Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 129
Entry time: 11 Apr 2017, 12:51
|
Author: |
Tobias Haas |
Location: |
General |
Severity: |
Information |
Subject: |
Status after 0930 meeting |
|
|
Tunnel Open.
Mirrors:
Status:
- Vacuum on M2 should be good enough to switch on ion pumps
- Surveying work going on
Vacuum Loop:
Status:
- Several vacuum sections successfully tested in XTD9 yesterday
- Tests need to proceed in XTD2 today
- The protection switch on the ion pumps cannot be actuated remotely
- Loop needs an update for the XGM
- XGM was in the vacuum interlock overnight. Will be taken out during the day but should be put back at the end of the day
- Interlock of High Voltage with vacuum in XGM not working yet
- V0 valve needs to be exercised in collaboration with DESY
EPS Loop:
Status:
- The terminal exchanged for the FEL imager was not the broken one. Another terminal needs to be exchanged today
- The MCP needs to be moved out of the beam manually. This will be checked using the EPS switch. For this the EPS loop is needed
Motion Loop:
Status:
- An improved fix for the motors not stopping was deployed yesterday
- The loop needs to be reconfigured to replace the SRA motors
- One broken motor was exchanged on the mirror chambers and needs to be tested
Imagers
Status:
- All motion tests in XTD2 done. Now continue in XTD9
- Photonics camera driver still not working but not critical for tunnel closure (there is also a workaround by the name of ebus player)
- EPS switch on FEL imager needs testing after terminal replacement
Karabo:
Status:
- New version with TCP was deployed. Experience overnight is good
Tasks for today:
Note: Loop reconfiguration and updates of Karabo to be done in the morning. Testing can resume after lunch. Status updates should please be recorded in the log
- Reconfigure vacuum, motion loop (updates for XGM interlock, SRA motors)
- Replace broken terminal in EPS loop for FEL imager
- Move MCP out of the beam manually and check using EPS
- Continue systematic test of the vacuum components (J. Eidam, V. Bondar)
- Test EPS switch on FEL imager after terminal exchange (A. Koch and W. Ehsan)
- Monitor stability and responsiveness of GUI Server and Log Servers (A. Silenzi)
- Set up monitoring of temperatures and pressures overnight (A. Silenzi)
- Test V0 and absorber
Tasks for tomorrow:
- Tunnels closed
- All loops should run stable
- No or only minimal interference with Karabo
- Continue tests from remote and check stability and robustness of systems
Other topics
- Tunnels open over the Easter weekend and also during the day on Tuesday 18 April
- There will be one more standup 09:30 meeting tomorrow (Wednesday)
- There will be a SASE Readiness Meeting at 09:00 on Thursday
|