Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 455     Entry time: 22 Jan 2018, 10:36
Author: Gerd Wellenreuther 
Location: General 
Severity: Information 
Subject: Status and plans after Readiness Meeting 

SPB/SFX:

  • 2nd AGIPD intervention will be finished today.
  • SE worked on a reliable procedure for nozzle exchange and trained the instrument scientists
  • SmarAct motors are in error, Mahadi / AE is informed. These motors are needed for user operation / commissioning.
  • loop 5 update still outstanding
  • Karabo update for loop 1-4 was done, seems to be ok. Full update is planned for beginning of next week.

FXE:

  • JJ X-rays finalized installation of the last components at FXE:
    • Diamond grating (in XTD9)
    • Spectrum analyzers
    • Timing tool
    • repositioning of the sample manipulator and working on better cabling
    • minor work on cables of FXE CRL to allow full movement along the beam direction
    • Johann spectrometer
  • FXE got the information from CAS that the Karabo update was successful and it’s ready for testing
  • FXE decided not not pursue the further commissioning of the new equipment due to the emergency power off tests
  • FXE is working on a more universal sample environment allowing faster and more reliable changes from solid to liquid experiments.

Vacuum:

SASE1:

  • vacuum system closed,
  • PLC loop update done,
  • ready for restart

SASE2:

  • XTD1 all devices in the tunnel and aligned

SASE3:

  • Soft Mono chamber closed yesterday, pumpdown, leaktest later today
  • GasAttenuator comissioning ongoing
  • Karabo scene developement

XPD:

  • SASE3 MCP detector technical commissioning:
    • HV tested OK (MPOD operational), today ADC/signal test
    • motors: rewiring done --> correct directions and limit switches
    • motors were intermediately ok, but are not stable (now there are again issues)
    • several PLC / karabo issues were sorted out, ok
  • SASE3 XGM:
    • test with Kr gas supply yesterday/today
    • test with gas plus HV
  • SASE3 PES:
    • ordered grounding works (cabling) to be done similar to what was done for the XGM
  • SASE2 XGM:
    • vacuum incident: vacuum operation of the XGM in XTD6 was unauthorized interrupted for some time, The rack had been powered down without prior information to XPD.
    • Reminder to all that rack near the XGMs shall be powered down only after informing and coordinating with XPD.

Laser:

 

  • SASE1 PP-laser commissioning and upgrade is continuing according to our plan.
  • Karabo upgrade to 2.2.1 was rather uneventful and successful.
  • Hutch readiness milestones for laser hutches in SASE 3 and 2 seem to consolidate:  15. March. If this continues to hold, we will start our Phase II installation of PP-lasers in E.04 and A.04 with laser tables at the start of April. Laser tables for the ILHs will be installed at the same time.

Detectors: Did not attend.

Advanced Electronics:

  • Replacement of the microTCA for the PES was done
  • microTCA update of the timing system was done
  • local test of the CRL can be done after the cables and the hardware have been fixed by the Vacuum group
  • All loops of FXE updated (firmware etc.)

ITDM:

  • Network ports for SASE2 in the racks have been fixed
  • DAQ in SASE1 needs fixing of hardware, foreseen for CW 4
  • Test of DAQ with new Karabo release is on its way, should be done by Wednesday 24.1.

CAS:

 

  • Karabo 2.2.1 has been deployed on FXE, LAS-LAB, LAS-PPL, and 3 SPB loops without any real problems
  • migration continues next week on SPB
  • BKR will be equiped with a 3rd Karabo Control PCs (we work with Tim already on it)

 