Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 76     Entry time: 05 Aug 2019, 10:19
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 09.30 

XO

FXE

  • Photon3 detector has been fully implemented.

SPB/SFX

  • Some issues reading the encoders of the JJ XRay CSLIT. EEE checks whether similar issues are also present in other instruments. ==> has been fixed.

SCS

SQS

MID

  • 2 Motors have to be checked: Rotation of the hexapod and the y motion of the AUX3 are needed for next week.
  • DPS turbo pump 3 behaving strangely. EEE to have a look
  • Loop 7 has to be updated. Offline discussion MS/JH

HED

  • Grating holder motion HED OPT. Motors to be commissioned. EEE required
  • Cable needed for the Jungfrau timing signal. KS BF to discuss offline.

Optical lasers

VAC

XRO

XPD

DET

EEE

CAS

ITDM

SRP

TS

AoB

 