Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 568     Entry time: 08 Oct 2018, 10:37
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 09.30 

SPB

  • Ready for users.

  • DAQ tests to be done on the SPB side.

  • MPS definitions being defined.

FXE

SQS

  • Loop 7-10-14 are running. 13 and 12 to come.
  • Crates for the loops 1/4/5 have been/are being modified.
  • Interlocks definition update. NJ, BB and SQS are clarifying the requirements.
  • Interlocks not working for the loops 3 and 5. Info sent to AE. Being worked on.
  • Still no beam available

SCS

MID

  • No issues.

HED

  • Beam in XTD6
  • Some CRLs arms are deactivated to avoid accidentally focusing on the shutter.

XPD

VAC

AE

  • MPS update for SPB is ready and has to be done. This includes the interlock definition for the detector's z motion.==> being reviewed by SPB.\
  • SASE3 EPS loop being updated to comply with the new D3 directives. Today a test with Z.Ansari will be performed.

ITDM

CAS

  • To preventy the copy of entire projects with all the relative subprojects and additional problems, the GUI servers in SASE2 will be updated. Only 1 server is running at the moment.
  • The milestones of the SASE2 Technical commissionig Task Force headed by CY have been achieved. Starting from today CY is no longer taking care of the SASE2 tunnel activities planning and coordination. It has to be discussed in the Friday meeting how to go on, since the planning and coordination of the shutdown activities is needed.