Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther, Page 28 of 29  Not logged in ELOG logo
Entry   Minutes of the Technical integration meeting 03.04.19 , posted by Adriano Violante on 03 Apr 2019, 10:44 
SPB/SFX


CRL implementation in the hutch. Cables at the back of the crate have been re-shuffled by EETf. VAC vessel had a leak and is being re-sealed
and pumped. If everything is fine and the vessel can be brought to the hutch the motors test can in principle start already this week.  Interaction
Entry   Report after dispatch meeting 09.30, posted by Adriano Violante on 01 Apr 2019, 10:21 
SPB/SFX


The quadrant motion system test for the AGIPD presented some issues with the limit switches. Being fixed.
Julabo chiller:
waiting for feedback from Julabo to know whether the chiller is going to be repaired on time for next users. If not, SPB/SFX are trying to borrow one from
Entry   Report after dispatch meeting 09.30, posted by Adriano Violante on 29 Mar 2019, 11:02 
SPB/SFX

FXE

​SQS
Entry   Minutes of the Technical integration meeting 27.03.19 , posted by Adriano Violante on 27 Mar 2019, 10:48 
SPB/SFX


CRL implementation in the hutch will happen in April. AE and EET involved. ==> Connectors on the beckhoff frames need to be re-shuffled
according to the newest version of the EPLAN documentation. EET will take care of that, so that the loop can be started as soon as possible.
CSS
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 25 Mar 2019, 11:38 
SPB/SFX


The Julabo chiller for the AGIPD detector broke. After intervention from TS was clear that it was not possible to fix on the fly. Users
time had to be cancelled. In generalr there are 3 solution being pushed simultaneously by SPB: Fix the existing one, buy a new one, integrate a new type
Entry   Minutes of the Technical integration meeting 20.03.19 , posted by Adriano Violante on 20 Mar 2019, 14:07 
SPB/SFX


CRL implementation in the hutch will happen in April. AE and EET involved. ==> ZA needs the documentation of the CRL. The point is
SRP to be able to evaluate the focusing properties to give beam permission after installation. TH will ask directly PVagovic. Still pending since PV is
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 18 Mar 2019, 10:04 
SPB/SFX


No major issues reported
Crates for the CRL will be installed today. Test is foreseen for next week.


FXE


Issue with the synchronization of the PP laser has been reported. This affects also SPB. The problem was found to be in the subsynch
Entry   Minutes after dispatch meeting 09.00, posted by Adriano Violante on 15 Mar 2019, 11:27 
SPB/SFX


No major issues reported
Motors in Loop 14 have been tested and problems with the motion sign and encoder were found. AE/EET
on it.


FXE
Entry   Minutes of the Technical integration meeting 13.03.19 , posted by Adriano Violante on 13 Mar 2019, 11:11 ElectricalSafety.pdf
SPB/SFX


CRL implementation in the hutch will happen in April. AE and EET involved. ==> ZA needs the documentation of the CRL. The point is
SRP to be able to evaluate the focusing properties to give beam permission after installation. TH will ask directly PVagovic. Still pending since PV is
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 11 Mar 2019, 11:58 
SPB/SFX


Experiments were succesfull
Calibration pipeline has issues - being fixed
Detailed planning of the shutdown works
is being done with AE to see whether some activities can be done before or after the critical week
JGFR calibration pipeline needed. SH will
Entry   Minutes of the dispatch meeting 09.00, posted by Adriano Violante on 08 Mar 2019, 13:01 
SPB/SFX


Only minor issues being addressed with the support groups.


FXE

​SQS
Entry   Minutes of the Technical integration meeting 06.03.19 , posted by Adriano Violante on 06 Mar 2019, 10:31 
SPB/SFX


CSS component commissioning. Concept and implementation finalized. EPLAN has been modified. PLC modification has to follow.
Issues
concerning the simultaneous operation of more Jungfrau detector modules has been solved.  Additional tests ongoing. 
CRL implementation
Entry   Minutes of the dispatch meeting 09.30, posted by Adriano Violante on 04 Mar 2019, 10:38 
SPB/SFX


Ongoing discussions with the support groups to organize the shutdown activities.Update of the shutdown task list could eventually be
provided.
X-Ray interlock system had issues in the WE and needed to be re set. Not clear why this happened.
Problem with Karabo freezing.
Entry   Report after dispatch meeting 09.00, posted by Adriano Violante on 01 Mar 2019, 14:18 
SPB/SFX


Today Loop 8 could be ready (AE)
Agipd - visualization of data shows variable rep rate... correlations to be investigated.


FXE

​SQS
Entry   Minutes of the Technical integration meeting 27.02.19 , posted by Adriano Violante on 27 Feb 2019, 11:27 
SPB/SFX


CSS component commissioning. Concept and implementation finalized. EPLAN is being modified. PLC modification will follow.
Loop
14 (Jungfrau) commissionig is ongoing. Issues concerning the simultaneous operation of more modules. SPB and DET on it. The detector is needed functional
Entry   Minutes of the dispatch meeting 09.30, posted by Adriano Violante on 25 Feb 2019, 09:52 
SPB/SFX


Change to the triggers for  cameras is being discussed/implemented with BF.
Preparation for the AGIPD intervention planned
in the next mini shutdown is being discussed with AE.
On Wednesday the user period start. No more commissioning possible. 


FXE
Entry   MInutes of the dispatch meeting 09.00, posted by Adriano Violante on 22 Feb 2019, 12:36 
SPB/SFX


Pulse picker commissiong - Issues concerning motors position and triggers ==> To be worked out with AE, but beam is needed. Has to
be done.
DET group is helping setting up the Jungfrau detector (w/o PLC).
DAQ performance test performed yesterday.
Trigger
Entry   Minutes of the Technical integration meeting 20.02.19 , posted by Adriano Violante on 20 Feb 2019, 11:16 
SPB/SFX


CSS component commissioning. Concept and implementation being finalized.==> Final tests have to be performed at SPB, if OK, the CR
will be finalized.
Loop 14 (Jungfrau) commissionig has started. 3 modules are being controlled. The movable stage should have been shipped from
Entry   Minutes of the dispatch meeting 09.30, posted by Adriano Violante on 18 Feb 2019, 10:09 
SPB/SFX


Data aggregators were often crashing during the WE and needed to be re initialized.
Puls picker commissiong - Scan tool was
used and worked. Issues concerning motors position and triggers ==> To be worked out with AE.
DET group is helping setting up the Jungfrau
Entry   Report after dispatch meeting 09.00, posted by Adriano Violante on 15 Feb 2019, 12:14 
SPB/SFX


SPB requires the new trigger solution to be implemented for AGIPD. This is urgent and should be done before the next run. SHauf
has to check in the DET group whether this can be pushed also wil Jola coming back only next week. ==> done and seems to work
Commissioning
ELOG V3.1.4-7c3fd00