Message ID: 52     Entry time: 24 Feb 2017, 15:15
Author: Martin Dommach 
Location: XTD9 
Severity: Information 
Subject: work on FXE distribution mirror chamber 

Dear all,

on Monday, 27th in the morning we will start with preparation work for the mirror installation in XTD9.

The mirror chamber (VS10130) will be vented and opened. This will affect:

V10270G and V10280G: they will be closed and disconnected

P10410I and P10420I: C10902I will be switched to "local" mode and the HV of the pumps will be switched off.

The work will take at least until Friday, March 3rd.

 