Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 37     Entry time: 29 Apr 2019, 10:04
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 09.30 

SPB/SFX

  • IRDa commissioning ongoing. Focus (<5um) in the second interaction region has been achieved.
  • CRL motors being tested. --> issue with a CRL motor is being addressed (connector issue). 
  • AE needs to know when Loop 9 and 10 are expected to run. SPB to check.
  • Jungfrau detector: first beam on the detector. Some issues (receiver had to be restarted, gain constants needed to be properly set) fixed by DET and ITDM OCDs.

FXE

SQS

  • Cameras and DAQ minor issues being fixed.
  • SQS will need to be able to switch the trigger off and connect this to the interlock system. This can be done but requires the addidtion of physical connections by AE and needs to be planned. A faster workaround will be discussed offline with PG.

SCS

  • The gender of a scroll pump and 4 detectors cables were found to be wrong. MT will ask EET for fixing.

 MID

  • The pico motors for the  monos in XTD6 are dead and need to be replaced. This is urgent and will be done this week.
  • AE is supporting MID for the integration of 3 user motors.

HED

  • Loop8 being commissioned. No big issues.

OPT Lasers

XRO

​​XPD

VAC

​​DET

  • LPD first charge injection test with emergency DAQ succesfull. Activities will be continued with the agreed LPD prio list. 
  • FXE. Karabo will be updated for the online calibration.

AE

  • During the WE an issue concerning digitizers and fast ADC was reported. Train ID was not correct. This has not happened before. A fw update solved the issue and is being deployed for all the intruments. A detailed investigation of the reasons is being done. No issue for SQS to have reliable digitizers for the next users run.

​​ITDM

​​EET

​​CAS

SRP

TS

AoB