General Announcement:
- Following Desy e-mail to all EUXFEL staff, the emergency call system of the elevators will be offline on Thursday March 18th during the morning. Please avoid using the
elevators in this day.
- On March 23rd is scheduled the SEPS interlock tests in SA3. On March 25rd is planned for SA2, pending a confirmation with the machine on the impact in SA1 operation.
CTRL:
- Progressing with investigating the train-ID issues, currently it relates to DOOCS/Desy.
- DOC: reports one fix today at 13:00 (following a call). Please respect a sign "we are in", "we are out" at the DOC to help staff focusing on issues.
DA:
- Nothing to report.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- All working fine in XPD.
DET:
- Detector commissioning in SPB: AGIPD was completed as planned and Jungfrau seems to run properly (data to be analyzed.
ITDM:
- ITDM will add more space to the storage system (data taking). Initial idea is to make it on March 30th to minimize impact. Acquiring data and data analysis are not
impacted.
XRO:
- Beam power increase ongoing.
LAS:
- An issue with SA1 interlock in PP-laser room: the inside doors were reported to be open on Thursday afternoon.
As SPB was not using the PP-laser, the laser was put in safe mode and Interlock was broken to access and verify the situation. The internal doors were closed.
Further discussions will follow. This door issue happened for the first time in SA1.
- LAS is providing beam to SPB and HED as requested.
UNSYS:
- Couple of e-log entries on settings of air coils and phase shifter, all addressed during the weekend.
SPB:
- Detector program is completed. One measurement (which is not critical) is missing from Jungfrau.
- Interacting with DOC worked nicely.
FXE:
- Preparing for this week.
MID:
- Fully in preparation for first April beam. All fine.
HED:
- Nothing to report.
SCS:
- SCS asks for update of missing CPU from EEE. No news from EEE. Contact will be made.
SQS:
- Preparing to have beam in April. |