Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 591     Entry time: 14 Jan 2019, 12:58
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 09.30 

SPB/SFX

  • D.23 Cabling ongoing. Minor problems concerning Chicane filling. 10 cables need to be routed through another chicane.  Being sorted out with EET.
  • Silicon oil pipe has been fixed and is undergoing pressure tests. So far successful.
  • Issue concerning tripping power plugs in D.09. Needs to be investigated (SPB/SFX <=> TS)

FXE

SQS

  • This week the AQS chamber will be removed. 
  • Power cut of the primary power line in the rackroom will occur to allow fixing of the emergency power off system (as agreed between TS ans MM last week). TBaumann will agree the time with TS. Note from MTeichmann: Even though 1 hour was foreseen, for  SCS it took 5 hours. Be careful and plan accordingly.

SCS

MID

  • Commissioning ongoing. The homing function of motors in the optics hutch will be tested this week.
  • VAC system in the optics hutch operational. Some issues with the control of the ion pumps need support from AE (1 hour). ==> Tomorrow, 14, Marjan.

HED

  • Mono in XTD6 testing ongoing. Piezo and encorders need some adapter. 
  • Hi res mono vessel is being opened and will be closed again at the end of the week
  • Si- mono vessel does not need to be opened. 
  • Commissioning of the OPT hutch starting tomorrow (Loop 1 and 2)

OPT Lasers

XRO

​​XPD

  • All FEL imagers have been replaced (now with Al coating reducing reflections).
  • XTD2 XGM gauge has been replaced.

​​VAC

AE

  • VAC loops in the tunnels are being coordinated with affected groups
  • Motion 2 in SASE2 loop needs to be updated. Being coordinated with AKoch.
  • Test with the 3 triggers coming from the machine for the 3 SASEs are ongoing.

EET

ITDM

DET

CAS

AoB

  • Fridays OP/Readiness meeting is not taking place anymore.
  • A new Operation meeting is being set up.
  • TT will propose a time slot to put a replacement for the Op/Readiness meeting where technical issues and information spreading after the dispatch meetings can follow.
  • Issues concerning the handling of the maintenance day on monday has been raised by the groups. Has to be seen how to cope with that.