SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 391
Entry time: 27 Sep 2017, 10:11
|
Author: |
Monica Aresté |
Location: |
General |
Severity: |
Information |
Subject: |
Status and plans after SASE1/SASE3 Readiness meeting |
|
|
General
- T. Tschentscher inform about Management Board priorities for the October shut down:
- Management Board Priority 1 after the Oct shutdown will be the characterization for SASE1 performance. Any still necessary development for this (MCP, HIrex operation; two-way functional DOOCS-Karabo interface and data exchange; etc.) should get highest priority during the shutdown period. It would be good to achieve substantial progress with the DOOCS-Karabo interface before the MAC meeting to avoid general bashing of our controls. The instruments will provide a detailed list to permit support groups (ITDM, CAS, AE) to plan resources.
- Priority 2: SASE3 completion. It is expected that the machine will anyway be able to reach lasing at SASE3, but this has lower priority at present.
SASE1 Instruments
- SPB :
- No major issues to report
- FXE:
- In the next days FXE will work in the commissioning of Gothard & LPD in parallel operation to be ready to test with beam on Saturday.
Electronics
- MPS Interlock for SPB already switched on.
- No further issues to report.
ITDM
- Users have no access to on-line DAQ. They can use off-line cluster, the transfer is 5 min. after the end of the run.
- Out of the shift scientist should work with off-line cluster.
Safety
- There is a new procedure for tunnel access. Accelerator areas will have to be measured by Safety group before tunnel access release.
|