Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 530     Entry time: 04 Jun 2018, 10:46
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 09.30 

SCS

  • List with the problems encountered so far during the end to end test was sent to AE. Bernard will get the info and eventually inform EET if problems with cables are found.

SQS

  • Elmo motors for KB system were ocnfigured and are being moved right now. If problems arise AE will be contacted.
  • It was not possible to control the turbo pump controllers via PLC. Bernard will have a look. In general also tirbo pump cables can and will be checked with the test box.
  • Loop 2 is being prepared including the MC2 motors. Should be ready by tomorrow.
  • SQS would like to start setting up the digitizers environment in Karabo. uTCA crates can be used on the HW side. AE acan support that.

AE

  • XTD6 VAC loop is being patched. Small problems with the cabling of the CRL occured but solved. 

XRD

  • XTD6 components being cabled. 2 Imagers still need to get the EPS signals. in 1/2 weeks ready for local tests.

ITDM

  • One IBM storage server failed. Reasons not clear. No impact on the performance of the system.

CAS

  • This Week VAC loop in XTD 6 will work.
  • For the MOV 2 loop still  EPLAN exports are needed.
  • MOV1/MOV2 interfaces have to be defined.