumps do not turn on after loop is cycled)
- Work is ongoing on the MKS gauge controller
- In the SASE1 tunnel the motion loop will be updated tomorrow and the vacuum loop on Wednesday
- At this time the SPB loop in XTD9 will also be cycled
- FXE is asked to provide information on what works need to be done
- SASE3 Tunnel:
- Interlock definitions arre prepared but need to be implemented
- Many local tests still ongoing
- There are still problems with inconsistent/wrong device names
- Two motions loops (mov1/mov2) mov1 contains the most important components upstream
- EPS not expected for some time
ITDM
- GPFS upgrade today
- redundancy data link might be done today
- Tomorrow: DAQ SW upgrade for LPD (Is still at KARABO 2.1.16.4)
CAS
- Long discussion happened on what the word "mandatory" means in conjunction with the most recent KARABO release
- CAS will look into the specific problems in SPB and FXE that have been brought up
- H. Santos discussed the scan tool with S. Brockhauser on Saturday
|