Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 468     Entry time: 05 Feb 2018, 13:18
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 09.30 

SPB

- MIrrors installation (2 horizontal mirrors) in D.02 has started 

 -Synch motion of mirrors will be tested with fake mirrors in D.09 as soon as the control is ready.

SASE3 - CYoungman

- After SASE3 tunnels were closed it was discovered that was not pobbile to set values of the massflow (GAT loop). This required a remote intervention (firmware) that was supposed to be fast and easy  but it was not, and this required work until friday evening. Current status is: The gas attenuator secion closed and in static vacuum since the shutdown of a turbo pump was required. The system is in asafe status.The issues are being analized and solved with experts right now.

-It is important to establish a procedure to set priorities for ZZ access. The issue will be brought up in the PSO meeting

ITDM

 

-AGIPD p[roject is OK. Jolanta will start taking data already today

 