SPB/SFX:
-
Preparation for the mirror installation were ongoing as planned.
-
The Karabo and server update went smooth, but scenes were broken a bit more then anticipated so we are still testing on that part.
-
ITDM was working on DAQ update and Jola checked out the detector with the new Karabo successfully.
FXE:
- did not attend / did not send any report
Vacuum:
Diagnostics:
- final checklist tour today 11h (because XTD10 closes tuesday), remove material
- MCP: installed webcam, some trigger issue with MCP-CAM-BEAMVIEW
- manipulator motors unstable
- KMONO: found some wrong motion directions, urgent work ongoing today to correct this, AE support needed
- PES: still no eplan available (laid some vacuum cables but of course unconnected)
- consequence: further progress on PES Beckhoff system only in April
- positive news: non-Beckhoff controls (HV, detector signals) operational !
- IMAGERS: The imagers in motion loop 1 are operational for first lasing.
- Some minor rework is planned until tunnel closure: default parameters, EPS, trigger in some cases
Laser:
- SASE1 PP-laser commissioning: progress is according to plan.
- SASE 2 and 3 laser safety and access control installations are in time for start of laser table installations in all laser hutches at beginning of April.
Detectors:
- LPD is waiting for DAQ-test with new Karabo
- DAQ-test for AGIPD is ongoing and okay so far
- Some issues were found, but they are not considered critical for the operation
AdvancedElectronics:
- Machine trigger is back to 10Hz, should again stay at 10Hz "forever", let's see...
- PLCs have been updated in SASE3 tunnels, and many tests are ongoing, with little time left
- Gas attenuator has an issue, AE is working on it, but it should not be a showstopper
- XTD2: Some issues with the CRLs, but first local test has to be done, then remote-control test can be done using Karabo
- MC2-based motors for synchronized movement of the mirrors are being done. Next week a test with the real nano-KB-system with fake mirrors will be done
- Jan found some issues in the SASE3 kMono, and is working on them
ITDM:
- Testing DAQ with new Karabo release, so far so good...
- DAQ for LPD is being deployed
- By the end of CW 5 the DAQ for SASE3 tunnels will be deployed
- Meeting with the laser group to check requirements for data acquisition
- Broken Linecard should have been replaced on the 26.1.
- Paths to Online- & Offline-data folders have been given the same pathname
- Update/switch for the gateway to the control network will happen in CW 5
CAS:
- This week we have been prioritizing: SASE1, SASE3 & SPB (Karabo 2.2.1) Deployment.
- We also have been working internally to speedUp the Karabo 2.2.2 tests and releases. This version will have, mainly, GUI improvements.
- We also have been discussing XGM requirements and tests. We will perform more XGM-TraindID tests, but the final statement can be done only after tests again real beam.
- FXE provided a "next steps list": Digitizer, OGT1_BIU, beam-position feedback
- Sergey and Hamed are working and prioritizing Digitizer implementation
|