SASE1 Status and SASE3 Readiness
Technical integration and coordination
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther
Not logged in
List
|
Find
|
Login
|
Help
Message ID:
530
Entry time:
04 Jun 2018, 10:46
Author:
Adriano Violante
Location:
General
Severity:
Information
Subject:
Status report after dispatch meeting 09.30
SCS
List with the problems encountered so far during the end to end test was sent to AE. Bernard will get the info and eventually inform EET if problems with cables are found.
SQS
Elmo motors for KB system were ocnfigured and are being moved right now. If problems arise AE will be contacted.
It was not possible to control the turbo pump controllers via PLC. Bernard will have a look. In general also tirbo pump cables can and will be checked with the test box.
Loop 2 is being prepared including the MC2 motors. Should be ready by tomorrow.
SQS would like to start setting up the digitizers environment in Karabo. uTCA crates can be used on the HW side. AE acan support that.
AE
XTD6 VAC loop is being patched. Small problems with the cabling of the CRL occured but solved.
XRD
XTD6 components being cabled. 2 Imagers still need to get the EPS signals. in 1/2 weeks ready for local tests.
ITDM
One IBM storage server failed. Reasons not clear. No impact on the performance of the system.
CAS
This Week VAC loop in XTD 6 will work.
For the MOV 2 loop still EPLAN exports are needed.
MOV1/MOV2 interfaces have to be defined.