  34   17 Apr 2019, 11:34 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 17.04.19

SPB/SFX

  • CRL motors being tested. Today BB (AE) will check the status.
  • CSS interlock tests being planned for tomorrow.
  • Jungfrau motors -  SS (EET) fixed some cable issues. Now ok.
  • Julabo chiller: loop 5 has been updated (interlocks definition, setpoints...) AE+DET working on it. 
  • AE needs to know when Loop 9 is expected to run. SPB to check.

FXE

  • AE needs to get information on PLCs loop splitting. FXE to comment. 

SQS

  • Loop 9 will be updated.
  • AE helping for commissioning
  • AE needs priorities for the next loops. SQS to comment.

SCS

  • DSSC installation progressing. Loop 5 motion loops should run
  • In general loops have been updated. Loop 13 (part of it) being commissioned. AE needs to know then the entire loop commissionig will start.
  • Discussion with EET ongoing concerning the installation of cables for end stations. Space problem.
  • Loop 4. BKF536 and 531 being modified. Clarification with AE/EET needed.

 MID

  • Epix voltage interlocks definition and implementation. AE (MS) and CAS (CY) working on it.
  • For Loop 9 CY is preparing a change request. AE involved.
  • Loop 12 will be operable this week
  • Priorities for next loops needed by AE to plan the work.

HED

  • Mono in XTD6 has been fixed.
  • Jungfrau and epix commissioned
  • Loop 7 being commissioned
  • Loops 1, 2 , 5, 7 could be done
  • Loop9 (Smaract stages) has to be brough up. 
  • Loop10 and 11 will be needed in June. HED to confirm.

OPT Lasers

  • SA2 PPL work ongoing this and next week. ready by next week.
  • AE support is needed in order to bring the SCS laser up by the end of may. Mail has been sent. NJardon checks.

XRO

XPD

  • Loop updates procedure being finalized by AE. NK asked for MOV2 loop update during next week. AE will try to follow this up.
  • Issue repoeted from CAS: Fast ADC for MCP in SASE3 duplicates data in the 3 % of cases. DAQ is not responsible. Tests have to be made and for that the ADC servers have to undergo to short interruptions. Will be coordinated with XPD. Should not be e problem. CAS to follow the issue up.

VAC

​​DET

AE

​​ITDM

EET

CAS

  • 5Hz test follow up is being done by CAS. Especially optimization concerning train id and time stamp with DESY with the goal to make the switch between the different operation mode easier. A meeting will be planned.
  • 2,4,1. hotfix (Fast data pipeline) is being prepared

SRP

  • Oil cans in and outside SPB rackroom should be removed. A proper cabinet has been requested to TS but it is not yet ready since exhaust lines are needed.
  • Patch cables in the racks should be limited to the very necessary amount since there the material storage is not allowed . TS can help finding space for this material in the hall..
  • Schedule changes for the Summer shutdown due to modification of the interlock systems. Additional meetings needed. No info is expected before the beginning of May.

TS

  • Support for chillers. Contact people by TS are T. Bartsch and P. Schmidt. They can support concerning issues and problems with chillers for the day to day operation. LKersting supports that. For bigger project, a specific request should be made to LK.

AoB

  43   15 May 2019, 12:53 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 15.05.19

SPB/SFX

  • Nano KB mirrors and CSS controls are OK
  • Digitizers have been requested. HW needs to be installed and set up and the timeline has to be clarified betweek BF and SPB. Not possible to have them running on short notice.
  • Comment from AS: Trigger Test with pulse on demand to test the conditional trigger (5Hz like operation) is done, but failed to deliver a real conditional trigger. The Karabo device is adapted to switch between the present mode and conditional trigger from Karabo (although some issue were identified). The X2Timer configuration still need adjustment, BF is on it.

FXE

  • Re shuffling of PLC CPUs drawers will occur during the next winter shutdown.

SQS

  • MPODS power supplies are behaving strangely. CY will have a look.
  • pnCCD: Commissioning should start today. Maxi cage for interlocks will be installed today by SQS.

SCS

  • Det. DAQ test ongoing.

 MID

  • Axes for users operation being commissed
  • Communication between VAC and AE concerning the electronics for the cryo coolers - heaters has to be improved since AE was not involved during the last ZZ intervention on monday. MD will discuss later today with NJ.

HED

  • Loop 6 can be operated in its completeness by middle of next week.
  • Laser beam has to be deivered to SCS in 2 weeks. Fw has to be uploaded in the PLCs. HW is ready, commissioning has to start.
  • There is the request to make the timing signal independent between the SASEs. Will be discussed offline with AE. It should be possible in the winter shutdown. ==> BF is talking to the involved people.

XRO

XPD

VAC

DET

  • Karabo 2.4.1. improves the pipieline stability. The deployment is strongly suggested to MID and SPB. ==> Pipeline for SPB has been deployed. Minor issues being addressed. MID has to folllow.

AE

ITDM

EET

  • Schedule for the Loop 10 and 11 of HED cables installation is confirmed. IN KW25 would be possible to bring the loop up.

CAS

SRP

TS

AoB

  79   14 Aug 2019, 10:01 Gerd WellenreutherGeneralInformationMinutes of the Technical integration meeting 14.08.2019

XO

  • On Monday at around 12:20 there was a power glitch at least in Hamburg, affecting the machine.
  • In this cause, the startup was delayed due to a missing signal from the Vacuum EPS-MPS-interface. The signal had to be manually enabled again.
  • Tuning is estimated to take until 14:00 today.
  • In the wake of such events a lot of communication about the machine status is happening. In the future, XO will ensure the readiness mailing list will be updated, too. In this respect, P. Gessler suggested to rethink / rename the multitude of mailing lists inherited from the construction phase.

FXE

  • There are concerns about the replacement of the simple motor with the MC2 library, in particular about whether all functionalities will still be available (e.g. step-up/down). According to EEE this should be okay. CAS has already release the new library for testing.

SPB/SFX

  • Hexapods are being integrated. ==> This was rescheduled due to the issues with hexapods at HED and MID. Currently, there is no dire need to integrate the SPB/SFX hexapod, it can be run from TwinCAT.

SCS

  • There is an issue with the main sample stage. SCS and SEC are working on it, will continue with commissioning the instrument.

SQS

  • Loop 14 will be updated today.

MID

  • DPS turbo pump issue. A software workaround exists. The problem is that the used controller has not been commissioned firmwarewise before. This is not a showstopper and wil be addressed later. ==> The cabling is done differently. EEE is testing the device + firmware.

HED

  • Loop 13 has been commissioned.

Optical lasers

VAC

XRO

  • There was an issue with a drift of the HED mirror. As a consequence, VAC and XRO have switched of the mirror cooling. HED and MID should report about the change of the situation.

XPD

  • During an intervention in XTD1 the LED for the Self-Seeding setup was replaced.

DET

EEE

CAS

  • 2.6.0. being prepared. ==> Sneak peak was deployed in SPB/SFX. Actual deployment datas can be found in the Shutdown planing, will be discussed in the chapters and with the SASE responsibles.

ITDM

SRP

  • The primary door of the HED experiment is currently not guarded with a magnet against incidential opening of the door leading to a trip of the machine. KWitt has to redo some cabling, until then, users can set the laser interlock, which will engage the magnet.

TS

  • Controller for the hexapod is currently in the MID control room. UBrueggmann should check the installation.

AoB

  • Please check the shutdown planning
  • No dispatch meeting on Friday.

  19   13 Mar 2019, 11:11 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 13.03.19

SPB/SFX

  • CRL implementation in the hutch will happen in April. AE and EET involved. ==> ZA needs the documentation of the CRL. The point is SRP to be able to evaluate the focusing properties to give beam permission after installation. TH will ask directly PVagovic. Still pending since PV is not here.
  • AGIPD motion. Prelminary tests are being performed to be ready for the final tests in the march shutdown. Still planned.

FXE

SQS

SCS

  • When operating the machine in the train pattern (not  10 Hz) mode and pulse on demand mode the data from the XGMs in XTD10 and SCS is not recorded. ==> That's still the case and it is caused by a Doocs update not agreed with CAS.

MID

  • Issue with the remote control of the ion pumps.MID OPT now ok. MID exp being implemented (waiting for some HW + Support from CY). Basically understood. Will be implemented in agreement with the instrument (requires access + fixed cables)
  • Smaract stages do not work propery and reliably. High priority. Has to be clarified with AE since it is not clear whether this is the same issue that SCS had and for whoch they developed a workaround.

HED

  • Cables for the experiment hutch are being installed but some quality issues occured. Last pallets of cables have been sent back for proper confectioning. It is possible that there will be some delays. KA will discuss with LW how to prioritize cables to eventually minimize the impact on the commissioning. ==> Quality issues are being addressed. The company increased the manpower for cable confectioning and installation. KS prepared a list of priorities. AE informs that they will be probably able only to provide fw for loops 5 and 7 by the end of March (collision with many shutdown activities). PG will send details to KA. This will eventually require a decision concerning priorities.  Ongoing. ==> There will be a dedicated meeting after this one to discuss the details, coordinate the process (Cables/fw export/ Loops start).
  • CRL2 in XTD6 - issue with motors losing steps. Will be fixed in the March shutdown. ==> L. Batchelor
  • DAQ is ready. Data sources list has been sent to CAS. Will be also sent to ITDM for implementation.==> Status not clear
  • For the fixing of the mono's Picomotor, XTD6 will be opened tomorrow and on friday during the day. On the evenings the tunnel will be searched and closed again to allow beam in MID.

 

OPT Lasers

  • Modules for the time stamp have to be installed by AE. How long does it take? Will be discussed offiline with PG. ==> Installation dates: SASE1 in summer shutdown,  SASE3 being worked out, SASE2 will follow. Workaround with time stamp is being investigated.

XRO

XPD

  • Hirex 2 will be shipped from Cologne tomorrow and will be brought into the VAC lab. Cretes ready, cables ready. AE can support local tests outside the shutdown week.

 

VAC

  • Charge injection test (LPD, FXE) have been perfomed successfully.

DET

AE

  • Data Correlation issue test between MCP detector and XGM - PG: Workplan has been made. Additional tests needed and have to be planned with beam. ==> Beamtime will be requested by JG.
  • Hirex and DSSC integration and commissioning will most probably not be supported in the shutdown week. AE will try to support them outside that period.

​​ITDM

EET

CAS

  • Who is responsible for the bunch pattern recording for the different instruments? CAS will clarify with ITDM and AE. ==> Ongoing.
  • Karabo 2.4.0 test ongoing
  • 2.3.7. Hotfix available today (pipieline in middle layer devices has been optimized). To be decided by the instr. whether to install it or not. Recommended.
  • HED kick off meeting for preparation for users has to happen.
  • XGMs: DOOCS was updated without agreement with CAS and this lead to problems with the controls. In this condition CAS can give only limited support , because they do not know excactly what was deployed and whoch tests were done. In general, this goes against the good practice rule of not updating stuff during the beamtime.

SRP

  • The self rescue training is supposed to become part of the access requirement in the DACHS system for the tunnel. This caused a lot of concerns during the meeting (visitors? Access to components only in the very firrt part of the tunnel ). PSPO will discuss with SRP .==> SRP is trying to find a way to minimize the impact of this training on the XFEL employees. Discussion with DESY needed. ==> The implementation date is the 01.05. The legal requirements are quite strict. SRP is trying to find a solution with DESY (proper training every 3 yrs + yearly updates? to be seen). Advice from SRP is to get the training. SScherz can support booking the trainings.
  • HED Radiation interlock issues: no agreement yet to get beam permission. Another meeting is planned for tomorrow (SRP chairs).==> Solved
  • EUPs: Procedures for the electrical safety trainings and appointments are being clarified (UB, TH, WUS) ==> 2 training per week (in german) are planned for KW 13,14,15. SRP and TS will approach the GLeaders to decide who has to take the trainig first in the different groups. PGessler and SHauff point out that it is not clear whether the policy is olready in place or not. THaas mentioned that we are still in the transition phase and a presentation was given in thre STGL meeting and it was responsibility of the GLs to inform the group members. TH will send AV the material that will be circulated to the readiness mailing list and  in this elog ElectricalSafety.pdf.
  • SArslan has been appointed Safety responsible for the Exp. Hall. Access for XFEL employees will be granted by him from now on and not anymore by AViolante and GWellenreuther

AoB

Attachment 1: ElectricalSafety.pdf
ElectricalSafety.pdf ElectricalSafety.pdf ElectricalSafety.pdf ElectricalSafety.pdf ElectricalSafety.pdf ElectricalSafety.pdf ElectricalSafety.pdf ElectricalSafety.pdf
  7   13 Feb 2019, 10:59 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 13.02.19

SPB/SFX

  • CSS component commissioning. RBean is discussing with AE. Concept and implementation being finalized.
  • Loop 14 (Jungfrau) is needed for next week to start the commissioning. IT Cables have been accepted after new measurements. Loop can be switched on.
  • Issue about parallel operation of the 3 Jungfrau modules. Being addressed (DET)
  • CRL implementation in the hutch will happen in April. AE and EET involved. Safety concept for the handling of Berlillium lenses has been finalized.

FXE

  • FXE is working with the SPB spare beam stop (new concept). XRO is in parallel preparing another beamstop for FXE to comply with the new safety standards. SPB needs to get the beamstop back in April.

SQS

  • The chain digitizers-triggers-software is being commissioned to allow online analysis. AE, CAS required and involved.==> Specific issues being addressed.
  • exhaust line for explosive gases has not been tested so far and no information is available to SQS. Urgent. SRP should comment.==> MMeyer is following up the issue. - NO update.

SCS

  • PLCs have been all installed. Firmware deployment has to be pushed. AE is on it.==> Ongoing and high priority. 
  • Commissioning (Smaract/microscope chamber) ongoing.
  • Detector group is working on the fastCCD. Cooling rod has been installed. Cooling is stable. According to DET should be OK.
  • Pulses for SASE3 has been delayed, but it will be no issue for the FastCCD.

MID

  • Issue with the remote control of the ion pumps. It is not possible to switch on and off the pumps remotely due to the fact that a wrong terminal was used . It seems this was also the same issue in SASE1 and 3. AE and EET are on it to fix it and update the doucumentation. ==> AE needs to perform a test at MID before deploying the solution. Since there are other priorities now the test has not happened yet.
  • An automatic chain of communicaton is needed (TS?) to notify relevant peopole when the power is down. ==> UBr will follow up the automatic notification setup.
  • Issue with the silicon oil leaks. Even though the system was testes with LN2 up to 5 bar. For now it is not  a showstopper but it needs to be addressed.

HED

  • Si bounce monochromators - Chiller leaks. Will be repaired in the next shutdown.
  • hirex mono water connections will be reworked in March.
  • Leak in the cooling unit of the racks in A.27 was repaired on site. (TS+External company)

 

OPT Lasers

XRO

  • In SASE3 additional safety shutters issue: Hardware will be ready by middle of Feb. On the 24 and 25. the installation and the modification of the EPS loop should take place if D3, SRP agree on the change request proposed by HS and MD. ==> Still no official decision from D3 and SRP. AE would like to get as many info as possible in advance to start preparing the loop update. According to MDommach NJardon is supposed to be already in the loop.
  • M2 in SASE3 is commissioned and being fine tuned by the instruments.
  • There was a DAQ issue concerning the reading of imagers. Should be solved accordina to ITDM, has to be checked and confirmed by XRO.
  • CAS is fixing some issue on the middle layer for the slit gap controls.

XPD

VAC

DET

  • Jungrfau control issues being addressed
  • SPB requires the new trigger solution to be implemented for AGIPD. This is urgent and should be done before the next run. SHauf has to check in the DET group whether this can be pushed also wil Jola coming back only next week.

AE

  • DESY reboot  of the timing system: small issue with SPB and XRD. Solved.

​​ITDM

  • Storage and logbooks are planned to be divided per week (different buckets for different weeks). It has to be discussed whether it makes sense to try to mergen some of them (e.g. instrument commisioning?). Has to be discussed with the instruments.

EET

CAS

AoB

 

  53   12 Jun 2019, 12:40 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 12.06.19

FXE

SPB/SFX

SCS

SQS

MID

  • Integration of the LDM: Safety document is needed. ==> This is needed ASAP!!! ==> J. Hallmann is now back and he is in contact with SRP ti finalize the documentation. The statement from MID is that until the documents are finalized no automatic movement of the detector is foreseen.

​HED

  • Due to missing endswitches / interlock conditions, some YAG-screens have been burnt. HED would like to try to get this fixed in the tunnels and the hutches still in this shutdown by installing endswitches etc., to be negotiated with EEE ==> Software limit switches can be implemented already next week if the definitions are delivered to EEE by the end of this week.

Optical lasers

​VAC

  • Requested to see the first pump + valve of SPB/SFX ==> definitions still needed by EEE

XRO

XPD

DET

EEE

  • Improvement of the communication concering loop updates with the XRO has to be achieved. Mails have been sent by PGessler to the STGL and by NJardon to the relevant people. Loops updates already planned for next week in SASE2. Coordination with the involved people ongoing.

CAS

ITDM

SRP

  • From SBP/SFX: Currently, it is not clear what to do if one of the Pandoras goes off. This apparently happened @ FXE on the night from Sat.-Sunday, and it took 12 hours to fix it. Update from SRP: Occasionally Pandoras trigger radiation alarms. It is not clear why. One possibility is that this is caused by electronic noise. Discussions with D3 are ongoing. Right now an expert is needed to reboot the system since it is not a simple off/on procedure, but data has to be analysed. There is a a document in preparation by SRP/D3 that will allow more people to be able to perform this procedure, but it is not ready yet. A side note is that there is no OCD agreement in place for these experts and the reboot is done on the best effort level.

TS

​AoB

  66   10 Jul 2019, 16:16 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 10.07.19

XO

  • In SASE3 the apertures of the GATT have to be realigned. The upstream apertures have been alreadz realigned. The downstream ones will be probablz realigned tomorrow. If not succesfull some restrictions of the operation have to be evaluated. ==> Done.
  • Turnstile issue: 2 days ago the hall was not accessible for some hours because of non functioning turnstiles. The problem was a change in the desy firewall configuration that lead to the transponders system not working. 

FXE

  • Loops update has to be coordinated between EEE and FXE. No feedback received from EEE. AG will remind TKorsh. Still pending.

SPB/SFX

  • No major issues
  • BB is coordinating the loops update with SPB/SFX

SCS

  • No Major issues
  • Loop1 has been updated

SQS

  • Aerosol will be commissioned next week. EEE waiting for the precise dates.==> Still waiting.

​​MID

  • XRO will agree with MID which functionalities of the attenuators in XTD1 have to be tested. 'to do list' will be issued. XRO will put the results in the operation logbook. If XRO will not make it to test everything, MID will be informed and will help.
  • XTD 6 will be closed tomorrow after lunch. CY points out that there is a list of issues to be fixed in XTD6 (e.g. motors not working) and many people in CAS are ill, hence, not available, NJ checks with MS and CY sends the list to EEE.
  • By the end of the week MID should send the requirements for the vacuum interlock to EEE.

HED

  • The monochromator can be cooled down now. The vacuul is still not optimal but the device is operable,.
  • Today loop 3 will be updated.

Optical lasers

VAC

XRO

  • M1 in SASE2 and 1 will be commissioned this week end. New positions will be found and written diwn in the logbook. Difference of some mm with respect to the old positions is expected.

XPD

DET

  • Tests with Karabo 2.5.0 OK.

EEE

  • Electrical safety regulation. From the beginning of July the new electrical safety regulation is supposed to be in place. According to this regulation the work at the back of the racks in the XHEXP1 and in the entire racks in the tunnels can only be done by certified EFK (Elektrofachkraefte) or by EUPs with an additional training. The additional training can only be provided after summer. The nomination of XFEL EFKs is suffering a delay due to the fact that is not clear who should nominate them (TS, UBR, HR?).  PG reported the problem and also the fact that no official statements were made in the past concerning the topic. THaas is trying to clarify the status, and come up with a statement and proposal in the Operations meeting. ==> there was no meeting on Friday. Still pending. ==> implementation of the electrical safety regulation has been postponed to the end of the year (mail from SRP).

CAS

  • Deployment of Karabo 2.5.0 has been completed

ITDM

SRP

TS

AoB

 

 

  31   10 Apr 2019, 10:54 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 10.04.19

SPB/SFX

  • CRL implementation in the hutch. Tests can start today.
  • CSS Test have been started. One elmo devide has to be implemented today. Interlocks have to be tested (later).
  • AGIPD motion. Middle layer final tests will be done during next reconfiguration od the detector.
  • Julabo chiller: loop 5 has been updated (interlocks definition, setpoints...) AE+DET working on it. seems ok.

FXE

SQS

  • Loop 8 and 11 up and running.

SCS

  • Loop 4 being updated. Loop 5 (DSSC related) will be updated this and next week.
  •  Loop 13 running with 1 crate. Part of cables will be delivered by EETf this week. 

MID

  • Smaract stages do not work propery and reliably. High priority. Has to be clarified with AE since it is not clear whether this is the same issue that SCS had and for whoch they developed a workaround. ==> BB will contact the Smaract company to address the issue.
  • Epix power issue has been fixed. The problem was a parameter not properly set in the power supply. No interlocks are being used. MID is aware of that.
  • Loop 9, 4 and 12 will be updated with interlocks next week.
  • Exapod control vs data policy issue (also affecting HED and SPB, as well as other components). The exapod control implementation via Beckhoff requires time and is planned for the end of April. For the time being SPB and MID control the exapods via software. This make somewhat difficult to store all the data in the correct way and is not fullfilling the data policy. PSPO will report the issue to TT. At this stage a reshuffling of priorities to speed up the HW implementation seems not to help, since it is anyway planned for end of April.
  • Loop 12 ready next week.

HED

  • Loop 5 being commissioned. Should be completed by today. Loop 7 cables are been reorganized and the commissioning will strat tomorrow. Planned to be completed by the end of the week. Lilla cables between patch panels and components will be asked and discussed with AE. 

 

OPT Lasers

  • SA2 PPL work ongoing. ready by next week.

XRO

  • Commissioning of M1 in SASE3 took place. An intervention concerning a limit switch has to be done (not critical)

XPD

  • Hirex 2 - Commissioning ongoing. Some imporvements, especially concerning DAQ is needed and will be discussed by AK with ITDM.

 

VAC

  • SASE2 beam permission button is hidden in the vacuum expert panel. It is not the case for SASE1 and 3... To be clarified with VAC, XRO and CAS.

DET

AE

  • 5Hz operation (HW trigger dependent on the bunch pattern) mode pre tests OK. New tests planned for tomorrow (SPB and SCS). MCP and hirex will also be included in the test with low priority.

​​ITDM

EET

CAS

SRP

  • A power supply was switched off by AE and found on again the next day despite a sign put on the device. This should not happen. SRP advices, in similar cases, also to add a contact of the person who switched off the device for safety reasons.
  • XS5000 controller in SCS issue. SRP clarifies that everybody must act in case of clear danger (e.g. preventig the access to a particular area). In this case, it was OK that UB and TS prevented the access to the SCS laser hutch to other people before the controller was put in a safe state.  Having said that, the responsibility lies with the scientific group operating the device.

TS

AoB

  40   08 May 2019, 10:10 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 08.05.19

SPB/SFX

  • IRDa commissioning ongoing. 
  • CSS. Limit switches re cabling is ongoing. For the next run the old configuration will still be used. RB and MS will meet to make sure the system can be safely (from the component point of view) operated. ==> Solved.
  • Comment from AS: Trigger test with pulse on demand was not succesfull due to missing karabo devices and issues with configuration. For the final fix 10 minutes of beamtine has to be taken from SPB/SFX. This will be agreed with the intrument.

FXE

  • Delay servo stages have been commissioned. Right now only one stage is being used.  

SQS

  • Integration of the photonic science camera is progressing. Status not clear.
  • MPODS power supplies are behaving strangely. CY will ahve a look.
  • The pnCCD is supposed to be used next week. SQS want to use channels dedicate to other components and work out a temporary solution. AE requested the list of channels to be used but no answer has been received so far. Also, proper CRDs to start preparing the propoer implementation of the controls is still missing.

SCS

  • Part of the uTCA system will need to be installed in the hutch (it was planned for the rackroom). Discussion channel is open with AE.

 MID

  • Servo motors require fw updates. Being agreed with AE.
  • Loop 7 update is being coordinated for this week between MS and UBoesemberg.

HED

  • For Loop 6 and 8, as well as smaract stages AE is waiting the go ahead from HED to switch on the Beckhoff modules. 

OPT Lasers

  • Laser beam has to be deivered to SCS in 2 weeks. Fw has to be uploaded in the PLCs. AE got the fw export and should upload it by friday this week.
  • There is the request to make the timing signal independent between the SASEs. Will be discussed offline with AE. It should be possible in the winter shutdown.

XRO

XPD

VAC

DET

  • Karabo 2.4.1. improves the pipieline stability. The deployment is strongly suggested to MID and SPB. ==> Deployment schedule for next week monday.

AE

ITDM

EET

  • GDB cables have been completely produced and are bein installed this week. 
  • Schedule for the Loop 10 and 11 cables installation is confirmed. IN KW25 would be possible to bring the loop up.

CAS

SRP

TS

AoB

  • Presentation showing the MPS schedule  is attached and is showing when the emergency power off system will be triggered. The Beckhoff modules shut down is being organized by AE. It is noted that the instruments should organize the temporary power supply for the vacuum system.
Attachment 1: Technical_Integration_Meeting_07.05.2019_-_Copy.pptx
  77   07 Aug 2019, 11:55 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 07.08.2019

XO

The accelerator is now working at 2.25 MHz. Kicker can be used. DET informs that for repetition rates different to the ones been used so far the calibration can be significatively different.

FXE

SPB/SFX

  • Hexapods are being integrated. 
  • Master loop has to be updated. EEE to agree offline with SPB/SFX

SCS

SQS

  • Commissioning of smaract stages done. 1 encoder cable is being checked (seems a problem of definition).

MID

  • DPS turbo pump issue. A software workaround exists. The problem is that the used controller has not been commissioned firmwarewise before. This is not a showstopper and wil be addressed later. 

HED

Optical lasers

VAC

XRO

XPD

DET

  • Offline calibration update has been performed in SCS. Tests are foreseen for today.

EEE

  • A new karabo device updating the digitizers with the beam parameters in real time has been successfully tested last week.

CAS

  • 2.6.0. being prepared.

ITDM

SRP

TS

AoB

The dispatch/tech. integration meetings will be re organized in the near future. Slides are attached.

Attachment 1: Technical_Integration_Meeting_07.08.2019_-_Copy_(4).pptx
  16   06 Mar 2019, 10:31 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 06.03.19

SPB/SFX

  • CSS component commissioning. Concept and implementation finalized. EPLAN has been modified. PLC modification has to follow.
  • Issues concerning the simultaneous operation of more Jungfrau detector modules has been solved.  Additional tests ongoing. 
  • CRL implementation in the hutch will happen in April. AE and EET involved. ==> ZA needs the documentation of the CRL. The point is SRP to be able to evaluate the focusing properties to give beam permission after installation. TH will ask directly PVagovic.
  • AGIPD motion. Prelminary tests are being performed to be ready for the final tests in the march shutdown.
  • It is possible to operate simultaneously the Agipd and Jungfrau detector. One issue is the restarting the Agipd afterwards. The issue is non critical and is being solved by DET/CAS.

FXE

SQS

  • exhaust line for explosive gases has not been tested so far and no information is available to SQS. Urgent. SRP should comment.==> MMeyer is following up the issue. ==> MM has got all the documentation and approval needed. The line can be used. XPD and CAS on it.

SCS

  • When operating the machine in the train pattern (not  10 Hz) mode and pulse on demand mode the data from the XGMs in XTD10 and SCS is not recorded.

MID

  • Issue with the remote control of the ion pumps.MID OPT now ok. MID exp being implemented (waiting for some HW + Support from CY)
  • AGIPD, Diamond and Epix detector tests succesful. AM thanks the technical groups for the support.

HED

  • Si bounce monochromators - Chiller leaks. Will be repaired in the next shutdown. ==> Waiting for delivery of parts. Not clear whether can be fixed in the next shutdown.==> Ongoing.
  • Cables for the experiment hutch are being installed but some quality issues occured. Last pallets of cables have been sent back for proper confectioning. It is possible that there will be some delays. KA will discuss with LW how to prioritize cables to eventually minimize the impact on the commissioning. ==> Quality issues are being addressed. The company increased the manpower for cable confectioning and installation. KS prepared a list of priorities. Ongoing.
  • Si- mono commissioning ongoing. Cameras for pico motors have been installed.
  • CRL2 in XTD6 - issue wit motors losing steps. Will be fixed in the March shutdown.
  • DAQ is ready. Data sources list has been sent to CAS. Will be also sent to ITDM for implementation.
  • Commissioning run proposal. Elogs to be used will be discussed with ITDM offline.
  • AE informs that they will be probably able only to provide fw for loops 5 and 7 by the end of March (collision with many shutdown activities). PG will send details to KA. This will eventually require a decision concerning priorities. 

 

OPT Lasers

  • Modules for the time stamp have to be installed by AE. How long does it take? Will be discussed offiline with PG. ==> Installation dates: SASE1 in summer shutdown,  SASE3 being worked out, SASE2 will follow. Workaround with time stamp is being investigated.

XRO

  • In SASE3 additional safety shutters issue: Hardware will be ready by middle of Feb. On the 24 and 25. the installation and the modification of the EPS loop should take place if D3, SRP agree on the change request proposed by HS and MD. ==> Still no official decision from D3 and SRP. AE would like to get as many info as possible in advance to start preparing the loop update. According to MDommach NJardon is supposed to be already in the loop. ==> Concept in written has not yet been communicated to SRP and AE. ZA will talk to HS. ==> HW is installed. Loop update can happen monday or tuesday. The proposed additional radiation safety measures for SASE3 were discussed with Zunaira Ansari. A test is foreseen for 5 March. Implementation in the SEPS system will be directly coordinated between Zunaira and Nerea. ==> Test successful. Limit for SASE3 has been nor raised to 1.3 keV.

XPD

VAC

DET

AE

  • Data Correlation issue test between MCP detector and XGM - PG: Workplan has been made. Additional tests needed and have to be planned with beam.

​​ITDM

  • Commissioning proposals form last year: The data will be moved physically to desy soon. ITDM will send an e mail aroung to inform the relevant people.

EET

CAS

  • Who is responsible for the bunch pattern recording for the different instruments? CAS will clarify with ITDM and AE. ==> Ongoing.

SRP

  • The self rescue training is supposed to become part of the access requirement in the DACHS system for the tunnel. This caused a lot of concerns during the meeting (visitors? Access to components only in the very firrt part of the tunnel ). PSPO will discuss with SRP .==> SRP is trying to find a way to minimize the impact of this training on the XFEL employees. Discussion with DESY needed. ==> The implementation date is the 01.05. The legal requirements are quite strict. SRP is trying to find a solution with DESY (proper training every 3 yrs + yearly updates? to be seen). Advice from SRP is to get the training. SScherz can support booking the trainings.
  • HED Radiation interlock issues: no agreement yet to get beam permission. Another meeting is planned for tomorrow (SRP chairs).
  • Procedures for the electrical safety trainings and appointments are being clarified (UB, TH, WUS)

AoB

  4   06 Feb 2019, 11:13 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 06.02.19

SPB/SFX

  • AGIPD commissioning and tests. ==> intervention on the wings is ongoing.
  • CSS component commissioning. RBean is discussing with AE. By the end of the week the changes could be implemented.
  • Loop 14 (Jungfrau) is needed for next week to start the commissioning. AE infrastructure is ready. The CAT cables measurements not compliant with XFEL standard, have to be re-measured. It was supposed to happen on Monday, but Fa. Bohn had problems with the measuring device. PSPO tries to apply pressure and get it done asap. In parallel AE will communicate to ITDM the number of ports required to prepare a temporary connection between D.22/D.23.
  • CRL implementation in the hutch will happen in April. AE and EET involved.

FXE

SQS

  • REMI chamber was installed. Final modifications to the DPS were done. Now the system is pumping down. Bake will be turned off during the WE.
  • CYoungmann is commissioning the Mpods.==> Working now.
  • The chain digitizers-triggers-software is being commissioned to allow online analysis. AE, CAS required and involved.==> Ongoing
  • New requirement document will be submitted today for a new slit system component (not for this SD). ==> Ongoing.
  • exhaust line for explosive gases has not been tested so far and no information is available to SQS. Urgent. SRP should comment.==> MMeyer is following up the issue.

SCS

  • PLCs have been all installed. Firmware deployment has to be pushed. AE is on it.==> Ongoing and high priority.
  • 1 Terminal needs to be exchanged. It is needed for next week. Eplan has been updated. AE has to implement the change now.
  • Concerning the smaract stages a technician is today here. If anybody is interested, please contact JTDelitz.==> The component has 17 motors but only 15 were included in the CRD and therefore controlled.
  • Detector group is working on the fastCCD. ==> Today the cooling rod will be installed.

MID

  • Issue with the remote control of the ion pumps. It is not possible to switch on and off the pumps remotely due to the fact that a wrong terminal was used . It seems this was also the same issue in SASE1 and 3. AE and EET are on it to fix it and update the doucumentation. ==> MS is doing some test today to see whether the tunnel solution could be implemented in a provisional way.
  • Fa. Schulz did not manage to pull all the MID EXP cables by Tue afternoon as requested. Fine tuning of whoch cables are needed to start the loop commissioning and whoch ones can be postponed has to be done and driven by EET/MID (M. Flade/JHallman) ==> Being finalized.
  • On Monday afternoon (17:00) a power cut caused by works on the SASE emergency power off caused the PLC to be switched off and additioanl efforts to bring them on again. This intervention was not known to MID and not planned in the winter schutdown list of activities. Technical Services is/will be reminded that proper communication is needed.==> Other unexpected power cuts due to MPS works both on Monday and today. The communication has to be improved (via SRP). In addition, also an automatic chain of communicaton has to be set up (TS?) to notify relevant peopole when the power is down.

HED

  • Loop 2 needed for commissioning. ==> Commissioning starts tomorrow.
  • Tomorrow the commisisoning of the monochromator in the tunnel and CRL in the optics hutch will start. ==> Mono 1 and 2 commissiong is ongoing.
  • hires mono water connections will be reworked in March.

 

OPT Lasers

  • In SASE3 commisioning isd ongoing and there are no concerns about having the laser ready in July
  • In SASE2 commissioning of the seeder started.
  • Issue with the door is being discussed with TS. ==> Door being fixed. Then the commissioning can start.

XRO

 

  • In SASE3 additional safety shutters issue: Hardware will be ready by middle of Feb. On the 24 and 25. the installation and the modification of the EPS loop should take place if D3, SRP agree on the change request proposed by HS and MD. AE is involved and has allocated resources. It is not clear to whoch extent CAS is involved. This should be clarified, also for proper CAS resourced allocation. ==> No feedback received but CAS is not involved a lot (mainly AE).
  • For this friday SRP schedule a test of the GATT. SQS/SCS informed and part of the activity. ==> Successful.
  • During the installation of mirrors for SASE3 with InGa an issue occured. While pumping down (slowly) foam was generated and it required baking of the system to be able to pump it and bring it to ion pumps vacuum level. Tests are needed to finalize the proper procedure. In general, all the instruments dealing with mirrors should contact XRO (M.Vannoni) for proper venting and pumping down of the system to avoid surprises.

XPD

VAC

  • Mono in XTD6 commissioning. AE and XRO involved.

DET

  • AGIPD calibration is being prepared

AE

  • DESY will reboot the timing system next monday. BF circulated a mail about that. ==> Has been postponed. No new date yet.
  • Instruments have been already informed about the new timing feature.

ITDM

  • Switch of the storage in SASE1 was succesful. Testing ios ongoing. OK so far. In the next days other tests with detectors will be done. (IBM technician also at XFEL today) ==> Done. Test to check the possibility for the users to read directly the raw data is being done.

EET

CAS

  • Gateway has been updated.
  • Karabo roadmap will be sent by mail in the next hours

AoB

Next technical integration meeting (Wed 13.02) will be anticipated at 9 due to the General assembly called for 10:00.

  51   05 Jun 2019, 09:59 Gerd WellenreutherGeneralInformationMinutes of the Technical integration meeting 05.06.2019

FXE

SPB/SFX

  • few days of beamtime remaining, no particular issues
  • preparing for emergency power off
  • preparing shutdown activities with EEE

SCS

  • beamtime, no particular issues.
  • preparing for shutdown
  • XGM is supposed to run even despite the emergency power off ==> M. Teichmann is in contact with T. Schoen (TS)

SQS

  • beamtime, first scattering images taken using the pnCCD!
  • preparing for shutdown, in particular some cabling together with EEE

 MID

  • Integration of the LDM: Safety document is needed. ==> This is needed ASAP!!! ==> THIS IS STILL NEEDED!!!

HED

  • CAS was able to follow up regarding the request for test of triggering / pulse on demand from this Monday. HED was kind of lucky, CAS would appreciate some further notice next time...
  • Due to missing endswitches / interlock conditions, some YAG-screens have been burnt. HED would like to try to get this fixed in the tunnels and the hutches still in this shutdown by installing endswitches etc., to be negotiated with EEE
  • The bias teeth(???) used by HED are not being supplied any more, new ones are not performing ==> to be checked with other instruments / EEE, Sato-san was suggested as another expert to ask.

Optical lasers

  • everything fine, thanks for the support!

VAC

  • Requested to see the first pump + valve of SPB/SFX ==> to be clarified by VAC, SPB/SFX + EEE

XRO

XPD

DET

EEE

CAS

ITDM

SRP

  • From SBP/SFX: Currently, it is not clear what to do if one of the Pandoras goes off. This apparently happened @ FXE on the night from Sat.-Sunday, and it took 12 hours to fix it.

TS

  • From CAS: TS should not rely on email alerts to monitor the cooling of the servers running for example the email services...

AoB

  63   03 Jul 2019, 10:18 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 03.07.19

XO

  • In SASE3 the apertures of the GATT have to be realigned. The upstream apertures have been alreadz realigned. The downstream ones will be probablz realigned tomorrow. If not succesfull some restrictions of the operation have to be evaluated.

FXE

  • Loops update has to be coordinated between EEE and FXE. No feedback received from EEE. AG will remind TKorsh. 

SPB/SFX

  • Loop updates continue.
  • Loop 8 will be commissioned on monday with EEE.

SCS

SQS

  • Aerosol will be commissioned next week. EEE waiting for the precise dates.

​​MID

HED

  • Suffered overhead due to the power cut occured on Monday.

Optical lasers

VAC

  • All XTDs apart from XTD 6 and 9 will be closed on Monday
  • XTD6/9 will be stay opened until Tuesday. Confirmation will be given during the dispatch meeting on Monday.
  • XTD1,2 ready for beam formt he VAC point of view
  • XTD6 -  mono works ongoing.
  • XTD9 -  Maybe worls planned by FXE on the gratings. To be double checked whether it is feasible.

XRO

XPD

DET

EEE

  • Electrical safety regulation. From the beginning of July the new electrical safety regulation is supposed to be in place. According to this regulation the work at the back of the racks in the XHEXP1 and in the entire racks in the tunnels can only be done by certified EFK (Elektrofachkraefte) or by EUPs with an additional training. The additional training can only be provided after summer. The nomination of XFEL EFKs is suffering a delay due to the fact that is not clear who should nominate them (TS, UBR, HR?).  PG reported the problem and also the fact that no official statements were made in the past concerning the topic. THaas is trying to clarify the status, and come up with a statement and proposal in the Operations meeting. ==> there was no meeting on Friday. Still pending.

CAS

ITDM

  • Additional CAT connections planned for SQS, FXE, SCS were installed and approved by ITDM.
  • During the maiinenance of the cooling water system the doors of the balcony rooms and racks were left open to cool down the electronics. Although in the past that worked, it is no longer the case. ITDM will discuss with MKK2 how to make the cooling of the balcony rooms more efficient during planned mainenance of the cooling water system or in case of emergency.

SRP

TS

AoB

On Monday Torsten Schoen informed AV that the power went off in MID and HED experiment hutch because of the radiation interlock test. This was due to the fact that according to the original plan (circulated and approved at the beginning of May), the SASE1 test was supposed to happen on Monday and the SASE2 test the day after. On monday, SASE1 system was accordingly bridged to avoid issues with the power. A last minute change in the plan was agreed between MID and MPS but the info unfortunately did not reach Torsten, hence the issue. Also, nobody from SRP, D3, HED was timely informed. 

There was obviously a lack of communication that has to be improved. AV will write a report and circulate it to the involved people for review and provide it to the MB.

 

  28   03 Apr 2019, 10:44 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 03.04.19

SPB/SFX

  • CRL implementation in the hutch. Cables at the back of the crate have been re-shuffled by EETf. VAC vessel had a leak and is being re-sealed and pumped. If everything is fine and the vessel can be brought to the hutch the motors test can in principle start already this week.  Interaction SPB/SRP ongoing to define operations parameters.
  • CSS Test have been started. 3 encoder connectors need to be fixed by EETf (not sure can be done by the end of this week).
  • AGIPD motion. Test ok.
  • Julabo chiller: waiting for feedback from Julabo to know whether the chiller is going to be repaired on time for next users. If not, SPB/SFX are trying to borrow one from CFEL. VAC interlocks would not be operational due to the different type of chiller. Needs to be evaluated and eventually take the risk (DET, SPB).

FXE

SQS

  • Loop 8 and 11 HW will be prepared by AE. Ongoing (AE/SQS coordination ongoing)
  • Meeting organized by PGessler to review the recurring issues with the digitizers. The outcome is that for the next users run the zero suppression mode will not be used (only raw data - confermed by SQS). In this case, no issues are expected. In the meanwhile a general solution will be worked out.

SCS

  • DSSC undergoing tests in Hera south. If OK, next week will be brought to the hall.
  • Loop 13 running but incomplete. Loop 11 being prepared. Nano motion controls now in this loop. 

MID

  • Smaract stages do not work propery and reliably. High priority. Has to be clarified with AE since it is not clear whether this is the same issue that SCS had and for whoch they developed a workaround. ==> BB will contact the Smaract company to address the issue.
  • Loop 9 has been updated and the flow meters can now be read.
  • Epix chiller has issues. Being investigated by MID and eventually replaced.

HED

  • Cables and loops for HED instrumentation. All the phase II cables needed for operation have been promised to be installed by the end of this week. Loop 5 cannot be available before.
  • 2 weeks ago the HR mono loop was mistakenly updated twice and the second time parameters were not saved (Fri evening). Sat morning was fixed again. AE confirmed it was a misunderstanding because of paralle pulse picker tests. HR mono conversion factors commissioning ongoing.  

 

OPT Lasers

  • SA3 trigger stopped working today. PP laser is down. The timing server in the balcony rooms was found to be down. BF is investigating what happened.

XRO

XPD

  • Hirex 2 - Crates being included in the loops by AE.

 

VAC

DET

AE

  • Waiting for the finalization of the MID LDM risk assessment from SRP to allow the usage of the remote control of the device.==> SRP is working on that. 75% done.
  • 5Hz operation mode tests planned for this thursday. It has already been communicated to the instruments.

​​ITDM

EET

CAS

SRP

TS

AoB

  • Next week XTOB 1.01 will not be available. Most probably the meeting will be held at the mockup control room. AV will anyway send a reminder.
  20   15 Mar 2019, 11:27 Adriano ViolanteGeneralInformationMinutes after dispatch meeting 09.00

SPB/SFX

  • No major issues reported
  • Motors in Loop 14 have been tested and problems with the motion sign and encoder were found. AE/EET on it.

FXE

SQS

  • Issue with digitizers not working was found this morning and was reported solved during the meeting by CAS.
  • 2 CRDs for the pn CCDs are coming. Once they are there it has to be seen how to schedule the design, production of PLCs, as well as of cables.

SCS

MID

  • It is reported by CY that, in order to advance with the Epix readiness, would be beneficial if AE and EETF could accelerate the power system work BKF 467 crate completion (with Bernard's latest change request) plus patch-panel planning Eplan update this would be much appreciated. MFlade reports the request to his group.
  • Issues with Smaract stages cables. Fixed.

HED

  • Si mono in XTD6 had problems with the pitch motor whoch does not work anymore. XTD6 was opened yesterday for intervention and the system was pumping overninght. Interlock modified not to stop operation during the night for MID. This morning ZZ foreseen to complete the intervention.
  • Firmware for Loops 5 and 7 ready. KS/EET are checking whether all the cables for loop 5 have been installed. When they are, AE will be notified to switch on the loop. Same for loop 7. After the meetgin with compkany Schulz it was said that all the priority 1 cables (set by HED) will be installed by 05.04.
  • XGM/Pulse picker alignment has to be checked. On monday AE will have a look.

OPT Lasers

XRO

​​XPD

​​VAC

AE

ITDM

DET

  • Delay scan in MID was successful

EET

CAS

  • Control of personal interlock shutters will be possible through one computer for each instruments control room. PCs have been defined. Implementation can be ready by next week.

AoB

  • GW asks the intruments to check the shutdown planning, especially for the cases in which the instruments are requested as support groups (MPS?). If there a re problems or something does not make sense, please notify PSPO.
  6   11 Feb 2019, 09:59 Adriano ViolanteGeneralInformationMInutes of the dispatch meeting 09.30

SPB/SFX

  • Beam is back on Wed. night.
  • IT cables in D.23 were re-measured on friday. Probemessung was OK. Waiting for the complete set of measurements. PSPO pushes the company.
  • Updates+testing of the AGIPD with the CFEL experts is ongoing.
  • interlock definitions were updated.

FXE

  • Last Thursday an alarm signal was heard from the control room and only entering the hutch it was realized that an additional radiation sensor was triggered, maybe due to a spike. The procedure and actual usefulness of the device should be commented on by SRP.
  • An additional beamstop will be installed otday in the hutch. This requires to OGT3 to be moved.
  • Performance issue with the digitizers when all 3 of them are used in parallel. AE on it.

SQS

SCS

  • Beam is back on Wed. night.
  • Today Loop 7 and 9 will be updated. Loop 7 includes the fast ccd motors and will be tested after update.
  • Smaract stages have to be tested with AE (today/tomorrow)

MID

  • Marjan is supporting the commissioning of components in the hutch.
  • Loop11 is probably already containing all the required components. JH will send a confirmation email to NJ today.

HED

  • Problems with the HV ion pump cables in the HED optics. Many of the cables failed the final test and showed sparks. KS, EET are in contact with Fa. Schulz to solve that. It is not clear whether this is a showstopper or the pumps could be operated locally.==> Fa Schulz will fix the connectors on site.
  • Loop1 is being commissioned (Gauges and gate vales are included)

OPT Lasers

XRO

​​XPD

VAC

AE

  • DESY is restarting the timing serve today at 11am. This will not affect the train ID. 
  • No feedback concerning the additional B4C controls in SASE3. Waiting...
  • Material for the trigger boxes is available at AE

ITDM

  • Issue with the DAQ was discovered (cameras/digitizers): problems occur when more than 1 camera is using the same data aggregator. Investigation and fix is ongoing. DAQ will need to be re deployed only for these aggregators between today and tomorrow. Tunnels and instruments affected. AGIPD is not affected.  

DET

  • Test of the Jungfrau foressen for tomorrow at SPB, for the end of the week for FXE. SCS fast CCD also needed asap.
  • online preview feature was deploted for SPB. FXE next week.

EET

CAS

  • Yesterday OCD was called by JG because of some problems with the data sources. This was found to be a configuration problem. Going to be fixed today.
  • CRL in XTD1 2 lenses are disconnected. They do not nmeed to be included in the Karabo scene.

AoB

  11   22 Feb 2019, 12:36 Adriano ViolanteGeneralInformationMInutes of the dispatch meeting 09.00

SPB/SFX

  • Pulse picker commissiong - Issues concerning motors position and triggers ==> To be worked out with AE, but beam is needed. Has to be done.
  • DET group is helping setting up the Jungfrau detector (w/o PLC).
  • DAQ performance test performed yesterday.
  • Trigger for ns laser is needed next week. Everything should be already prepared but BF checks.

FXE

SQS

SCS

MID

HED

  • Commissioning of components ongoing. There is a learinig curve concerning Karabo.
  • Cabling issues and CR are being followed up with high priority by EET
  • A camera is needed in the tunnel to align the spectrometer. Either a webcam or the camera dedicated to the second spectroemeter has to be moved (only temporary - no definitive changes needed). This can be done with a ZZ access on monday. KA is organizing the hardware, CAS and AE will take care of software and evetaually trigger.

OPT Lasers

XRO

​​XPD

​​VAC

  • On monday the HW for the B4C in SA3 will be mounted. and tested. No loop updates concerning the interlock. This will happen in march.
  • GATT loop update for SASE3 planned for Monday

AE

  • A PLC in HED has to be replaced because of some beckhoff license that expired ==> Problem solved replacing the PLC. Whys did this happen is still not clear.

ITDM

DET

  • SCS took data with the fast CCD. Data has to be analyzed but seems ok. ==> Ongoing
  • SPB agipd OK==> Calibration is now running.
  • FXE LPD had issues being followed up

EET

CAS

  • Kickoff meeting with ITDM to start to evaluate InfluxDB, Grafana and Elastic Search as an alternative to the current Karabo DataLogger implementation (LA and VAC represents use cases to be addressed/solved). However, "nothing" will impact operation in the next months.
  • SPB Loop 14 needs to be deployed (Karabo)

AoB

 

  75   02 Aug 2019, 09:10 Adriano ViolanteGeneralInformationInfo on dispatch meeting 09.00

The meeting did not take place since only EEE was attending.

  Draft   30 Mar 2020, 08:57 Andreas Galler   

CTRL:

  • Broker Pile Up in 4 topics over the weekend
    • LAS affected in all topics, LA2 even twice
    • SPB affected once
  • mitigation startegy worked

EEE:

  • nothing to report

VAC:

nothing to report

 

XPD

  • vac systems in the lab had been secured --> secuvac valves installed plus webcams

DET:

  • nothing to report

ITDM:

  • exflgateway hardware problem on Saturday --> fixed

XRO:

  • nothing to report

SPB:

  • rough pump turned off, possibly lack of cooling water
    • interlock tripped --> pressures raised
  • were able to set remotely

FXE:

  • nothing to report

MID:

  • everything is fine

HED:

  • VAC is fine, ion pumps are on, no roughing pumps running

DA:

  •  

 