Group Selection Page HELP Controls Group Data Analysis Group ITDM WP76 DET Vacuum EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Operation PSPO XO TS Migrated2Zulip
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther, Page 29 of 30  Not logged in ELOG logo
Entry   Minutes of the Technical integration meeting 08.05.19 , posted by Adriano Violante on 08 May 2019, 10:10 Technical_Integration_Meeting_07.05.2019_-_Copy.pptx
SPB/SFX


IRDa commissioning ongoing. 
CSS. Limit switches re cabling is ongoing. For the next run the old configuration will
still be used. RB and MS will meet to make sure the system can be safely (from the component point of view) operated. ==> Solved.
Comment
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 06 May 2019, 10:20 
SPB/SFX


IRDa commissioning ongoing. 
For this week AGIPD works and re commissioning of the nanometer mirrors will be perfermed.
It is possible that support from AE will be required.
CSS. Limit switches re cabling is ongoing. For the next run the old configuration will
Entry   Report after dispatch meeting 9:00, posted by Adriano Violante on 03 May 2019, 14:07 
SPB/SFX


IRDa commissioning ongoing. First images have been taken with the Jungfrau detector. Possible to record using 7 to 8 memory cells,
after that there are issues. CAS is having a look. 
CRL motors being tested. --> issue with a CRL motor is being addressed (connector
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 29 Apr 2019, 10:04 
SPB/SFX


IRDa commissioning ongoing. Focus (<5um) in the second interaction region has been achieved.
CRL motors being tested.
--> issue with a CRL motor is being addressed (connector issue). 
AE needs to know when Loop 9 and 10 are expected to run. SPB to check.
Jungfrau
Entry   Report after dispatch meeting 09.00, posted by Adriano Violante on 26 Apr 2019, 12:28 
SPB/SFX


IRD commissioning ongoing.
CRL motors being tested. --> Mechanical issue with a CRL motor is being addressed.
CSS
interlock tests with AE still ongoing.
AE needs to know when Loop 9 and 10 are expected to run. SPB to check.
Jungfrau detector:
Entry   Minutes of the Technical integration meeting 24.04.19 , posted by Gerd Wellenreuther on 24 Apr 2019, 10:05 
SPB/SFX


SPB/SFX is preparing for the upcoming beamtime.
CRL motors being tested. --> Still ongoing.
CSS interlock tests
being planned for tomorrow. --> Still ongoing.
AE needs to know when Loop 9 and 10 are expected to run. SPB to check.


​FXE
Entry   Minutes of the Technical integration meeting 17.04.19 , posted by Adriano Violante on 17 Apr 2019, 11:34 
SPB/SFX


CRL motors being tested. Today BB (AE) will check the status.
CSS interlock tests being planned for tomorrow.
Jungfrau
motors -  SS (EET) fixed some cable issues. Now ok.
Julabo chiller: loop 5 has been updated (interlocks definition, setpoints...) AE+DET
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 15 Apr 2019, 09:55 
SPB/SFX


Tomorrow set up of the donwstream interaction region will start.
Jungfrau calibration pipeline has to be pushed. ITDM and
DET involved. Can be done this week.
Additional motors control bein implemented by AE.
Request presented to CAS to resume a project
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 12 Apr 2019, 10:41 
SPB/SFX


Hercules students period. During the night a pump failed and recovered after a power cycle.
5Hz mode tests were performed
and successful
CSS being commissioned. X mov elmo stage still has to be configured. Will be done probably today.
After some updates,
Entry   Minutes of the Technical integration meeting 10.04.19 , posted by Adriano Violante on 10 Apr 2019, 10:54 
SPB/SFX


CRL implementation in the hutch. Tests can start today.
CSS Test have been started. One elmo devide has to be implemented
today. Interlocks have to be tested (later).
AGIPD motion. Middle layer final tests will be done during next reconfiguration od the detector.
Julabo
Entry   Report after dispatch meeting 09.30, posted by Adriano Violante on 08 Apr 2019, 10:48 
SPB/SFX


5Hz mode tests started (SPB/SQS) and partially successful. A detailed report will be sent around. 2 cameras in SPB and digitizers in
SQS were tested. Cameras OK. Digitizers data recordin has some issues being fixed (train id related). Next week on Thursday a test with beam is foreseen.
Entry   Report after dispatch meeting 09.00, posted by Adriano Violante on 05 Apr 2019, 10:07 
SPB/SFX


5Hz mode tests started (SPB/SQS) and partially successful. A detailed report will be sent around. 2 cameras in SPB and digitizers in
SQS were tested. Cameras OK. Digitizers data recordin has some issues being fixed (train id related). Next week on Thursday a test with beam is foreseen.
Entry   Minutes of the Technical integration meeting 03.04.19 , posted by Adriano Violante on 03 Apr 2019, 10:44 
SPB/SFX


CRL implementation in the hutch. Cables at the back of the crate have been re-shuffled by EETf. VAC vessel had a leak and is being re-sealed
and pumped. If everything is fine and the vessel can be brought to the hutch the motors test can in principle start already this week.  Interaction
Entry   Report after dispatch meeting 09.30, posted by Adriano Violante on 01 Apr 2019, 10:21 
SPB/SFX


The quadrant motion system test for the AGIPD presented some issues with the limit switches. Being fixed.
Julabo chiller:
waiting for feedback from Julabo to know whether the chiller is going to be repaired on time for next users. If not, SPB/SFX are trying to borrow one from
Entry   Report after dispatch meeting 09.30, posted by Adriano Violante on 29 Mar 2019, 11:02 
SPB/SFX

FXE

​SQS
Entry   Minutes of the Technical integration meeting 27.03.19 , posted by Adriano Violante on 27 Mar 2019, 10:48 
SPB/SFX


CRL implementation in the hutch will happen in April. AE and EET involved. ==> Connectors on the beckhoff frames need to be re-shuffled
according to the newest version of the EPLAN documentation. EET will take care of that, so that the loop can be started as soon as possible.
CSS
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 25 Mar 2019, 11:38 
SPB/SFX


The Julabo chiller for the AGIPD detector broke. After intervention from TS was clear that it was not possible to fix on the fly. Users
time had to be cancelled. In generalr there are 3 solution being pushed simultaneously by SPB: Fix the existing one, buy a new one, integrate a new type
Entry   Minutes of the Technical integration meeting 20.03.19 , posted by Adriano Violante on 20 Mar 2019, 14:07 
SPB/SFX


CRL implementation in the hutch will happen in April. AE and EET involved. ==> ZA needs the documentation of the CRL. The point is
SRP to be able to evaluate the focusing properties to give beam permission after installation. TH will ask directly PVagovic. Still pending since PV is
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 18 Mar 2019, 10:04 
SPB/SFX


No major issues reported
Crates for the CRL will be installed today. Test is foreseen for next week.


FXE


Issue with the synchronization of the PP laser has been reported. This affects also SPB. The problem was found to be in the subsynch
Entry   Minutes after dispatch meeting 09.00, posted by Adriano Violante on 15 Mar 2019, 11:27 
SPB/SFX


No major issues reported
Motors in Loop 14 have been tested and problems with the motion sign and encoder were found. AE/EET
on it.


FXE
ELOG V3.1.4-7c3fd00