Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 51     Entry time: 05 Jun 2019, 09:59
Author: Gerd Wellenreuther 
Location: General 
Severity: Information 
Subject: Minutes of the Technical integration meeting 05.06.2019 

FXE

SPB/SFX

  • few days of beamtime remaining, no particular issues
  • preparing for emergency power off
  • preparing shutdown activities with EEE

SCS

  • beamtime, no particular issues.
  • preparing for shutdown
  • XGM is supposed to run even despite the emergency power off ==> M. Teichmann is in contact with T. Schoen (TS)

SQS

  • beamtime, first scattering images taken using the pnCCD!
  • preparing for shutdown, in particular some cabling together with EEE

 MID

  • Integration of the LDM: Safety document is needed. ==> This is needed ASAP!!! ==> THIS IS STILL NEEDED!!!

HED

  • CAS was able to follow up regarding the request for test of triggering / pulse on demand from this Monday. HED was kind of lucky, CAS would appreciate some further notice next time...
  • Due to missing endswitches / interlock conditions, some YAG-screens have been burnt. HED would like to try to get this fixed in the tunnels and the hutches still in this shutdown by installing endswitches etc., to be negotiated with EEE
  • The bias teeth(???) used by HED are not being supplied any more, new ones are not performing ==> to be checked with other instruments / EEE, Sato-san was suggested as another expert to ask.

Optical lasers

  • everything fine, thanks for the support!

VAC

  • Requested to see the first pump + valve of SPB/SFX ==> to be clarified by VAC, SPB/SFX + EEE

XRO

XPD

DET

EEE

CAS

ITDM

SRP

  • From SBP/SFX: Currently, it is not clear what to do if one of the Pandoras goes off. This apparently happened @ FXE on the night from Sat.-Sunday, and it took 12 hours to fix it.

TS

  • From CAS: TS should not rely on email alerts to monitor the cooling of the servers running for example the email services...

AoB