Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 49
Entry time: 29 May 2019, 10:30
|
Author: |
Gerd Wellenreuther |
Location: |
General |
Severity: |
Information |
Subject: |
Minutes of the Technical integration meeting 29.05.19 |
|
|
FXE
SPB/SFX
- XTD2 attenuator appears to be damaged. ==> Request to VAC: is it possible to exchange the attenuators in the summer shutdown? LBatchelor might have spares.
- Digitizers have been installed
- Bunch number is reported to have jumped from 1 --> 150, report to be provided by SPB/SFX so CAS can investigate.
- Top priority: Testing new camera + DAQ interface along with motor positions recording @ 10Hz
SCS
- Currently running + supporting the user experiment
SQS
MID
- Integration of the LDM: Safety document is needed. ==> This is needed ASAP!!!
- Further commissioning is ongoing
HED
- Loop 6 being commissioned. ==> done
VAC
XRO
XPD
DET
EEE
- Loop priorities for HED and MID are needed.
- AE reminds everybody to contact TSchoen if power is required during the middle of June, e.g. in order to keep the vacuum running.
CAS
- Supported / tested measurements of gain curves in SASE1
- Next week: Testing of correlator
- Karabo Hotfix 2.4.2 was released, new week testing of 2.5. commences
- Progress regarding InfluxDB etc. was achieved and reported, e.g. to readiness mailing list
ITDM
SRP
TS
AoB
- No Dispatch on Friday due to the bridge day!
|