Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 187     Entry time: 28 Apr 2017, 13:08
Author: Tobias Haas 
Location: General 
Severity: Information 
Subject: Status and plans after SASE1 Readiness Meeting 

 Tunnel Status (T. Haas):

  • Tunnels XTD2/4/10 were interlocked yesterday afternoon
  • Beam is already going through the T2 and T4 beam lines to T4D
  • XTD9 remains open until approximately 15 May

Vacuum (J. Eidam, R. Villanueva):

  • The interlock in the gas section was tested successfully in XTD9. The interlock does currently not include the gas injection. This still needs setting up and testing
  • Systematic testing of ion pumps and interlocks is ongoing in XTD9 but needs to continue next week
  • The system generally works reliably
  • However, there was an incident this week in which the gas sections in XTD2 and XTD9 went completely off. The reason is still not understood

Mirrors and PBLMs (H. Sinn):

  • All three mirrors in the SASE1 beam line in XTD2/9 are installed and pumped
  • N. Gerassimova installed PMTs in XTD2 yesterday and set up the cameras of the PBLMs
  • The problem with injected properties disappearing was identified on the Karabo side and fixed. The fix still needs to be deployed
  • The motors of the PBLMs are still not functioning completely. 
  • The read out rate of the cameras is ok (of the order of 10Hz or better)

Imagers (A. Koch):

  • Imagers in XTD2 and XTD9 are ready for beam
  • Work continues on improvements
  • Read out rate is ok, but the latency is sometimes high and needs to be unterstood

XGM (J. Grünert):

  • The gas on the XGM in XTD2 was changed at the request of K. Tiedtke from Ar to Ne
  • Tests were done with the remote control of the gas system. This is now fully functional
  • The HV/Vacuum interlock is not operational yet
  • Otherwise the XGM is ready accept beam. Next week software tests should be performed with the readout

FXE (A. Galler):

  • Currently commissioning loop 1. There is still a problem reading out encoders. It appears that this is a firmware issue. TF is working on this.

SPB (B Weinhausen):

  • Currently commissioning the SPB tunnel components. The encoders have the same problem as the one reported by FXE
  • I broken terminal required changing

PLC (T. Freyermuth):

  • CRL in XTD2 was integrated into the PLC motion loop yesterday during the access.
  • A first version of the EPS logic was agreed upon and implemented. Details to be discussed again with DESY next week

Karabo (A. Silenzi):

  • ITDM provided an additional control server
  • A redeployment of Karabo is necessary and will be done later today (users will need to re-connect afterwards) 
  • The problems previously observed with the GUI server have not re-occured. 

Plans for next week:

  • Consolidate vacuum in XTD2 so that V0 can be reliably opened when first beam should be transported
  • Finish work in XTD2, in particular PBLMs and instrument components
  • Finish systematic tests of ion pumps in XTD2
  • Deploy fix for Renishaw encoders in firmware

Other topics:

  • We continue the 09:30 meetings next week until further notice

 

 