SPB/SFX
- are working on achieving a good focus @ 6 keV, which currently is not as good as expected.
- Digitizers are ready, have been tested by CAS ==> to be be installed / integrated probably next week
- Different GUIs were reporting varying values for STATUS on different clients / machines ==> ARound will make sure a proper description of the issue (which machines, which clients, when, ...) will be brought to the attention of the proper people @ CAS.
FXE
- The Karabo FAI went well, FXE thanks explicitly for the support received.
SQS
- The pnCCD is being set up. AE will be required to help for axes commisisoning next week. ==> this should happen today.
SCS
- MTeichmann attended, fresh from vacation, nothing to report, everything is "awesome".
MID
- Commissioning the cryomanipulator. Had to use a couple of work arounds in order to align it with the beam (travel range issues it appears).
- The AGIPD Julabo chiller failed on Saturday, it has to be sent in. Meetings this mornings should clarify what other options remain to support the user experiments as planned.
HED
- User experiment went very well.
- Currently commissioning ion pumps in the optics hutch
- Starting on Wednesday loop 6 is to be commisioned (exp. hutch components) together with AE
OPT Lasers
XRO
XPD
VAC
DET
- Question to ITDM: Did the crash of git on Saturday affect the calibration database (there were apparently issues @ FXE for 2 hours) ==> No. If there would have been problems, they would not have resolved with nobody doing anything, the system requires manual intervention. So most probably the problem was somewhere else...
AE
- SCS had a problem with the fast ADC, was fixed Friday. Did this gave further problems during the weekend ==> MTeichmann to check.
ITDM
EET
CAS
SRP
TS
AoB
|