Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 36     Entry time: 26 Apr 2019, 12:28
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Report after dispatch meeting 09.00 

SPB/SFX

  • IRD commissioning ongoing.
  • CRL motors being tested. --> Mechanical issue with a CRL motor is being addressed.
  • CSS interlock tests with AE still ongoing.
  • AE needs to know when Loop 9 and 10 are expected to run. SPB to check.
  • Jungfrau detector: calibration being finalized.

FXE

  • Loop 6 is required to drive 2 servo motors. BB will try to bring this into operation this week. NC checked the setup. ==> The loop 9 will be temporarily used. This will be updated either on Monday/Tuesday, or during beamtime. Agreed with FXE.
  • Drawers 2 and 3 have to be rebuilt by AE in order to host new ATCA crates. JE needs time plan info from FXE. 

SQS

  • AE still needs priorities for the next loops. Only Loops 15 and 16 left to be brought up. No plans yet. 
  • Export of motors config. parameters needed by AE. SQS asks CAS
  • Interlocks minor issues being fixed with AE

SCS

  • Discussion with EET ongoing concerning the installation of cables for end stations. Space problem. --> This is a long term issue, to be discussed in the other meetings, ongoing.
  • Commissioning of the quadrant motion has been completed.
  • Loop 12 (chiller) issues with some cables miswiring has been found. AE and EET to check.
  • Motors / encoder of the inlinemic component being commissioned. 

 MID

  • For Loop 9 CY is preparing a change request (naming convention for interlocks). AE involved. --> still pending
  • Loop 12 will be operable this week --> an 100V input is needed, but not readily available. --> the 100 V were needed to increase the speed of a motor. The alternative solution of using a 48V teminal and a gear box was proposed by AE and accepted by MID. 
  • Priorities for next loops needed by AE to plan the work. --> Still required.
  • Peltier being debugged by MS
  • monochromators pico motor in the tunnel is stuck and needs to be fixed. Will be done on Monday.

HED

  • Loop9 (Smaract stages) has to be brough up.  --> being done. Smaract stages being also tested
  • Next loops are 8 followed by the priority-items from loop 6. Loop8 has been started yesterday
  • Loop10 and 11 regarding PPL will be needed in June. HED to confirm. --> Feedback from MN required.
  • Limit switches (loop8?) are not operable right now due to a 24V terminal missing.

OPT Lasers

  • AE support is needed in order to bring the SCS laser up by the end of may. Mail has been sent. NJardon checks. --> Loop extended and running by the end of next week. --> will be done on 06.05.Eplan export will be ready next monday the latest.

XRO

  • Motion loop for Hirex 2 has been delayed until June -> update will be done on 11.06.

XPD

  • Issue repoeted from CAS: Fast ADC for MCP in SASE3 duplicates data in the 3 % of cases. DAQ is not responsible. Tests have to be made and for that the ADC servers have to undergo to short interruptions. Will be coordinated with XPD. Should not be e problem. CAS to follow the issue up. --> Unclear, CAS not attending.

VAC

​​DET

AE

​​ITDM

​​EET

​​CAS

SRP

  • Schedule changes for the Summer shutdown due to modification of the interlock systems. Additional meetings needed. No info is expected before the beginning of May. --> an uncoordinated email was sent around by MDressel (MPS). SRP will take care of clarifying with MPS what has to be done, when, and will communicate this.

TS

AoB