Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 302     Entry time: 27 Jun 2017, 10:26
Author: Gerd Wellenreuther 
Location: General 
Severity: Information 
Subject: Tunnel access schedule updated 

Dear all,

according to Dirk Nölle access to XTD4 during the shutdown will be extended until Thursday.

Link to Tunnel Access Schedule

Cheers, Gerd

ELOG V3.1.4-7c3fd00