General
- First users have done experiments - despite the current problems it appears as if everybody was able to take some data for future publications.
Short Report from SASE1 Instruments
- SPB (A. Mancuso):
- Beam was lost due to incident with electron beam hitting & damaging components downstream of the northern dump.
- Currently only single bunch operation
- Lots of work to be done in Oct. shutdown, Adrian will provide a list to Thomas Tschentscher
- FXE (T. Tschentscher):
- Problem with the Tangerine-laser affects PP-experiment ==> to be fixed on Tuesday
- Consider to switch to oscillator only until then ==> lower repetition rate, lower OL pulse energy
- Next experiments require Gotthard & LPD in parallel operation ==> merge Gotthard & LPD to same run control next week before user run.
- Today, test with DAQ and Gotthard was successful, but Gotthard has never seen XFEL X-rays so far. ==> Test with beam could happen potentially Monday night (instead of user experiment)
Tunnels (M. Dommach, J. Grünert):
- SASE1:
- Few issues with XGM, have been or are being solved.
- It was suggested to put the Hirex-grating into the beam while FXE is taking beam to measure / commission parasitically. But it appears next week neither Naresh nor Jan will be available.
- SASE3:
- Due to the electron beam incident the first vacuum sections have been vented, there is most probably a hole in the V0, but only Rad. Safety to access the tunnels right now. ZZ/Access by anyone else only after clearance through SRP - working there is probably only possible in Octorb
- Beam did hit the beam pipe apparently just upstream of the transmissive imager. Imager and further (vacuum) electronics seems to have been damaged in the upstream part of XTD10.
- Due to this incident, it should be reconsidered if dosimeters are required in XTD10, too. SRP did unfortunately not participate, and thus was not able to comment.
Laser
- Working still on improving the laser
- Issue regarding motors coming back to their position is most probably a firmware/options issue
Detectors
- AGIPD:
- According to Yolanta "operates better than expected"
- LPD
- Also operates better than expected
- Configuration of LPD is getting messed up by people working in parallel / unclear status of the detectors Gotthard & LPD ==> There should be a responsible for the detector, who is present in the control room and can allow remote access to work with the detectors / run configuration. ==> These steps should be well-documented in the FXE-Logbook.
- K. Wrona: Next week will be better with just one run controller.
Electronics (P. Gessler)
- There is an issue with some motors & encoder @ SPB.
- AE will finish the work on the last loops in SASE1.
- WP79 needed & got support by AE.
ITDM (K. Wrona)
- DAQ for the tunnels is setup. ==> XGM-run control for the tunnel is to be tried.
- Slow data: It is an issue how and how fast to store slow data (lots of properties which do not change).
Software
- FXE:
- Still daily meetings, prepare LPD & Gotthard
- Working on GreatEyes, too
- SPB
- Configure slow-data cameras
- Laser project is running in CAS
- SASE3:
- C. Youngman is the CAS-responsible, should collect requirements to compile master equipment list for SASE3 ==> to be compared against MEL SASE1 to identify additional work required.
- SASE1:
- Loops & Karabo will be updated together.
October Shutdown:
- SASE1
- No major items here currently, focus is on SASE3 / XTD10.
- SASE3
- First priority is to get all items required for first lasing up & running ==> Vacuum system including anything up to the absorber.
- CAS is starting to set up Karabo and all controls.
- ITDM will also start to work, but does not require access to the tunnel.
- C. Youngman to generate MEL from input from the groups ==> invites to a meeting if necessary.
- Eplan for PES will not be available on time ==> has to be pumped in a provisional fashion.
|