Notes XO Integration Meeting 19.06.2020, posted by Frederik Wolff-Fabris on 19 Jun 2020, 14:28
|
General Announcement:
- Next Monday it is planned the NOT-AUS experiment in the frame of Interlock tests and the emergency off will be disabled.
Only groups with EQP persons can continue working in the hutches. An e-mail was sent by TS.
|
Notes XO Integration Meeting 17.06.2020, posted by Frederik Wolff-Fabris on 18 Jun 2020, 13:40
|
General Announcement:
- Today and tomorrow it takes place the tunnel ventilation maintenance between 6:30 and 8:00AM;
- An e-mail was sent to readiness list with tunnel access restrictions for next Friday morning at the Osdorf Born site in and XTD4 work between 10-11AM.
|
Notes XO Integration Meeting 15.06.2020, posted by Frederik Wolff-Fabris on 16 Jun 2020, 13:32
|
General Announcement:
- There will be additional ventilation maintenance on all tunnels, scheduled for next WED/17th and THU/18th between 06:30AM and 08:00AM.
We request staff to do not enter in tunnels during this period.
|
Notes XO Integration Meeting 12.06.2020, posted by Frederik Wolff-Fabris on 12 Jun 2020, 13:48
|
General Announcement:
- There will be tunnel ventilation additional maintenance on two mornings next week from 6:30 to 8:00AM. An e-mail to Readiness list will be send when
dates are known.
|
Notes XO Integration Meeting 10.06.2020, posted by Frederik Wolff-Fabris on 10 Jun 2020, 11:12
|
General Announcement:
- Maintenance in the Tunnel Air Conditioning is completed. No more work restrictions are in place besides the regular COVID-19 rules.
|
Notes XO Integration Meeting 08.06.2020, posted by Frederik Wolff-Fabris on 09 Jun 2020, 15:47
|
General Announcement:
- SA2 lasing: up to 2mJ@9keV was achieved with strong linear and quadratic tapering with 250pC bunch charge.
Lasing with 500pC achieved 0.45mJ@9keV and with 100pC achieved 0.75mJ@9keV.
|
Notes XO Integration Meeting 05.06.2020, posted by Frederik Wolff-Fabris on 05 Jun 2020, 13:44
|
General Announcement:
- Many summer shutdown tasks have been scheduled already and information has been sent to the groups with tunnel tasks.
- XO will not fully engage with tasks in the instrument Hall carried by the Instruments. Please contact XO if there are difficulties in organizing these |
Notes XO Integration Meeting 03.06.2020, posted by Frederik Wolff-Fabris on 04 Jun 2020, 13:31
|
General Announcement:
- Summer shutdown is nearing. Few dates on crane maintenance at XHEXP1 were sent to the readiness mailing list. Please be aware on the dates when planning
activities.
|
Notes XO Integration Meeting 29.05.2020, posted by Frederik Wolff-Fabris on 29 May 2020, 14:22
|
General Announcement:
- Due to the public holiday this meeting do not take place on Monday.
- Safety related questions:
|
Notes XO Integration Meeting 27.05.2020, posted by Frederik Wolff-Fabris on 28 May 2020, 13:58
|
General Announcement:
- It seems EuXFEL was not affected due to the power glitch at the Desy site last Tuesday (no device was found in off state or damaged).
- TS informed no indications of power failure at EuXFEL. Groups are encouraged to inform XO if they find components that have been affected.
|
Notes XO Integration Meeting 25.05.2020, posted by Frederik Wolff-Fabris on 25 May 2020, 15:29
|
General Announcement:
- Machine started SA2 lasing last weekend. Currently photon energy is 0.5mJ at 9keV.
- CTRL OCD was called Friday on the SR slits position and movement. It was quickly solved.
|
Notes XO Integration Meeting 20.05.2020, posted by Frederik Wolff-Fabris on 22 May 2020, 08:57
|
General Announcement:
- XO Integration Meeting will not take place next Friday 22.05 due to the bridge holiday.
- MPS group shared some info on the SA1 emergency power off event that happened last week. Further investigations are ongoing.
|
Notes XO Integration Meeting 18.05.2020, posted by Frederik Wolff-Fabris on 18 May 2020, 14:53
|
General Announcement:
- Starting today 18.05 the XTD1 tunnel will be closed. It is not accessible until the summer shutdown. All other tunnels remain open.
- XO and PMO have sent a communication for updating the task list. Please indicate if tasks were already carried out. Deadline for submitting it back is |
Notes XO Integration Meeting 15.05.2020, posted by Frederik Wolff-Fabris on 15 May 2020, 14:35
|
General Announcement:
- Judging by feedback and communication to XO both Tunnel and control network works are progressing.
- Friday is a good opportunity to discuss the Karabo tasks to be submitted next week as well as direct questions to SRP.
|
Notes XO Integration Meeting 13.05.2020, posted by Frederik Wolff-Fabris on 13 May 2020, 13:51
|
General Announcement:
- SRP will join this meeting series. If you have questions please raise the points.
- DET has questions on the policy in how to proceed with team work (how close and what is the interaction that different teams can have, e.g. when working |
Notes XO Integration Meeting 11.05.2020, posted by Frederik Wolff-Fabris on 11 May 2020, 14:53
|
General Announcement:
- The proposed works on the Control network are fully organized for this week;
- Safety: The EuXFEL task force for the Covid-19 discussed this morning the safety issues here presented last Friday.
|
Notes XO Integration Meeting 08.05.2020, posted by Frederik Wolff-Fabris on 08 May 2020, 16:44
|
General Announcement:
- Q&A session with SRP/Tobias Haas:
|
Notes XO Integration Meeting 06.05.2020, posted by Frederik Wolff-Fabris on 06 May 2020, 14:45
|
General Announcement:
- SRP is invited and urged to participate in this series of meetings.
- Several groups have questions to the SRP regarding:
|
Notes XO Integration Meeting 04.05.2020, posted by Frederik Wolff-Fabris on 04 May 2020, 14:20
|
General Announcement:
- From today on there is no general restrictions in accessing the EuXFEL site: only consent of group leader is needed.
- Control Network activities: there is a sensible approach for this week and currently CTRL and XO do not observe issues needing discussions.
|
Notes XO Integration Meeting 29.04.2020, posted by Frederik Wolff-Fabris on 29 Apr 2020, 17:28
|
General Announcement:
- The Work on the Controls Network are progressing very nicely;
- Work in the tunnels: safety practices due to Covid-19 were covered in the staff meeting.
|