SPB/SFX:
- 2nd AGIPD intervention will be finished today.
- SE worked on a reliable procedure for nozzle exchange and trained the instrument scientists
- SmarAct motors are in error, Mahadi / AE is informed. These motors are needed for user operation / commissioning.
- loop 5 update still outstanding
- Karabo update for loop 1-4 was done, seems to be ok. Full update is planned for beginning of next week.
FXE:
- JJ X-rays finalized installation of the last components at FXE:
- Diamond grating (in XTD9)
- Spectrum analyzers
- Timing tool
- repositioning of the sample manipulator and working on better cabling
- minor work on cables of FXE CRL to allow full movement along the beam direction
- Johann spectrometer
- FXE got the information from CAS that the Karabo update was successful and it’s ready for testing
- FXE decided not not pursue the further commissioning of the new equipment due to the emergency power off tests
- FXE is working on a more universal sample environment allowing faster and more reliable changes from solid to liquid experiments.
Vacuum:
SASE1:
- vacuum system closed,
- PLC loop update done,
- ready for restart
SASE2:
- XTD1 all devices in the tunnel and aligned
SASE3:
- Soft Mono chamber closed yesterday, pumpdown, leaktest later today
- GasAttenuator comissioning ongoing
- Karabo scene developement
XPD:
- SASE3 MCP detector technical commissioning:
- HV tested OK (MPOD operational), today ADC/signal test
- motors: rewiring done --> correct directions and limit switches
- motors were intermediately ok, but are not stable (now there are again issues)
- several PLC / karabo issues were sorted out, ok
- SASE3 XGM:
- test with Kr gas supply yesterday/today
- test with gas plus HV
- SASE3 PES:
- ordered grounding works (cabling) to be done similar to what was done for the XGM
- SASE2 XGM:
- vacuum incident: vacuum operation of the XGM in XTD6 was unauthorized interrupted for some time, The rack had been powered down without prior information to XPD.
- Reminder to all that rack near the XGMs shall be powered down only after informing and coordinating with XPD.
Laser:
- SASE1 PP-laser commissioning and upgrade is continuing according to our plan.
- Karabo upgrade to 2.2.1 was rather uneventful and successful.
- Hutch readiness milestones for laser hutches in SASE 3 and 2 seem to consolidate: 15. March. If this continues to hold, we will start our Phase II installation of PP-lasers in E.04 and A.04 with laser tables at the start of April. Laser tables for the ILHs will be installed at the same time.
Detectors: Did not attend.
Advanced Electronics:
- Replacement of the microTCA for the PES was done
- microTCA update of the timing system was done
- local test of the CRL can be done after the cables and the hardware have been fixed by the Vacuum group
- All loops of FXE updated (firmware etc.)
ITDM:
- Network ports for SASE2 in the racks have been fixed
- DAQ in SASE1 needs fixing of hardware, foreseen for CW 4
- Test of DAQ with new Karabo release is on its way, should be done by Wednesday 24.1.
CAS:
- Karabo 2.2.1 has been deployed on FXE, LAS-LAB, LAS-PPL, and 3 SPB loops without any real problems
- migration continues next week on SPB
- BKR will be equiped with a 3rd Karabo Control PCs (we work with Tim already on it)
|