Tunnel Open.

Vacuum Loop:

Status:

  • Communication problem with Ion pump controllers is fixed after adjusting controller settings
  • Loop is now down to allow inclusion of XGM

EPS Loop:

Status:

  • Temperature sensors return reasonable values after EPS loop fix
  • EPS to MPS interface is working but fiber to central desy interface still lacking

Motion Loop:

Status:

  • Should be up for testing PBLMs and Imagers

Imagers

Status:

  • Test of FEL imager ok, but hampered by occasional slow response of the system
  • SR Imager needs work on the driver

Tasks for today:

  • Include XGM in Vacuum loop (N. Jardon, M. Planas, T. Matsopoulos, V. Bondar)
  • Test updated MC2 lib with PBLM in the tunnels (N. Gerasimova, M. Jidda)
  • Work on camera driver for SR imager (A. Koch and W. Ehsan)
  • Test motion system of the imagers in the tunnels (A. Koch and W. Ehsan)
  • Monitor stability and responsiveness of GUI Server and Log Servers
  • Set up monitoring of temperatures and pressures overnight
  • Push DESY to get fiber connection to MPS (P. Gessler)

Tasks for tomorrow:

  • Terminals need to be added and firmware adjustments made in motion loop (take loop down as early as possible for one hour)
  • Test EPS inputs to MPS system with DESY people
  • Power down crate 1.15 for grounding. Could take longer than one day

Other topics

  • N. Jardon needs complete info of motor names in rack 1.18