Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 70     Entry time: 22 Jul 2019, 12:42
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 09.30 

XO

FXE

  • DAQ issue reported (data not being recorded). Comment from ITDM is that this was a miro issue solved with the re initialization of the proposal. More details will eb discussed offline.
  • Contact person for EEE is now Timo Korsh (deputy is Paul Frankenberger)

SPB/SFX

SCS

SQS

MID

  • Vacuum interlock tests have been (almost completely) performed
  • ITDM OCD was quite busy last week because of some DAQ instabilities. MID/ITDM to discuss offline.
  • CY and RS are working on the nanocube scan device, BF needed today at 13:00 for futher trigger tests.

HED

  • Commissioning ongoing.
  • Problems with data migration: to be discussed with ITDM
  • Epix DAQ issue: solved restarting the server.

Optical lasers

VAC

XRO

XPD

DET

EEE

  • Some issues were reported from NK about motors in SASE1 M2. EEE will need to have a look.
  • Some OCD calls concerning errors from encoders (due to cabling issues)
  • Conditional trigger test in SASE1 was successful.

CAS

ITDM

  • Calibration server for mid has memory problems and needs to be replaced. Calibration pipeline has to be moved to a different servers. Will be discussed offline with MID.
  • SASE3 data migration issues: has to be checked by ITDM
  •  

AoB