Group Selection Page
HELP
DOC
Controls Group
Data Analysis Group
ITDM
WP76
DET
Vacuum
XRO
EEE
WP78
WP74
FXE
SCS
SPB
MID
HED
SQS
SXP
Sample Environment
Photon Commissioning Team
Operation
PSPO
XO
TS
|
Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 36
Entry time: 26 Apr 2019, 12:28
|
Author: |
Adriano Violante |
Location: |
General |
Severity: |
Information |
Subject: |
Report after dispatch meeting 09.00 |
|
|
SPB/SFX
- IRD commissioning ongoing.
- CRL motors being tested. --> Mechanical issue with a CRL motor is being addressed.
- CSS interlock tests with AE still ongoing.
- AE needs to know when Loop 9 and 10 are expected to run. SPB to check.
- Jungfrau detector: calibration being finalized.
FXE
- Loop 6 is required to drive 2 servo motors. BB will try to bring this into operation this week. NC checked the setup. ==> The loop 9 will be temporarily used. This will be updated either on Monday/Tuesday, or during beamtime. Agreed with FXE.
- Drawers 2 and 3 have to be rebuilt by AE in order to host new ATCA crates. JE needs time plan info from FXE.
SQS
- AE still needs priorities for the next loops. Only Loops 15 and 16 left to be brought up. No plans yet.
- Export of motors config. parameters needed by AE. SQS asks CAS
- Interlocks minor issues being fixed with AE
SCS
- Discussion with EET ongoing concerning the installation of cables for end stations. Space problem. --> This is a long term issue, to be discussed in the other meetings, ongoing.
- Commissioning of the quadrant motion has been completed.
- Loop 12 (chiller) issues with some cables miswiring has been found. AE and EET to check.
- Motors / encoder of the inlinemic component being commissioned.
MID
- For Loop 9 CY is preparing a change request (naming convention for interlocks). AE involved. --> still pending
- Loop 12 will be operable this week --> an 100V input is needed, but not readily available. --> the 100 V were needed to increase the speed of a motor. The alternative solution of using a 48V teminal and a gear box was proposed by AE and accepted by MID.
- Priorities for next loops needed by AE to plan the work. --> Still required.
- Peltier being debugged by MS
- monochromators pico motor in the tunnel is stuck and needs to be fixed. Will be done on Monday.
HED
- Loop9 (Smaract stages) has to be brough up. --> being done. Smaract stages being also tested
- Next loops are 8 followed by the priority-items from loop 6. Loop8 has been started yesterday
- Loop10 and 11 regarding PPL will be needed in June. HED to confirm. --> Feedback from MN required.
- Limit switches (loop8?) are not operable right now due to a 24V terminal missing.
OPT Lasers
- AE support is needed in order to bring the SCS laser up by the end of may. Mail has been sent. NJardon checks. --> Loop extended and running by the end of next week. --> will be done on 06.05.Eplan export will be ready next monday the latest.
XRO
- Motion loop for Hirex 2 has been delayed until June -> update will be done on 11.06.
XPD
- Issue repoeted from CAS: Fast ADC for MCP in SASE3 duplicates data in the 3 % of cases. DAQ is not responsible. Tests have to be made and for that the ADC servers have to undergo to short interruptions. Will be coordinated with XPD. Should not be e problem. CAS to follow the issue up. --> Unclear, CAS not attending.
VAC
DET
AE
ITDM
EET
CAS
SRP
- Schedule changes for the Summer shutdown due to modification of the interlock systems. Additional meetings needed. No info is expected before the beginning of May. --> an uncoordinated email was sent around by MDressel (MPS). SRP will take care of clarifying with MPS what has to be done, when, and will communicate this.
TS
AoB |