  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 55     Entry time: 17 Jun 2019, 10:43
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Report after dispatch meeting 09.30 

FXE

  • Floor is being re-worked. Experiment hutch is not accessible until Wednesday. After that only accessible for walk until next Monday. 

SPB/SFX

SCS

SQS

  • It was asked by TBaumann when is the power coming back. It should be on Thursday.  The details must be asked to TSchön. AV will ask TS to send a mail to readiness when the power is back in a stable way.

 MID

  • Updates in the tunnel being agreed with EEE. CRLs should be updated today and the MOV loop latest on Wednesday.

​​HED

Optical lasers

VAC

XRO

XPD

DET

EEE

  • During the power down a heating up of the uTCAs was observed, in the XHEXP1 as well as tunnels. The reason is not clear. Now the situation is back to normal. ITDM checks the situation in the servers racks.

CAS

  • Deployment schedule for Karabo 2.5.0. has been discussed in CAS . Deployment is foreseen to start on the 1st week of July.

ITDM

AoB