Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther, Page 2 of 29  Not logged in ELOG logo
ID Date Author Location Severity Subjectdown
  45   20 May 2019, 10:02 Gerd WellenreutherGeneralInformationStatus report after dispatch meeting Monday 20.5. 09.30

SPB/SFX

  • are working on achieving a good focus @ 6 keV, which currently is not as good as expected.
  • Digitizers are ready, have been tested by CAS ==> to be be installed / integrated probably next week
  • Different GUIs were reporting varying values for STATUS on different clients / machines ==> ARound will make sure a proper description of the issue (which machines, which clients, when, ...) will be brought to the attention of the proper people @ CAS.

FXE

  • The Karabo FAI went well, FXE thanks explicitly for the support received.

SQS

  • The pnCCD is being set up. AE will be required to help for axes commisisoning next week. ==> this should happen today.

SCS

  • MTeichmann attended, fresh from vacation, nothing to report, everything is "awesome".

 MID

  • Commissioning the cryomanipulator. Had to use a couple of work arounds in order to align it with the beam (travel range issues it appears).
  • The AGIPD Julabo chiller failed on Saturday, it has to be sent in. Meetings this mornings should clarify what other options remain to support the user experiments as planned.

HED

  • User experiment went very well.
  • Currently commissioning ion pumps in the optics hutch
  • Starting on Wednesday loop 6 is to be commisioned (exp. hutch components) together with AE

OPT Lasers

​​XRO

XPD

VAC

DET

  • Question to ITDM: Did the crash of git on Saturday affect the calibration database (there were apparently issues @ FXE for 2 hours) ==> No. If there would have been problems, they would not have resolved with nobody doing anything, the system requires manual intervention. So most probably the problem was somewhere else...

​​AE

  • SCS had a problem with the fast ADC, was fixed Friday. Did this gave further problems during the weekend ==> MTeichmann to check.

ITDM

EET

CAS

SRP

TS

AoB

  47   24 May 2019, 11:01 Gerd WellenreutherGeneralInformationStatus report after dispatch meeting Friday 24.5. 09.00

SPB/SFX

  • are working on achieving a good focus @ 6 keV, which currently is not as good as expected. ==> This is understood now, those were higher harmonics, too many absorbers in the beam. Absorber still shows some structure, though
  • Digitizers are ready, have been tested by CAS ==> to be be installed / integrated probably next week ==> according to Adrian probably Monday, to be confirmed with AE (Bruno + Hamed)
  • Different GUIs were reporting varying values for STATUS on different clients / machines ==> ARound will make sure a proper description of the issue (which machines, which clients, when, ...) will be brought to the attention of the proper people @ CAS. ==> CAS is aware.
  • Data from motor + camera was taken to correlate motion data. ==> still has to be understood with help of DET and ITDM.
  • AGIPD quadrant motion is needed in summer in order to align the detector in order to record data at low scattering angles / closely around the beam center. ==> is scheduled for summer shutdown

FXE

SQS

SCS

  • First light was seen on the DSSC!

MID

  • AGIPD control server is dead ==> to be replaced by a spare by ITDM / Janusz

HED

OPT Lasers

​​XRO

XPD

VAC

DET

  • pnCCD integration is progressing at SQS, testing taking data with the DAQ.
  • MID-chiller issue: chiller will return in next week.
  • Increasing amount of problems and sufferings due to unreliability of gitlab

​​AE

ITDM

EET

CAS

  • OCD-call regarding device communication: The polling-intervall epsilon was set too small, such that the client became flooded and turned unresponsive.

SRP

TS

AoB

  • Shutdown planning now includes MKK, which includes some activities concerning cooling water. Please check, email was sent to readiness.

  78   12 Aug 2019, 09:50 Gerd WellenreutherGeneralInformationStatus report after dispatch meeting 12.8.

XO

FXE

  • XTD1 CRLs: There is an issue regarding a limit switch, to be repaired in the shutdown by MKnoll + EEE.

SPB/SFX

  • Master loop has to be updated. EEE to agree offline with SPB/SFX ==> has been fixed
  • Hexapods are being integrated. ==> was supposed to be tackled today. But since both HED and MID experienced different issues with their hexapods, the commissioning at SPB/SFX has to rescheduled (Tuesday?)
  • Micro KB encoders + beam are drifting away, so closed loop operation would stabilize things... has to be commissioned, foreseen for Wednesday. Users start at Thursday...
  • A microscope got stuck on a limit switch. Probably the limit switches have to be rewired.
  • An encoder in loop 11 seems to be missing. EEE is on it...

SCS

  • Since Sunday there appears to be an issue with the in-vacuum sample stage. Is kind of urgent...

SQS

  • Last week: Commisioned the laser
  • This week: Users & night shift

MID

  • There is an issue with the hexapod, EEE is on it.
  • Chris is testing some cooling / heating using peltier elements.

HED

  • Train IDs are missing in loop 5 and 10. EEE is on it, too.

Optical lasers

VAC

XRO

XPD

  • There is probably an intervention in XTD1 to repair a camera for the self-seeding setup. Others might want to jump on the train. Time is not yet decided.

DET

EEE

CAS

  • Test for 2.6. are ongoing.

ITDM

SRP

TS

AoB

  18   11 Mar 2019, 11:58 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30

SPB/SFX

  • Experiments were succesfull
  • Calibration pipeline has issues - being fixed
  • Detailed planning of the shutdown works is being done with AE to see whether some activities can be done before or after the critical week
  • JGFR calibration pipeline needed. SH will support SPB/SFX today
  • Motors in Loop 14 should be tested. ASilenzi can help. Then info to AE.

FXE

SQS

SCS

MID

  • Epix planning is advancing. List of activity being maintained and followed up by CY. Interface box for cables being modified by KS, CRs being implemented by AE. Ongoing. Goal date is 10.04.2019 to have the detector completely commissioned ==> Ongoing.
  • Issues with Smaract stages cables. Being fixed. (MS will help)
  • Loop 4 would need to be resterted next week.

HED

  • Si mono in XTD6 had problems with the pitch motor whoch does not work anymore. Same problems happened in other mono motors in MID and FXE in the past. MS will have a look. It has be decided how to proceed with the fixing. The mono is required for users operation in HED.
  • Loops readiness and cables readiness have to be aligned and priorities have to be set. It is not clear what can be provided by the end of March in terms of loops and cables. AV calls for  a meeting to clarify and set priorities...

OPT Lasers

XRO

​​XPD

​​VAC

AE

ITDM

DET

  • FXE JGRF was requested to be ready for last week end (done and working), but it was planned for April! In general better planning!
  • SPB calibration pipeline tests ongoing.

EET

CAS

AoB

  21   18 Mar 2019, 10:04 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30

SPB/SFX

  • No major issues reported
  • Crates for the CRL will be installed today. Test is foreseen for next week.

FXE

  • Issue with the synchronization of the PP laser has been reported. This affects also SPB. The problem was found to be in the subsynch hutch. WP18 has been informed and is working on it.

SQS

  • Again Issue with digitizers not working was found and was  solved with the help of CAS.  For the long run PGessler proposed to have a task force with ITDM and CAS to look for eventual bottlenecks in the configuration of the chain. 
  • First CRD for the pn CCDs has been submitted. The second CRD (interlocks) is still in preparation

SCS

  • Loop 7 need to be updated (old) due to problems with readind encoders.
  • 2 fuses in the PLCs have to be replaced. AE has been informed.

MID

  • It is reported by CY that, in order to advance with the Epix readiness, would be beneficial if AE and EETF could accelerate the power system work BKF 467 crate completion (with Bernard's latest change request) plus patch-panel planning Eplan update this would be much appreciated. ==> Mails between CY and LW have been exchanged. CR implementation and Patch panel design are needed by Wednesday. 
  • Loop 9 needs a framework update today.
  • Preparation for the first users coming on Wednesay is ongoing.

HED

  • Si-Mono in XTD6 has been aligned with the cristals parallel to the beam but two issues were found: 1 - On of the movements is at ist limit and needs to be fixed. ZZ today (VAC+OPT support). 2 - One motor in Mono2 that does not work. Has to be checked (AE).
  • XGM/Pulse picker alignment has to be checked with beam. AE will come back to HED today.

OPT Lasers

XRO

​​XPD

​​VAC

AE

ITDM

  • Info was sent to the GLs concernig the use of the Maxwell cluster for users. These seemed not to be propagatet to the users since support was requested to IDTM concerning this specific issue. This is also the case for the detector calibration pipeline. These info should be proprly distributed in the future.

DET

  • FXE had small issues with LPD. DET on it.

EET

CAS

  • HED reported as an info to CAS that yesterday karabo was very slow for 2 hrs (10 seconds to push a button...) but it recovered by itself. Will be looked into... 

AoB

  23   25 Mar 2019, 11:38 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30

SPB/SFX

  • The Julabo chiller for the AGIPD detector broke. After intervention from TS was clear that it was not possible to fix on the fly. Users time had to be cancelled. In generalr there are 3 solution being pushed simultaneously by SPB: Fix the existing one, buy a new one, integrate a new type of chiller. AMancuso is also preparing a document for the MB with the details of the failure.

FXE

SQS

  • REMI being removed. NQS being brought in on wednesday. Support form AE for testing and configuration will be needed.
  • Vac interlock loop updates are being coordinated with AE
  • Laser being set up. Support from AE maybe needed.

SCS

MID

  • DET and ITDM working on the AGIPD this and next week.
  • Loop 9 needs a framework update (flow control with broncos).
  • Patch panel design in eplan for epix ongoing.
  • Opt hutch VAC being implemented in karabo (w/o interlock definitions. interlock tests still outstanding)

HED

  • XGM/Pulse picker alignment has to be checked with beam. AE will come back to HED today. Has been postponed since timing was not properly implemented. 

OPT Lasers

XRO

​​XPD

​​VAC

AE

  • MOV loop in SASE1 and 3 tunnels is going to be updated tomorrow at the latest. Instruments and involved groups are supposed to check if everything is fine after the update
  • SASE2 Vac loop update today
  • ITDM is supposed to work on the redundant switches in the balcony on Wednesday. Karabo is going to be interrupted for about 30 minutes. NJardon will send an email to readiness when the activity is confirmed.
  • Timing card issue issue caused the timing signal to fail in SASE1. Issue was found to be the DESY people rebooting thr PLC without informing the relevant AE people.

ITDM

DET

EET

CAS

  • 2.4.0 released. Waiting for ITDM for DAQ tests. No deployment in the tunnels foreseen for now.

AoB

  32   12 Apr 2019, 10:41 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30

SPB/SFX

  • Hercules students period. During the night a pump failed and recovered after a power cycle.
  • 5Hz mode tests were performed and successful
  • CSS being commissioned. X mov elmo stage still has to be configured. Will be done probably today.
  • After some updates, AGIPD run control topology light does not go to green. Start stop buttons do not work properly (cannot be seen when the detector stops aquiring data). CAS to have a look.

​​FXE

  • After some modifications in the chain fast valve-mps-plc a connector was found to be not properly reconnected and triggering the interlock. FXE should involve AE when such activities are performed in order not to cause overhead to the support groups.

SQS

 

SCS

  • Loop 4 updated. Loop 3 motors being commissioned. Loop 5 quadrant motion being finalized. Loop 12 (VAC) being prepared.
  • It is not clear when BKF 536 and 531 have to be installed by AE. SCS should comment.

MID

  • Loop 12 being prepared and should work by the end of next week.

HED

  • Loop 7 commissiong will start today. KS will send a list of crates to be put in the loops to AE (Prio-non prio PLCs)

 

OPT Lasers

  • SA2 PPL project, HW prepared.

​​XRO

XPD

 

VAC

DET

AE

​​ITDM

EET

CAS

SRP

TS

AoB

  33   15 Apr 2019, 09:55 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30

SPB/SFX

  • Tomorrow set up of the donwstream interaction region will start.
  • Jungfrau calibration pipeline has to be pushed. ITDM and DET involved. Can be done this week.
  • Additional motors control bein implemented by AE.
  • Request presented to CAS to resume a project concerning jetting. Library exists.
  • Issues with Train ID/ cell ID for AGIPD. Fix is ongoing.

​​FXE

SQS

  • Photonic science camera issue: fixed by CAS OCD (SB) but requires a hotfix. Will be provided after Easter
  • VAC interlocks for the NQS chamber will be implemented by AE. Definitions were provided.
  • Turbo only going to 50% when operated by Karabo. Fix ongoing
  • New devices to be implementd in karabo. Contact person informed
  • TB and AE to meet to fix some issues with motors

SCS

  • DSSC is pumping down
  • 6 Elmo motors needed for DSSC needed this week.
  • BKF controls will be tested with the DET group
  • Test of motors with the laser hutch is ongoing. Software installation ongoing.

​​MID

  • Users time ongoing. 2 Epix and Agipd being used without major issues
  • Agipd, 1 useful image every 276. This seems to be the stable configuration. ITDM asks for more optimized usage of the IT hardware next time...
  • ATT arm in the tunnel get stuck from time to time
  • for the 7th of may, 3 users motors have to be imlemented in Karabo. Via UPP, test with CY.

HED

  • Loop 7 commissiong ongoing
  • KS to give green light for next loops
  • Jngfr and epix being commissioned
  • Mono in XTD6 - issue with motor. to be fixed as soon as feasible.

 

OPT Lasers

XRO

XPD

VAC

DET

AE

​​ITDM

EET

CAS

SRP

TS

AoB

  37   29 Apr 2019, 10:04 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30

SPB/SFX

  • IRDa commissioning ongoing. Focus (<5um) in the second interaction region has been achieved.
  • CRL motors being tested. --> issue with a CRL motor is being addressed (connector issue). 
  • AE needs to know when Loop 9 and 10 are expected to run. SPB to check.
  • Jungfrau detector: first beam on the detector. Some issues (receiver had to be restarted, gain constants needed to be properly set) fixed by DET and ITDM OCDs.

FXE

SQS

  • Cameras and DAQ minor issues being fixed.
  • SQS will need to be able to switch the trigger off and connect this to the interlock system. This can be done but requires the addidtion of physical connections by AE and needs to be planned. A faster workaround will be discussed offline with PG.

SCS

  • The gender of a scroll pump and 4 detectors cables were found to be wrong. MT will ask EET for fixing.

 MID

  • The pico motors for the  monos in XTD6 are dead and need to be replaced. This is urgent and will be done this week.
  • AE is supporting MID for the integration of 3 user motors.

HED

  • Loop8 being commissioned. No big issues.

OPT Lasers

XRO

​​XPD

VAC

​​DET

  • LPD first charge injection test with emergency DAQ succesfull. Activities will be continued with the agreed LPD prio list. 
  • FXE. Karabo will be updated for the online calibration.

AE

  • During the WE an issue concerning digitizers and fast ADC was reported. Train ID was not correct. This has not happened before. A fw update solved the issue and is being deployed for all the intruments. A detailed investigation of the reasons is being done. No issue for SQS to have reliable digitizers for the next users run.

​​ITDM

​​EET

​​CAS

SRP

TS

AoB

  39   06 May 2019, 10:20 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30

SPB/SFX

  • IRDa commissioning ongoing. 
  • For this week AGIPD works and re commissioning of the nanometer mirrors will be perfermed. It is possible that support from AE will be required.
  • CSS. Limit switches re cabling is ongoing. For the next run the old configuration will still be used. RB and MS will meet to make sure the system can be safely (from the component point of view) operated. 

​FXE

  • Karabo online data analyzer is being used and is stable.
  • LPD no longer overheats but there is still a small leak.
  • Delay stage will be comissioned with the support of AE today.

​SQS

  • This week SQS will have night shifts. BB will be needed today for motors configuration.
  • Integration of the photonic science camera is progressing (should be with ITDM now)
  • MPODS power supplies are behaving strangely. TB will summarize the issue and send an email to CY

SCS

  • The gender of a scroll pump and 4 detectors cables were found to be wrong. According to MT it is not high priority. Nevertheless, EET did not receive any information about whoch cables need to be checked and repaired.
  • List of nice to have electronics fixes has been sent to NJ and AE requested additional feedback. Fedback from MT needed to proceed.

 MID

  • The pico motors for the  monos in XTD6 and optics hutch are dead and need to be replaced\fixed. ==> the XTD6 mono was fixed but has problems again. The opt hutch mono works but is still not aligned. Now OK.
  • AE is supporting MID for the integration of 3 user motors. Done.
  • ZZ access today for an intervention on CRL1.
  • Loop 7 update is being coordinated for this week between MS and UBoesemberg.

​HED

  • Users assisted commissioning. PVagovic attended. Online processing of data was possible. Characterization ofbeam focus has been done. Data being analyzed.
  • Additional moros will need to be implemented for next run.MS supporting.
  • Mono in XTD 6 requires ZZ access today for fixing.
  • If pulse on demand capability is needed to be used by HED the other instruments need to be informed (especially SQS this week - night shifts) since this mode reduces the beam staibility! This issue should be addressed in general in the operation meetings.

​OPT Lasers

XRO

XPD

VAC

DET

  • Karabo 2.4.1. improves the pipieline stability. The deployment is strongly suggested to MID and SPB.
  • DSSC DAQ was supposed to be tested but more fundamental tests are still being performed. Meeting today at 10 to address the issues.
  • Fast CCD low energy calibration improvement is being discussed.

AE

  • During the WE an issue concerning digitizers and fast ADC was reported. Train ID was not correct. This has not happened before. A fw update solved the issue and is being deployed for all the intruments. A detailed investigation of the reasons is being done. No issue for SQS to have reliable digitizers for the next users run.
  • Servos for FXE implementation ongoing.

ITDM

EET

CAS

SRP

TS

AoB

  • Mail to STGL for the collection of the next summer shutdown activities has been sent. Deadline is the end of next week.
  50   03 Jun 2019, 12:57 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30

SPB/SFX

  • No major issues.

FXE

  • Tool to save motor positions is not working reliably. ==> CAS + AE have different tools on different levels. There is not automatic / global restoring of for example motor positions from the CAS-side available. BUT in the shutdown motor position should not be lost, unless there is a true power outage also affecting the CPUs. ==> Issues are being addressed.

​​SQS

  • Plan for this week is to combine the use of pnCCD and cluster source and make proper mesurements. The CCD measured already X-Rays in 10 Hz mode.

SCS

  • No Major issues

MID

  • No Major issues

HED

  • Beam drifts on the minute scale. The issue could be minimised with a karabo routine in use at FXE (mirrors feedback).
  • Dark images acquired with the jungfrau were not correct due to overheating. It has to be checked by HED whether the issue was solved.
  • Request to trigger the epix and jungfrau detectors via pulse on demand feature and scan tool. Motoaki will ask Daniel and Bruno and discuss the details.

OPT Lasers

​​XRO

XPD

VAC

DET

  • No major issues.

​​AE

ITDM

  • Issue about cooling failure in the lab floor in XHQ is being discussed between KWrona and LKersting

EET

CAS

 

AoB

  59   24 Jun 2019, 09:53 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30

FXE

  • CRLs mainteinance has been completed.

SPB/SFX

  • Some power sockets are not active. NReimers will contact TS.
  • Detectors has been moved in the new position. MOV tests have started. Tomorrow detector modules will be swapped.

SCS

SQS

  • Some Harting connectors have been plugged in the modules. TB will make sure NRennhack informed JEilers. 1 beckhoff module has still to be modified (according to a CR not yet implemented)
  • Some labels are not correct. NR is discussing with EEE
  • AVC3000 leak controller from Pfeiffer. EEE will release the controls today.
  • Vacuum interlocks. BB is working on it this week.

MID

  • Schutdown activities basically on schedule
  • Bias system tests have been done
  • This week R. Schaffer and J.Hallmann will work on the ALAS
  • Quadrant motion system test will start this week. ASilenzi is the product owner.
  • For next week vacuum interlock tests are foreseen

​​HED

  • It is not clear whether the tunnels are accessible or not. They should not be accessible. SK asks SRP and AGaller.
  • This week cooling system works for the M2 are being executed. Hi res mono will follow.

Optical lasers

VAC

XRO

  • M1  in XTD6 is closed and pumped (10^-7 mbar range). How to proceed with the second mirror is being discussed 
  • XTD2 SA1 M1n works have been initiated. Now stopped because of the interlock tests. Will resume next WE.
  • Self seeding mono in XTD1 is now closed and pumping but the vacuum level is not satisfactory.
  • After the last Karabo restart some devices are not working and this should be fixed before the end of the shutdown. Robert is the contact person in CAS and will follow the issue up.

XPD

DET

EEE

  • Timing will not be available due to maintenance until 5pm, as announced last week.

CAS

  • Tests of Karabo 2.5.0. are ongoing (integration PLC/DAQ). 

ITDM

  • AoB
  62   01 Jul 2019, 10:07 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30

XO

FXE

SPB/SFX

  • Detector tests are running this week. Before working on loops or around the detectors the SPB/SFX team should be asked/informed.
  • The SPB/SFX team is on retreat on Thursday and Friday.

SCS

  • Pulse IDs written by detector digitizers are recorded inconsistently by the different instruments. Some discussions have started to improve the situation and work is ongoing, but no target date is known. Right now the people working on this topic are BF, AS, KW, PG. A Karabo data guy should be also involved. The progress should be tracked in the Wednesday meetings.

SQS

MID

  • Loop 7/11 need to be updated. Already coordinated with EEE.
  • Loop8 is needed (remote control of the vac system).

HED

  • Works in the tunnels will resume this week.
  • Commissioning of the Amplitude laser is ongoing. The goal is to bring the optical laser beam into the hutch this week. There might be radiation involved, but HED is working together with SRP to define all the needed steps.
  • This week radiation interlock tests are foreseen with D3. 

Optical lasers

VAC

XRO

XPD

DET

EEE

CAS

  • 2.5.0 will be deployed in SA3 tomorrow and probably in SA2 on Wed (depends on the outcome of the SASE3 deployment). 

ITDM

SRP

TS

AoB

  65   08 Jul 2019, 10:25 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30

XO

FXE

  • Loops update has to be coordinated between EEE and FXE. No feedback received from EEE. AG will remind TKorsh. ==> TK will discuss the topic in the FXe group meeting today and contact EEE.

SPB/SFX

SCS

SQS

​​MID

  • The VAC interlock tests performed on Friday showed some unexpected behavior of the system. Change request is being prepared to fix these (minor) issues.
  • Quadrant motion tests foreseen for this week

HED

  • Tunnel installations have been completed
  • VAC final leak tests today
  • High power laser being aligned to bring beam into the HED experiment enclosure
  • In the optics hutch a new grating is being installed.

 

Optical lasers

VAC

  • All tunnel closed apart from XTD9 and 6

XRO

  • An encoder for the mirrors in SASE1 shows an error. This is known. XRO will notify EEE if they want to have special actions taken.

XPD

DET

  • Karabo 2.5.0 update OK. Update of the calibration system still has to happen for all the detectors apart from DSSC

EEE

CAS

  • On Friday many requests were sent to CAS about final checks needed for commissioning of the components. Priorities have to be set since CAS does not have the resources to deal with all of them.
  • Data loggers for HED will be brought online today.
  • In the 2.5.0 the MPODs were moved to the new configuration. MPC and PES have also been updated. XPD knows that in the standard configuration 0V is set as voltage target since the old values probably were not making sense anymore. A summary/update mail will be sent by CY to readiness@xfel.eu today.

ITDM

SRP

TS

AoB

  67   15 Jul 2019, 10:01 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30

XO

FXE

SPB/SFX

  • After the loops update the MPS signals have to be tested. The plan is to start today. (AS+EEE support is required)

SCS

SQS

​​MID

  • The VAC interlock tests performed on Friday showed some unexpected behavior of the system. ==> have been almost 100% fixed.
  • hexapods can be controlled by Karabo now.
  • Servo motor drivers are now in the EEE lab and would be needed asap in MID to start commissioning. Could happen this week already.

HED

  • High power laser being aligned to bring beam into the HED experiment enclosure. ==> It was not possible to bring the laser into the hutch apparently because of some communication problems with safety. 
  • Mirror s could not be aligned for HED during the WE because of a crash of the MOV loop. This was due to a NaN delivered to the plc instead of a motor position. This problem has been fixed with the last loop update, which was not implemented in the XTD6 MOV loop yet. It will be discussed with EEE, MDommach and L.Samoylova whether to perform the update now.
  • EEE should return the nanocube controllers as soon as possible for commissioning.
  • Hexapods remote controls needed.

 

Optical lasers

  • the status of the SASE1 PP laser is not yet clear.

VAC

XRO

XPD

DET

  • Karabo 2.5.0 update OK. 
  • Online calibration tools will be available for MID and SPB/SFX starting from tomorrow.

EEE

CAS

  • Not a number values  can be filtered by karabo. AS will have a look at that. 

ITDM

SRP

TS

AoB

  • Mail has been sento to the STGL and readiness mailing list. Deadline is the 2.08. for the delivery of the info to XO/PM
  70   22 Jul 2019, 12:42 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30

XO

FXE

  • DAQ issue reported (data not being recorded). Comment from ITDM is that this was a miro issue solved with the re initialization of the proposal. More details will eb discussed offline.
  • Contact person for EEE is now Timo Korsh (deputy is Paul Frankenberger)

SPB/SFX

SCS

SQS

MID

  • Vacuum interlock tests have been (almost completely) performed
  • ITDM OCD was quite busy last week because of some DAQ instabilities. MID/ITDM to discuss offline.
  • CY and RS are working on the nanocube scan device, BF needed today at 13:00 for futher trigger tests.

HED

  • Commissioning ongoing.
  • Problems with data migration: to be discussed with ITDM
  • Epix DAQ issue: solved restarting the server.

Optical lasers

VAC

XRO

XPD

DET

EEE

  • Some issues were reported from NK about motors in SASE1 M2. EEE will need to have a look.
  • Some OCD calls concerning errors from encoders (due to cabling issues)
  • Conditional trigger test in SASE1 was successful.

CAS

ITDM

  • Calibration server for mid has memory problems and needs to be replaced. Calibration pipeline has to be moved to a different servers. Will be discussed offline with MID.
  • SASE3 data migration issues: has to be checked by ITDM
  •  

AoB

  73   29 Jul 2019, 10:16 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30

XO

FXE

SPB/SFX

SCS

SQS

MID

  • Nanocube being used with the scan tool. 
  • Cleanup and preparation for the next experiments ongoing
  • VAC interlock has been tested due to an accidental trigering of a vacuum valve. Some dcetails will need to be fixed.

HED

  • Loop 6 will be updated as soonas the new interlock definitions will be available. KS will talk to HED and EEE to make sure vacuum systems are safe during the update.
  • Loop 7 and 9 will be updated today.

Optical lasers

VAC

XRO

XPD

DET

EEE

 

CAS

  • Crash of PLCs because of not a number values. Karabo client is now available to filer NaN values.
  • 2.5.1. available. FIxes a bug for cameras (restricted ROI), and GUI machines. 

ITDM

  • Some issues with the GPFS will results in slowness of the system. Has been fixed.
  • Cleanup of the GPFS during the weekend. Petabytes of data have been recorded. This may reduce the time in which the data is available on the GPFS for the next user runs. 
  • Xfel gateway will be shut down for a short time today around lunchtime. JS will send a mail to readiness with the precise time.

SRP

TS

AoB

  76   05 Aug 2019, 10:19 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30

XO

FXE

  • Photon3 detector has been fully implemented.

SPB/SFX

  • Some issues reading the encoders of the JJ XRay CSLIT. EEE checks whether similar issues are also present in other instruments. ==> has been fixed.

SCS

SQS

MID

  • 2 Motors have to be checked: Rotation of the hexapod and the y motion of the AUX3 are needed for next week.
  • DPS turbo pump 3 behaving strangely. EEE to have a look
  • Loop 7 has to be updated. Offline discussion MS/JH

HED

  • Grating holder motion HED OPT. Motors to be commissioned. EEE required
  • Cable needed for the Jungfrau timing signal. KS BF to discuss offline.

Optical lasers

VAC

XRO

XPD

DET

EEE

CAS

ITDM

SRP

TS

AoB

 

  44   17 May 2019, 10:47 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.00

SPB/SFX

  • ADC have been requested. HW should be already installed (SPB to check). BF will discuss with SPB how to proceed.

FXE

  • LPD is running.

SQS

  • MPODS power supplies are behaving strangely (1 channel trips, but the power supply does not send any error message). CY following it up but the priority is now with the DSSC (working on powering sequence. To be then adopted later also for other detectors.
  • The pnCCD is being set up. AE will be required to help for axes commisisoning next week.Some issues with electronics to read data have been solved. Tests to understand the reasons of the issues are being performed by AE.

SCS

 MID

  • Setting up next weeks experiments. Some equipment that the users are bringing have to be integrated. This may couse some delays.
  • 2 crates for the remote contro of vacuum compoennts are required to run in the intrument. CY wants to be present. There are difficulties finding a suitable time slot both for MS and CY. To be addressed offline.==> done, interlock tests have to be scheduled by MID.

HED

  • Epix card died. Workaround using some MID infrastructure has been proposed. Risks will be presented by HED ( Sebastian Goede) to MID and a decision has to be taken by the group leaders.

OPT Lasers

​​XRO

 

XPD

VAC

DET

  • Updated pipeline in SPB has been updated yesterday. Seems to work. MID probably will be updated today. Has to be discussed offline with ITDM.

​​AE

ITDM

  • DSSC DAQ was basically not commissioned due to lack of time (although scheduled). Now the detector cannot be oprated. More time has to be scheduled for DAQ commissioning. Meanwhile test on the VETO system are being performed. This would help to save much less data (200 images/train with VETO instead of 800 images/train).

EET

CAS

SRP

TS

AoB

  54   14 Jun 2019, 10:47 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.00

FXE

SPB/SFX

  • Getting ready for the shutdown. No relevant issues.

SCS

SQS

  • PLCs have been switched off. Parameters have been saved.
  • GATT loop update will happen on tuesday. The schedule of the other loop updates are being agreed with EEE.

 MID

​​HED

  • Due to missing endswitches / interlock conditions, some YAG-screens have been burnt. Software limit switches will be implemented probably next week. Definitions have been provided by Karen Appel to EEE.
  • Instrument PLCs also switched off.

Optical lasers

VAC

XRO

  • HED mono has been opened and the crystal analized. The crystal shows radiation damages. XRO is discussing with HED to understand how to proceed. Since it its not yet clear why the damages happened, it would probably make sense to continue using the same cristal sending the beam to a different region.

XPD

DET

EEE

  • PLC Powering down in SPB SFX is being performed today.
  • Several loop updates are being planned and organized.

CAS

  • Gain curve device has been commissioned with and approved by L. Samoylova.
  • New structure for the CAS contacts to the instruments has been prepared by HSantos. He will send a mail around with the details.

ITDM

AoB