SASE1 Status and SASE3 Readiness
Technical integration and coordination
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther
Not logged in
List
|
Find
|
Login
|
Help
Message ID:
54
Entry time:
14 Jun 2019, 10:47
Author:
Adriano Violante
Location:
General
Severity:
Information
Subject:
Status report after dispatch meeting 09.00
FXE
SPB/SFX
Getting ready for the shutdown. No relevant issues.
SCS
SQS
PLCs have been switched off. Parameters have been saved.
GATT loop update will happen on tuesday. The schedule of the other loop updates are being agreed with EEE.
MID
HED
Due to missing endswitches / interlock conditions, some YAG-screens have been burnt. Software limit switches will be implemented probably next week. Definitions have been provided by Karen Appel to EEE.
Instrument PLCs also switched off.
Optical lasers
VAC
XRO
HED mono has been opened and the crystal analized. The crystal shows radiation damages. XRO is discussing with HED to understand how to proceed. Since it its not yet clear why the damages happened, it would probably make sense to continue using the same cristal sending the beam to a different region.
XPD
DET
EEE
PLC Powering down in SPB SFX is being performed today.
Several loop updates are being planned and organized.
CAS
Gain curve device has been commissioned with and approved by L. Samoylova.
New structure for the CAS contacts to the instruments has been prepared by HSantos. He will send a mail around with the details.