Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 32     Entry time: 12 Apr 2019, 10:41
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 09.30 

SPB/SFX

  • Hercules students period. During the night a pump failed and recovered after a power cycle.
  • 5Hz mode tests were performed and successful
  • CSS being commissioned. X mov elmo stage still has to be configured. Will be done probably today.
  • After some updates, AGIPD run control topology light does not go to green. Start stop buttons do not work properly (cannot be seen when the detector stops aquiring data). CAS to have a look.

​​FXE

  • After some modifications in the chain fast valve-mps-plc a connector was found to be not properly reconnected and triggering the interlock. FXE should involve AE when such activities are performed in order not to cause overhead to the support groups.

SQS

 

SCS

  • Loop 4 updated. Loop 3 motors being commissioned. Loop 5 quadrant motion being finalized. Loop 12 (VAC) being prepared.
  • It is not clear when BKF 536 and 531 have to be installed by AE. SCS should comment.

MID

  • Loop 12 being prepared and should work by the end of next week.

HED

  • Loop 7 commissiong will start today. KS will send a list of crates to be put in the loops to AE (Prio-non prio PLCs)

 

OPT Lasers

  • SA2 PPL project, HW prepared.

​​XRO

XPD

 

VAC

DET

AE

​​ITDM

EET

CAS

SRP

TS

AoB