| ID |
Date |
Author |
Location |
Severity |
Subject |
|
174
|
03 Nov 2020, 08:39 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 02.11.2020 |
General Announcement:
- A. Galler reminds the attendance that this meeting is also an opportunity for making comments/questions on the new Covid-19 rules that start to take place.
CTRL:
- Main issue last days was related to the SA3 VAC PLC. The applied fix was left running during the weekend. So far it works faster and reacts faster for diagnostics.
CTRL is getting some statistics in order to get the final solution. If something goes wrong, please call OCD.
- No OCD calls during the weekend.
DA:
- No issues or news.
EEE:
- uTCA crate of SA2 balcony room is not reachable. A quick fix on Friday was not successful and EEE needs to power cycle or replace the whole crate.
This will interrupt timing for PP-laser and the signals sent to MPS. Meeting between EEE, lasers, instruments and XO will take place.
- (Note after meeting: the power cycle of the actual crate will be done today after lunch. If this does not helps then immediately exchange of crate will be done
afterwards.
PP-laser will be brought to a safe state and takes about 4-5 hours to restart it).
VAC:
- Nothing to report.
XPD:
- Worked at BKR with MCP detectors. XPD reported to CTRL an issue with ADC - some channels see no signal or not standard ones.
EEE knows and runs some scripts - this happens from time to time and may affect recording data.
- In general, from XGM side, Theo M. has prepared a way to switch settings to extreme changes of photon energies.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Nothing to report.
UNSYS:
- Motor problem with SA1/cell31 last week was repaired and undulator should be working fine.
SPB:
- STAB campaign last week went fine and collected data that has to be analyzed.
FXE:
- Nothing to add.
MID:
- Waiting for invitation to a meeting on the AGIPD train-ID.
HED:
- Requests the beam delivery schedule in order to know if has to schedule people for Tuesday night.
SCS:
- Not present.
SQS:
- Nothing to report. |
|
553
|
02 Oct 2024, 09:41 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 02.10.2024 |
General Announcement:
-
CTRL:
- Announcement by Dennis Goeries: next week on Tuesday a test phase is to start with login / authentication in Karabo. An e-mail is to be sent to xo-info. The group accounts will have limited access.
DA:
- Update on investigation of issues with services last weekend: user that was scheduled by chance could access it but not run jobs. Security will be made to avoid people breaking into it in future.
EEE:
- Nothing to report.
VAC:
- Everything is fine.
XPD:
- Nothing to report.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Not present.
LAS:
- Not present.
UNSYS:
- Not present.
- ZZ in SA1 took place yesterday to fix a phase shifter.
SPB:
- Nothing to report.
FXE:
- THz has started.
MID:
- All fine at MID.
HED:
- Not present.
SCS:
- Nothing to report.
SQS:
- Not present.
SXP:
- Not present. |
|
456
|
02 Oct 2023, 09:59 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 02.10.2023 |
General Announcement:
-
CTRL:
- Deploy dataloggers fix today; it takes around 5 minutes.
DA:
- Couple of OCD calls over the week that could be all addressed.
EEE:
- PLC team checking motors in SQS to test issue.
- uTCA team: 1. replace a CPU at MID (possible); 2. digitizers at HED will be replaced by uTCA team to improves setup;
- Also install power supply at SQS.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- Last week started bumpy but operation stabilized later on.
ITDM:
- Nothing to report.
XRO:
- XTD1 attenuator: one arm is blocked; after speaking with SA1 instruments the decision is to wait to fix during the winter maintenance. In case of urgencies to use it please contact Maurizio V.
LAS:
- Issue with FXE laser: will need CTRL to help debug;
- AMPHOS issues at PP-lasers are solved.
UNSYS:
- Nothing to report; all fine.
SPB:
- Test with machine tomorrow / taking beam.
FXE:
- Nothing to report.
MID:
- Nothing to report.
HED:
- Nothing to report.
SCS:
- Not present.
SQS:
- Nothing to report.
SXP:
- Nothing to report. |
|
544
|
02 Sep 2024, 09:53 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 02.09.2024 |
General Announcement:
-
CTRL:
- Today an IT update on project database at 13:00: 15min service is not available (not able to open them). Reminder will be sent.
DA:
- Note after meeting: Nothing to report.
EEE:
- Nothing to report.
VAC:
- Pressure spike in SA1 vacuum system that tripped interlock but it was quickly recovery on Thursday.
XPD:
- Nothing to report.
DET:
- Issue with Julabo chiller at AGIPD still persists as test last week did not succeed.
ITDM:
- Nothing apart of the mentioned CTRL report.
XRO:
- Vacuum spike was caused by the one motor at M1/SA1 being loose; Incident with InGa spillage in mirror chamber as a result;
- M1 Rz motor was reconnected and mirror was put in place again but now should not be moved anymore and it is interlocked.
- On Saturday beam was found back at SPB/SFX (saved trajectory at one photon energy; for others have to be checked - please do not rely on previously saved positions).
- Beam was not yet found at FXE – M3 reflection at the M3 Pop-in still seen but not further downstream.
- In case of need please do not hesitate in contacting XRO and Antje Trapp for help.
LAS:
- SA1 PP-laser NOPA alignment starting today for delivery tomorrow as AMPHOS service is done.
UNSYS:
- Quad mover stuck in cell7/SA3; needs ZZ.
- Apple-X activities during FD week had re-alignment with beam; found issue with one CAM mover in cell#25.
SPB:
- Chiller for AGIPD: tests did not get enough temperature.
FXE:
- Nothing to report.
MID:
- All fine at SA2.
HED:
- Getting ready to take beam.
SCS:
- Nothing to report.
SQS:
- Not present.
SXP:
- Not present. |
|
157
|
02 Sep 2020, 13:33 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 02.09.2020 |
General Announcement:
- If instruments find the machine is not performing as you expect when comparing to previous weeks, please contact PRC that he may help you to address it.
This is also valid for changes of beam parameters if not previously reported in the operation tables.
CTRL:
- CTRL is supporting the ongoing Laser installations.
DA:
- Nothing to report.
EEE:
- Fast ADC in HED: this is solved. The only limitation is if the system is restarted the ADC is misconfigured. In this case please inform EEE for loading the
configurations.
- SCS switch issue is also fixed.
VAC:
- Working on the M3/SA2 mirror. Mechanical problems were fixed by XRO. Leak test ongoing and closure of the tunnel afterwards. Beam can be back to XTD6 this afternoon.
XPD:
- Nothing to report.
DET:
- Nothing to report.
ITDM:
- No big announcements at this moment.
XRO:
- M3 mirror: mechanical axis was disconnected and mirror was not moving. XRO and VAC fixed the problem. Hopefully beam can be injected to XTD6 this afternoon.
- It was chosen not open the full chamber to make the repair in 2 days' time. As beam is there XRO will re-align mirror. Cooling system is disconnected.
- After closing tunnels, it will allow beam in MID certainly and to HED we will look after the re-alignment of the mirror (to be scheduled). Maurizio V. is open to
clarifications/discussions.
- Ulf asks on the plans for re-alignment of the beam: Maurizio says either after the Self-seeding on Friday or on Monday.
LAS:
- Upgrades are ongoing in all lasers: a bit behind schedule.
- SA1: ADC has to be serviced by EEE; SA2: delays due to microTCA.
- SA1 and SA3 shall be available tomorrow afternoon.
- Tests with HED laser pattern on demand: LAS demands to be included in discussions for October use of PP-laser. Synchronization must be developed to run properly. LAS
can't guarantee it will work from the first try.
- Cw37: SCS needs laser, as well as MID has preparations. LAS states both lasers shall be back in operation on THU afternoon shall be available.
UNSYS:
- Nothing to report.
SPB:
- Getting ready for test experiments and commissioning.
FXE:
- Nothing to report.
MID:
- Setting up for user experiments.
HED:
- Waiting for M3.
SCS:
- SCS/XGM presents issues with interlocks being activated due to pressure levels. This required intervention from expert.
If this happens in the middle of the night, SCS proposes to develop an automated way to reset it or to be trained by XPD experts. XO, SCS and XPD will follow up.
- Extra-foam: SCS asks on the possibility for access to remote users. DA says is under discussion between DA and ITDM to extend the service but no decision has been made.
It will anyway need access to online clusters.
SQS:
- Not present. |
|
440
|
02 Aug 2023, 10:12 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 02.08.2023 |
General Announcement:
- Status of machine: a lot of work was done last days on laser injector and RF jitter; all seems to be OK and improvement were done.
Concluded that electron beam shape is now Gaussian and right now SASE is being tuned. Aim is to have about 2mJ in SA1 and 1mJ in SA2 at 9keV. Beam to be handled to the instruments on Thursday morning, as
planned.
- MID HED asked on use of HXRSS this week/next week. To be discussed at the daily Ops meeting today.
CTRL:
- Investigating the MOV loop in SA3 watchdog.
DA:
- Nothing to report.
EEE:
- Routine checks in rack for instruments (currents for ground lines). One rack presented an issue and today there is a plan to disconnect the wrong wiring line and a second power will be installed.
No impact shall be seen on motors using 40V at SQS.
VAC:
- Nothing to report.
XPD:
- If HED or MID goes to use seeding then N. Kujala has to setup the Hirex.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Progress in SA1 PP-L going well.
UNSYS:
- Error in gap of SA1 cell 10 undulator. It seems to be fine now.
SPB:
- Preparing for the shifts from tomorrow.
FXE:
- Nothing to report.
MID:
- Will discuss with HED on the using of beam for next 2-3 weeks.
HED:
- Nothing to add.
SCS:
- Nothing to report.
SQS:
- Not present.
SXP:
- Nothing to report. |
|
247
|
02 Aug 2021, 12:06 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 02.08.2021 |
General Announcement:
-
CTRL:
- Deployment announcement: there are two more motors to be updated on ARAVIS cameras (photonic and Bassler). CTRL proposes to do this afternoon.
Cameras devices will be down after update, aimed to enable train-ID corrections. Please instruments check on Tuesday if cameras are back.
DA:
- Nothing to report.
EEE:
- uTCA CPU in SA1 balcony room is not reachable. Bruno F. is investigating.
- CPU of LOOP16-SQS is not reachable. Nerea J. will check it today.
- Issues with LPD and AGIPD are being tested in the lab and the check at FXE will be done later today.
VAC:
- Some OCD calls related to instability of SA3 vacuum loop. DOC is informed and shall be working on that.
ME:
- Alberto De Fanis asked if ME is present, willing to discuss topics. A. Galler says group was around a couple of times and if groups have questions please use this meeting series to address.
XPD:
- No issue to report.
- Steffen H. will check if some XPD tunnel devices are affected by the ARAVIS update.
DET:
- Nothing to report.
ITDM:
- Influx problem on Thursday (disabling live-view on Karabo): with help of Influx data support this was fixed. The cluster is up and running well.
The part of the old data during the time it was down was written by Grafana and will be synchronized back to the cluster during this week (tests are needed).
- Following on Friday for the Influx third node that went down (not related to the previous incident): DOC was blind for a couple of hours. Investigation ongoing. It's not related to Grafana.
Instruments were not affected.
- Reminder of reviewing and closing proposals for the second half of this year. Please look at the sent e-mail and make a cleanup.
XRO:
- Not present.
LAS:
- All PP-lasers are running.
UNSYS:
- Issue with phase shifter in SA3 for the 3keV use: problem is that at 14 GeV the tables of phase shifters go to 25.3mm gap and this is in the upper limit for making 3 keV.
Phase shifter tables will be extended to a larger gap. Better to use 3keV at higher electron energies.
- For the UOM's mention on the update of phase shifters on the chicanes, this has to be prioritized. XO will discuss with Sara C.
SPB:
- Minor issues with SPB imager being saturated. A. Koch adds that it will be followed up and he is aware and will analyze better.
- Organization limitation: RF discussion for last weekend. The BKR / Operators were not aware they would use 404 bunches and costed 2 hours.
FXE:
- Nothing to report.
MID:
- All fine at MID.
- Laser went down for 12 hours due to the issues with HED interlocks on Wednesday (action taken due to the restart of laser interlock performed by SRP).
HED:
- Not present.
SCS:
- Issue on the scanning speed of monochromator. Parameters will be adjusted with Marijan S. today.
SQS:
- Loop for moving DSSC got a fault but has been addressed by EEE. |
|
625
|
02 Jul 2025, 10:03 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 02.07.2025 |
General Announcement:
- M. Doering announces on the LIMP-25:
1. Old's AIBS removal is starting already this week (today), after agreement between Inaki de Diego and instruments;
2.This Saturday 5.07 the shaft building 3 has a training for the fire brigade so no work can be done in this shaft building;
- M. Doering announces for next week:
1. Tunnel racks will be opened;
2. EEE racks in balcony rooms and Laser rooms will be OFF;
3. Cooling water: MID cooling water will be placed OFF next week;
3. Electricity: affecting SA1 (9-10.07) and SA2 afterwards; UPS work on 12-13.07 will affect the DACHS system (no access to Experimental Hall and emergency OFF of lab levels).
- Above info can be found at Alfresco's XO page.
- A. Galler announces machine has been warmed up.
CTRL:
- Nothing to report.
DA:
- All quiet at DA.
EEE:
- Nothing to report.
VAC:
- All fine accordingly to the plan.
XPD:
- Everything fine.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Nothing to report.
UNSYS:
- SA2: the monochromator space for rack installation is free; also valid for SA1.
- SA1: undulator moved from cell#17 to cell#1.
- SA2 crates from cell#1 and cell#2 to downstream are not yet free for move (expected to happen in about 2-3 weeks).
SPB:
- Preparing for the ramp down.
FXE:
- All was ramped down and preparing for switching OFF next week.
MID:
- Nothing to report.
HED:
- Finishing with ramp down until Friday.
SCS:
- Bringing beamline to shut down.
SQS:
- Not present.
SXP:
- Not present. |
|
617
|
02 Jun 2025, 09:51 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 02.06.2025 |
General Announcement:
- The ongoing delivery sees a HXRSS at 12GeV with 1mJ total intensity (~350uJ background).
CTRL:
- Nothing major to report.
DA:
- Nothing to be reported.
EEE:
- Nothing to report.
VAC:
- Not present.
XPD:
- No issues to report.
- Big brother stopped SA1 because of HIREX power limit: J. Gruenert reports that all pulses of the train are now being seen by Big Brother and things worked as expected.
DET:
- Nothing major to report.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Ticket was discussed for SPB (timing issues): under investigation and a bug on the code has been found and is under work.
UNSYS:
- Issue with PS in cell#8 in SA1 was already fixed remotely.
SPB:
- Two issues: 1. HIREX watchdog needs a change of filter then works fine; 2. Issue with sample delivery leads that SPB will not use beam tonight (FXE can take if wanted).
- uTCA tested a monitor for received timing info together with ITDM and this test was performed parasitically at SPB.
FXE:
- Nothing to report.
MID:
- Nothing to report.
HED:
- HXRSS performance this week is excellent.
SCS:
- Not present.
SQS:
- Nothing to report.
SXP:
- Not present. |
|
229
|
02 Jun 2021, 10:24 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 02.06.2021 |
General Announcement:
- XO reminds staff to check the safety trainings and the DACHS access rights/permissions for the tunnels when planning tunnel accesses during the maintenance period.
- A. Galler asks all instruments who work with X-ray beam that in case it is found any damaged component, please take a snapshot and post in the operation e-log.
This allows to get known prior/during the maintenance period.
- Last UOM prior maintenance period takes place next Friday.
CTRL:
- For the maintenance period: CTRL will send around the Karabo schedule for updates such as MC2 motors. CTRL will get also in touch with affected people.
- Macro update announcement on Monday will not take place anymore.
DA:
- Nothing to report.
EEE:
- EEE is gathering and scheduling all shutdown tasks and will start next week with tunnel works.
- SASE1 VAC, EPS and MOV, and SASE2 MOV2 loops will be updated next week.
- EEE will also assist, if needed, on the testing of the Mc2 interface migration that Steffen H. / CTRL has informed.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- This is the last week of DOC operation. The DOC will re-start on cw28.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Man Jiang reports all 3 PP-Lasers are running.
- SCS can't open the shutter (interlock issue) but this is not related to LAS.
UNSYS:
- Nothing to report.
SPB:
- DOC has contacted SPB saying Maxwell calibrations failed. This will be checked.
FXE:
- Nothing to add.
MID:
- All fine at MID.
HED:
- Issue with camera at 10:30PM. It Needed to be power cycled. Steffen H. says that the camera worked this morning. Maybe case is already solved. One will keep an eye if
it happens again.
SCS:
- Issue with Interlock mentioned by LAS. Pouneh S. is working on it.
SQS:
- User operation this week including optical laser.
- Thomas B. says SQS struggles with temporal overlap but spatial overlap is fine. They have first to find clear signal to investigate more on the temporal overlap. |
|
321
|
02 May 2022, 07:27 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 02.05.2022 |
General Announcement:
- Martin Doering gives update on the maintenance planning progress: a Dashboard will be introduced and updated every week and almost all groups have submitted the lists.
CTRL:
- Reminder: today at 13:00 there is a deployment of Karabo Beckhoff in the tunnels (motors with newly features). No issues are expected; otherwise a reset may suffice.
DA:
- Nothing to report.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- No incidents to report;
- Two ZZs in tunnels are taking place this morning.
DET:
- Feedback regarding AGIPD at SPB (cw16): one module has to be replaced during the summer maintenance period. Reason behind the damage has to be investigated together with SPB staff.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Nothing to report.
UNSYS:
- ZZ taking place at SA3 cell 14 this morning.
SPB:
- Everything went smooth last week.
FXE:
- Couple of issues with Bassler cameras not connecting or acquiring data (DOC helped).
- Gun trips on the weekend means that one hour is needed to wait until running again Mono (using high heat load). Many gun trips were seen during the weekend.
Raul V. says that a possibility was discussed yesterday at around 09:45AM for an intervention to minimize the gun trips but after consultation with FXE staff it was decided to run in that condition. Peter
Z. says that calling 9-4800 was not reachable.
MID:
- Everything looks good for the last experiment with HXRSS.
- It lost the timing after a big trip on Sunday.
- Frequent broker Pile-ups happened and for mid-term has to be addressed (J. Hallmann). Gabrielle G. and Setffen H. say that a fix is known and in the mid-term it will be solved.
- Problem with multipatern of Laser happened; reported by Angel R.-F. LAS will look into it.
HED:
- CRL3 was tested and enabled it back.
- Tomorrow the mirror vertical motors will be checked together with XRO.
SCS:
- Nothing to report. Only smaller issues that were addressed.
SQS:
- Nothing to report. |
|
601
|
02 Apr 2025, 10:31 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 02.04.2025 |
General Announcement:
- A. Galler reminds instruments that enquiring and requests on beam parameters shall come prior the respective RC meeting. Otherwise it will be difficult to accommodate last minute
changes.
CTRL:
- Performed update of dataloggers yesterday.
DA:
- All fine with DA.
EEE:
- Nothing to report.
VAC:
- Issue with broken power supply in SA3 on Monday 2PM. Downtime of 2 hs and it was fixed by exchanging it in a ZZ.
XPD:
- Nothing to report.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Not present.
LAS:
- Laser system working;
- Last Thursday evening decisions were done that incurred effects on PP-laser and access. An e-mail to XO will be sent with details.
UNSYS:
- Everything is fine.
SPB:
- Nothing to report.
FXE:
- Reported motor issues are fixed.
MID:
- Nothing to report.
HED:
- Not present.
SCS:
- Nothing to report; busy preparing DSSC2 setup.
SQS:
- Nothing to report; ready for beam.
SXP:
- Not present. |
|
305
|
02 Mar 2022, 10:12 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 02.03.2022 |
General Announcement:
- There is a high probability that we will run out of Helium gas due to difficulties with stock. If an instrument needs He on next weeks please get in touch with TS to verify its availability.
CTRL:
- Last Monday intervention on the SA3 GATT middle layer servers was successful.
DA:
- Today a major upgrade of offline calibration is scheduled during which services won't be available.
EEE:
- Supporting different tasks at SQS (recommissioning motors), HED (motor encoders), SCS and FXE.
VAC:
- Ion pump in XTD9 shows a potential risk of tripping interlock: a ZZ on Friday 14:00 will take place to change parameters.
- Another ZZ in XTD2 to attempt to fix the solid attenuator in SA1 (hole in the arms reported by SPB / 0.5mm Si damaged); try to change the blocking mechanism.
- Dmitry K. asks on the Si intervention in XTD2: Martin D. says a change of Si is a major intervention as it involves need of clean tent etc… and will not be done this Friday.
The idea is to use a fresh spot on the attenuator. Conditions for interlocks have to be later checked with Liuba S.
XPD:
- ZZ on Monday to remove Shimadzu camera was successful.
DET:
- Nothing to report.
ITDM:
- Problem with Influx cluster which did not accepted data for 3 hours: search for fixes last days and today a new configuration will be applied, followed by restart afterwards (minutes downtime). No effect
in tunnels DAQ.
XRO:
- Commissioning beamtime for SA2 mirrors: available beamtime was short. The coating stripes were found in beamlines in respect to motor positions. More beamtime is needed to continue commissioning of M1,
M2 and M3 in XTD6.
LAS:
- Nothing to report.
UNSYS:
- Apple-X commissioning ongoing: working on Control systems commissioning. Last cell was controlled; more tests ongoing today. The phase shifter tables are not yet ready.
SPB:
- Working with different groups during the week.
FXE:
- D3 was present on Monday to test the BTM; it was successful.
MID:
- Radiation alarm triggered due to a false alarm at MID hutch. Thomas P. from HED helped by calling RPOs; W. Clement, Eric B. and M. Prollius helped to solve it.
HED:
- Preparing for the high intensity laser and also working on motors.
SCS:
- Not present.
SQS:
- Not present. |
|
297
|
02 Feb 2022, 08:39 |
Andreas Galler | General | Information | Notes XO Integration Meeting 02.02.2022 |
|
General Announcement:
CTRL:
- observation from DOC
- macros some times after the upgrade to Python 3.8 --> please contact CTRL?
DA:
- significant upgrade to Offline Analysis -->
- proc data won't inlcude a copy of raw data any longer
EEE:
VAC:
XPD:
- no incidents
- 2 tunnel accesses on Monday --> succesful
DET:
- DET commissioning at SPB (AGIPD JUNGFRAU 1M), MID (AGIPD), HED (ePIX, JUNGFRAU)
ITDM:
- E0.604 rack room, Wed next week
- fixing power distribution units in every rack --> TS and external company will need a full day
- affected services are: Lab DAQ, LAB control servers (EEE; CTRL, DET), GitLab runners, one machine for data analysis, PLC database, karabo project database (?)
- Yesterday short interruption with influx reading note --> test requested for next Monday causing a 1 hour interruption
XRO:
- SA1 / SA2 M3 PBLMs have been equipped with diamond plates and can be used for beam stability measurements
- Backlash Controls implemented last week --> values
- report of lost positions of vertical slit in SA3
- in case of similar issues please contact DOC prior to self fixing.
LAS:
- SA2 PPL is good
- SA3 PPL planned to be up today
- SA1 PPL being investigated as agreed with SA1 instruments
UNSYS:
- transparency test for APPLE X went successful
SPB/SFX:
- SPB/SFX aligned since yesterday, no issues
FXE:
- blown fuses in crates --> solved with EEE
MID:
HED:
- Com yesterday
- outstanding issue: fastADC not working EEE aware of that
SCS:
SQS:
- GATT always worked but very slowly responding
- OCD contacted
- Raul comments that this is a known issue and should be communicated to CTRL
- SH nesures that Raul creates the ticket
- XTD10_PES
- digitizer display frozen almost all time (connected to 2 DAQs) --> reported to DOC
- SH comments that when connecting to two DAQs (tunnel and SQS), should be connected to only one DAQ.
|
|
283
|
01 Dec 2021, 09:49 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 01.12.2021 |
General Announcement:
- Info that today the 20C cooling water will be switched to the towers was sent. Please also open rack doors to help until further notice. Tomorrow we will understand if cooling water tower is working and
if not, then A. Block and XO will communicate.
- Fire alarm happened this morning but not affecting people working at XHQ.
- Steffen H. says that DOC is not operational until middle January.
- Next Friday there won't be an UOM.
CTRL:
- Start with deployment today.
DA:
- Nothing to report.
EEE:
- Fully busy with preparation works and starting updates today.
VAC:
- Maintenance period activities been prepared. Tunnels are opened - if staff access rights are expired, please contact M. Dommach.
XPD:
- Not present.
DET:
- Nothing to report.
ITDM:
- Starting the maintenance activities today; On-line processes are unavailable until end of the week.
XRO:
- Last Monday: ramp down activities (stored motor positions for instruments with proper beam trajectories; XPD also worked with MCP detectors for all 3 SASEs (not done in SCS);
- XRO activities will be reported during this meeting series.
- Calibration SASE2 mirrors FD proposal was submitted for starting 2022.
- One PC at BKR (middle one) is extremely slow and shall be investigated during the maintenance time.
LAS:
- Maintenance on the PP-lasers are started.
UNSYS:
- Not present.
SPB:
- Not present.
FXE:
- Nothing to report.
MID:
- All fine at MID. It will investigate the water leak that happened this morning with chiller.
HED:
- Preparing XTD6 activity (exchange screen in monochromator) next week.
SCS:
- Nothing to report.
SQS:
- Nothing to report. |
|
465
|
01 Nov 2023, 10:04 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 01.11.2023 |
General Announcement:
- Jan G. as PRC comments: 1. reminds SQS and FXE instruments to place entries at the Operations e-log;
2. machine is running well and ZZ accesses happened on Monday (hindered by issues with tunnel entrance) but all done;
3. the XTD2 issue with upstream differential pump close to the XGM: one pump is defective and VAC will exchange if a ZZ is allowed next week.
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- FSSS motor in MID: OCD received a call yesterday and device was restarted and came back to operation.
VAC:
- Not present.
XPD:
- Nothing to report from XPD.
DET:
- Nothing to be reported.
ITDM:
- Nothing to report.
XRO:
- On the XTD10 ZZ last Monday: V-slit was checked and a faulty cable for the encoder was found. For the time being this was fixed by tapping it and will continue monitoring.
LAS:
- Nothing to report.
UNSYS:
- All fine with Undulator.
SPB:
- Nothing to report.
FXE:
- Beam was not stable the last night / down for few times. To be investigated internally at FXE and reported to XO.
MID:
- Roll motor for M2 mirror at tunnel was moving very slowly; to be seen with XRO.
HED:
- Nothing to report.
SCS:
- Nothing to report; working in hutch preparations.
SQS:
- Nothing to report.
SXP:
- Not present. |
|
273
|
01 Nov 2021, 10:10 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 01.11.2021 |
General Announcement:
- XO is currently setting scheduling meetings with the groups for planning and cross-checking the preparation for the Winter maintenance 2021. Meetings will take place between this and next week.
CTRL:
- Nothing to report.
DA:
- Announcement on the online calibration: for SPB it will be upgraded to Karabo 2.11. Today is preparation and later this week it will be deployed for the user beamtime.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- Nothing to report.
ITDM:
- Together with CTRL and DA and HED/MID instrument: solving hardware problem of online cluster - one has to swap locations of SA3 and SA1. This is ongoing right now.
XRO:
- Nothing to report.
LAS:
- Water leak in SA1. TS is aware and fixing it. The PP-laser was not switched OFF.
UNSYS:
- All is good; The seeding crystal in SA2 is on the right position for the self-seeding. Support will be available for helping the expert.
SPB:
- Nothing to report; Interesting data was acquired along the week and analysis will take few weeks.
FXE:
- Nothing to add.
MID:
- All fine.
HED:
- User experiment;
- Yesterday after midnight beam intensity dropped down from 1mJ down to 300uJ and BKR did not managed to recovered it.
SCS:
- Nothing to report.
SQS:
- Nothing to report. |
|
653
|
01 Oct 2025, 09:47 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 01.10.2025 |
General Announcement:
- M. Doering announces on the LIMP-25 for next week:
1. PLC updates in SA2 and SA3 tunnels (HED postponed to later week);
2. Karabo deployment happening (no availability);
3. Timing system update on Tuesday from 09:00 to 16:00 with interruptions during this time;
4. MKK maintenance on pressurizer for 8C water (e-mail to be sent - please avoid changes on cooling water on Monday);
5. Magnet cabling in XTD10 starts on Wednesday 08.10.
- M. Prollius says hot work permits are allowed again.
- I. de Diego says D3 will be testing AIBS / air boxes systems in SA3 experiments tomorrow (access is required).
- Nerea Jardon says please contact EEE if EEE systems need to be operated during the time Karabo is down.
CTRL:
- Preparing for Karabo3 rollout from today.
DA:
- Nothing to report.
EEE:
- Delay on PLC CPU replacement in tunnels: to be done after Karabo is back.
- Timing systems have to be updates - discussed with LAS already and fine with them.
VAC:
- Everything fine.
XPD:
- Nothing to report.
DET:
- Nothing to report.
ITDM:
- Long standing issue with SA2 storage system: needs to power cycle system probably tomorrow or Monday, when Karabo is anyway down.
- Update PCs in experiment Hall next week.
XRO:
- Not present.
LAS:
- Nothing to report.
UNSYS:
- Not present.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- Nothing to report.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Not present.
SXP:
- Nothing to report. |
|
642
|
01 Sep 2025, 09:37 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 01.09.2025 |
General Announcement:
- There are no general updates regarding LIMP-25.
CTRL:
- No major updates from CTRL.
DA:
- Nothing to report.
EEE:
- PLC updates in tunnels: coordinating with VAC and XPD and updates are still ongoing this week.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- Nothing to report. All fine.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Nothing to report.
UNSYS:
- Nothing to report.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
- Construction of 2nd control hutch at FXE is ongoing accordingly to the plan.
MID:
- All fine at MID.
HED:
- Not present.
SCS:
- Nothing to report.
SQS:
- Not present.
SXP:
- Nothing to report. |
|
256
|
01 Sep 2021, 10:36 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 01.09.2021 |
General Announcement:
- A change of meeting room occupancy will happen soon (increase by some %) and will be posted at each meeting room door.
CTRL:
- Together with EEE, CTRL updated the pnCCD system and is working again. Hardware train-IDs acquisition was used by SQS yesterday afternoon and was successful.
DA:
- Nothing to report.
EEE:
- Nothing special to report.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- Follow up for the pnCCD today (offline calibration fixed). Detector is being cooled down and then data will be collected. DET supports CTRL that one had to make better plan earlier.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Nothing to report.
UNSYS:
- Nothing to report; Cell#16 in SA3 got repaired on Monday.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- All fine at MID.
HED:
- Yesterday the beam was available for delivery later than 15:00 due to issues with machine tuning.
SCS:
- Not present.
SQS:
- Not present. |