Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther, Page 2 of 29  Not logged in ELOG logo
ID Date Author Location Severity Subjectdown Text Attachments
  45   20 May 2019, 10:02 Gerd WellenreutherGeneralInformationStatus report after dispatch meeting Monday 20.5. 09.30SPB/SFX


are working on achieving
a good focus @ 6 keV, which currently is
  
  47   24 May 2019, 11:01 Gerd WellenreutherGeneralInformationStatus report after dispatch meeting Friday 24.5. 09.00SPB/SFX


are working on achieving
a good focus @ 6 keV, which currently is
  
  78   12 Aug 2019, 09:50 Gerd WellenreutherGeneralInformationStatus report after dispatch meeting 12.8.XO

FXE


XTD1 CRLs: There is an
  
  18   11 Mar 2019, 11:58 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30SPB/SFX


Experiments were succesfull
Calibration
pipeline has issues - being fixed
Detailed
  
  21   18 Mar 2019, 10:04 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30SPB/SFX


No major issues reported
Crates
for the CRL will be installed today. Test
  
  23   25 Mar 2019, 11:38 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30SPB/SFX


The Julabo chiller for
the AGIPD detector broke. After intervention
  
  32   12 Apr 2019, 10:41 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30SPB/SFX


Hercules students period.
During the night a pump failed and recovered
  
  33   15 Apr 2019, 09:55 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30SPB/SFX


Tomorrow set up of the
donwstream interaction region will start.
Jungfrau
  
  37   29 Apr 2019, 10:04 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30SPB/SFX


IRDa commissioning
ongoing. Focus (<5um) in the second interaction
  
  39   06 May 2019, 10:20 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30SPB/SFX


IRDa commissioning
ongoing. 
For this week AGIPD
  
  50   03 Jun 2019, 12:57 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30SPB/SFX


No major issues.


FXE


Tool to save motor positions
  
  59   24 Jun 2019, 09:53 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30FXE


CRLs mainteinance has been
completed.


​SPB/SFX
  
  62   01 Jul 2019, 10:07 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30XO

FXE

SPB/SFX
  
  65   08 Jul 2019, 10:25 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30XO

FXE


Loops update has to be
  
  67   15 Jul 2019, 10:01 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30XO

FXE

SPB/SFX
  
  70   22 Jul 2019, 12:42 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30XO

FXE


DAQ issue reported (data
  
  73   29 Jul 2019, 10:16 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30XO

FXE

SPB/SFX
  
  76   05 Aug 2019, 10:19 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30XO

FXE


Photon3 detector has been
  
  44   17 May 2019, 10:47 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.00SPB/SFX


ADC have been requested.
HW should be already installed (SPB to check).
  
  54   14 Jun 2019, 10:47 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.00FXE

SPB/SFX


Getting ready for the shutdown.
  