SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 187
Entry time: 28 Apr 2017, 13:08
|
Author: |
Tobias Haas |
Location: |
General |
Severity: |
Information |
Subject: |
Status and plans after SASE1 Readiness Meeting |
|
|
Tunnel Status (T. Haas):
- Tunnels XTD2/4/10 were interlocked yesterday afternoon
- Beam is already going through the T2 and T4 beam lines to T4D
- XTD9 remains open until approximately 15 May
Vacuum (J. Eidam, R. Villanueva):
- The interlock in the gas section was tested successfully in XTD9. The interlock does currently not include the gas injection. This still needs setting up and testing
- Systematic testing of ion pumps and interlocks is ongoing in XTD9 but needs to continue next week
- The system generally works reliably
- However, there was an incident this week in which the gas sections in XTD2 and XTD9 went completely off. The reason is still not understood
Mirrors and PBLMs (H. Sinn):
- All three mirrors in the SASE1 beam line in XTD2/9 are installed and pumped
- N. Gerassimova installed PMTs in XTD2 yesterday and set up the cameras of the PBLMs
- The problem with injected properties disappearing was identified on the Karabo side and fixed. The fix still needs to be deployed
- The motors of the PBLMs are still not functioning completely.
- The read out rate of the cameras is ok (of the order of 10Hz or better)
Imagers (A. Koch):
- Imagers in XTD2 and XTD9 are ready for beam
- Work continues on improvements
- Read out rate is ok, but the latency is sometimes high and needs to be unterstood
XGM (J. Grünert):
- The gas on the XGM in XTD2 was changed at the request of K. Tiedtke from Ar to Ne
- Tests were done with the remote control of the gas system. This is now fully functional
- The HV/Vacuum interlock is not operational yet
- Otherwise the XGM is ready accept beam. Next week software tests should be performed with the readout
FXE (A. Galler):
- Currently commissioning loop 1. There is still a problem reading out encoders. It appears that this is a firmware issue. TF is working on this.
SPB (B Weinhausen):
- Currently commissioning the SPB tunnel components. The encoders have the same problem as the one reported by FXE
- I broken terminal required changing
PLC (T. Freyermuth):
- CRL in XTD2 was integrated into the PLC motion loop yesterday during the access.
- A first version of the EPS logic was agreed upon and implemented. Details to be discussed again with DESY next week
Karabo (A. Silenzi):
- ITDM provided an additional control server
- A redeployment of Karabo is necessary and will be done later today (users will need to re-connect afterwards)
- The problems previously observed with the GUI server have not re-occured.
Plans for next week:
- Consolidate vacuum in XTD2 so that V0 can be reliably opened when first beam should be transported
- Finish work in XTD2, in particular PBLMs and instrument components
- Finish systematic tests of ion pumps in XTD2
- Deploy fix for Renishaw encoders in firmware
Other topics:
- We continue the 09:30 meetings next week until further notice
|