SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 426
Entry time: 29 Nov 2017, 09:56
|
Author: |
Adriano Violante |
Location: |
General |
Severity: |
Information |
Subject: |
Status after 9.30 dispatch meeting |
|
|
General
- Preparation for the user's run starting tomorrow (until 7:00 Tuesday morning)
Instruments
- FXE:
- On Monday night the DAQ seemed to be slow. This problem was caused by a misconfiguration in the DAQ which could be solved by ITDM once they were informed. In general both the Configuration understanding by the users and the communication with ITDM has to improve.
- The Gotthard detector could not be used. The Greateyes detector is being used now and works properly.
- PP laser is now synchronized but not commissioned yet. This is going on now (crucial point is the pulse width measure). It is not yet clear whether the PP laser will be used in the next users run.
- SPB
- AGIPD was moved 5 m downstream for the next experiments. Vacuum is OK. Alignment checked with the ALAS, will be checked with beam probably today evening.
- A change in the DAQ configuration has to be (is being) done today (CAS/ITDM)
ITDM
- Upgrade switches today at 9:00 will be checked if there were problems right after this meeting.
|