Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther, Page 29 of 29  Not logged in ELOG logo
Entry   Minutes of the Technical integration meeting 13.02.19 , posted by Adriano Violante on 13 Feb 2019, 10:59 
SPB/SFX


CSS component commissioning. RBean is discussing with AE. Concept and implementation being finalized.
Loop 14 (Jungfrau) is
needed for next week to start the commissioning. IT Cables have been accepted after new measurements. Loop can be switched on.
Issue about parallel
Entry   MInutes of the dispatch meeting 09.30, posted by Adriano Violante on 11 Feb 2019, 09:59 
SPB/SFX


Beam is back on Wed. night.
IT cables in D.23 were re-measured on friday. Probemessung was OK. Waiting for the complete set
of measurements. PSPO pushes the company.
Updates+testing of the AGIPD with the CFEL experts is ongoing.
interlock definitions
Entry   Report after dispatch meeting 09.00, posted by Adriano Violante on 08 Feb 2019, 10:42 
SPB/SFX


IT cables in D.23 were re-measured yesterday. Waiting for the measurements. PSPO pushes the company.


FXE

​SQS
Entry   Minutes of the Technical integration meeting 06.02.19 , posted by Adriano Violante on 06 Feb 2019, 11:13 
SPB/SFX


AGIPD commissioning and tests. ==> intervention on the wings is ongoing.
CSS component commissioning. RBean is discussing
with AE. By the end of the week the changes could be implemented.
Loop 14 (Jungfrau) is needed for next week to start the commissioning. AE
Entry   Report after dispatch meeting 09.30, posted by Adriano Violante on 04 Feb 2019, 10:17 
SPB/SFX


Waiting for the loop 12 to be running to start the commissioning of Jungfrau. Some cables for th fus boxes missing. Also IT cables are
being mesaured.
CSS motion. Discussions ongoing to fix it.


FXE
Entry   Report after dispatch meeting 09.00, posted by Adriano Violante on 01 Feb 2019, 12:49 
SPB/SFX


Open AGIPD wing. Next 3 days are needed for fixing purposes.


FXE

​SQS
Entry   Minutes of the Technical integration meeting 30.01.19 , posted by Adriano Violante on 30 Jan 2019, 11:26 
SPB/SFX


Planned for the next 2 weeks

AGIPD commissioning and tests. DET group heavily involved.
Screens are being installed
and commisisoned in the hutch.
CSS component commissioning. AE involved and informed.
Loop 14 (Jungfrau) is needed for next week
ELOG V3.1.4-7c3fd00