Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 33
Entry time: 15 Apr 2019, 09:55
|
Author: |
Adriano Violante |
Location: |
General |
Severity: |
Information |
Subject: |
Status report after dispatch meeting 09.30 |
|
|
SPB/SFX
- Tomorrow set up of the donwstream interaction region will start.
- Jungfrau calibration pipeline has to be pushed. ITDM and DET involved. Can be done this week.
- Additional motors control bein implemented by AE.
- Request presented to CAS to resume a project concerning jetting. Library exists.
- Issues with Train ID/ cell ID for AGIPD. Fix is ongoing.
FXE
SQS
- Photonic science camera issue: fixed by CAS OCD (SB) but requires a hotfix. Will be provided after Easter
- VAC interlocks for the NQS chamber will be implemented by AE. Definitions were provided.
- Turbo only going to 50% when operated by Karabo. Fix ongoing
- New devices to be implementd in karabo. Contact person informed
- TB and AE to meet to fix some issues with motors
SCS
- DSSC is pumping down
- 6 Elmo motors needed for DSSC needed this week.
- BKF controls will be tested with the DET group
- Test of motors with the laser hutch is ongoing. Software installation ongoing.
MID
- Users time ongoing. 2 Epix and Agipd being used without major issues
- Agipd, 1 useful image every 276. This seems to be the stable configuration. ITDM asks for more optimized usage of the IT hardware next time...
- ATT arm in the tunnel get stuck from time to time
- for the 7th of may, 3 users motors have to be imlemented in Karabo. Via UPP, test with CY.
HED
- Loop 7 commissiong ongoing
- KS to give green light for next loops
- Jngfr and epix being commissioned
- Mono in XTD6 - issue with motor. to be fixed as soon as feasible.
OPT Lasers
XRO
XPD
VAC
DET
AE
ITDM
EET
CAS
SRP
TS
AoB |