SPB
- MIrrors installation (2 horizontal mirrors) in D.02 has started
-Synch motion of mirrors will be tested with fake mirrors in D.09 as soon as the control is ready.
SASE3 - CYoungman
- After SASE3 tunnels were closed it was discovered that was not pobbile to set values of the massflow (GAT loop). This required a remote intervention (firmware) that was supposed to be fast and easy but it was not, and this required work until friday evening. Current status is: The gas attenuator secion closed and in static vacuum since the shutdown of a turbo pump was required. The system is in asafe status.The issues are being analized and solved with experts right now.
-It is important to establish a procedure to set priorities for ZZ access. The issue will be brought up in the PSO meeting
ITDM
-AGIPD p[roject is OK. Jolanta will start taking data already today
|