Group Selection Page
HELP
Controls Group
ITDM
Vacuum
WP78
SPB
SQS
XO
ToBeMigrated2XWiki
ToBeMigrated2GitlabPages
ToBeMigratedByGroup
Migrated2Zulip
Archived2PDF
not2MigrateOrArchive
SCS
SXP Migrated2Zulip
Photon Commissioning Team
XRO
DOC
HED Migrated2Zulip
WP74
MID
PSPO_XO
XO_Operation
SQS Migrated2Zulip
FXE Migrated2Zulip
DET
Sample Environment
SPB Migrated2Zulip
SASE1 Status and SASE3 Readiness
Technical integration and coordination
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther
Not logged in
List
|
Find
|
Login
|
Help
Message ID:
73
Entry time:
29 Jul 2019, 10:16
Author:
Adriano Violante
Location:
General
Severity:
Information
Subject:
Status report after dispatch meeting 09.30
XO
FXE
SPB/SFX
SCS
SQS
MID
Nanocube being used with the scan tool.
Cleanup and preparation for the next experiments ongoing
VAC interlock has been tested due to an accidental trigering of a vacuum valve. Some dcetails will need to be fixed.
HED
Loop 6 will be updated as soonas the new interlock definitions will be available. KS will talk to HED and EEE to make sure vacuum systems are safe during the update.
Loop 7 and 9 will be updated today.
Optical lasers
VAC
XRO
XPD
DET
EEE
CAS
Crash of PLCs because of not a number values. Karabo client is now available to filer NaN values.
2.5.1. available. FIxes a bug for cameras (restricted ROI), and GUI machines.
ITDM
Some issues with the GPFS will results in slowness of the system. Has been fixed.
Cleanup of the GPFS during the weekend. Petabytes of data have been recorded. This may reduce the time in which the data is available on the GPFS for the next user runs.
Xfel gateway will be shut down for a short time today around lunchtime. JS will send a mail to readiness with the precise time.