Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 50     Entry time: 03 Jun 2019, 12:57
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 09.30 

SPB/SFX

  • No major issues.

FXE

  • Tool to save motor positions is not working reliably. ==> CAS + AE have different tools on different levels. There is not automatic / global restoring of for example motor positions from the CAS-side available. BUT in the shutdown motor position should not be lost, unless there is a true power outage also affecting the CPUs. ==> Issues are being addressed.

​​SQS

  • Plan for this week is to combine the use of pnCCD and cluster source and make proper mesurements. The CCD measured already X-Rays in 10 Hz mode.

SCS

  • No Major issues

MID

  • No Major issues

HED

  • Beam drifts on the minute scale. The issue could be minimised with a karabo routine in use at FXE (mirrors feedback).
  • Dark images acquired with the jungfrau were not correct due to overheating. It has to be checked by HED whether the issue was solved.
  • Request to trigger the epix and jungfrau detectors via pulse on demand feature and scan tool. Motoaki will ask Daniel and Bruno and discuss the details.

OPT Lasers

​​XRO

XPD

VAC

DET

  • No major issues.

​​AE

ITDM

  • Issue about cooling failure in the lab floor in XHQ is being discussed between KWrona and LKersting

EET

CAS

 

AoB