Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 210     Entry time: 24 Mar 2021, 10:06
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 24.03.2021 
General Announcement:
-	 

CTRL:
- In SA2/HED few interlocks are protected and not altered. CTRL needs to re-start the HEDloop1 and HEDcryo loop and SA2 EPS loop. It takes about 5-10 minutes without PLC 
restart. 
Suggestion is to make it today: XO will communicate to HED. 
- When submitting a ticket, please include the device ID on it. 

DA:
- Not present due to training. 

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Nothing to report.

DET:
- Problem with SPB Jungfrau: M. Sikorski says the chiller was OFF and two modules are misbehaving. One can’t be fixed now and cards are ordered and have to be replaced.
The Chiller went OFF manually. It may become protected by EPS.

ITDM: 
- Nothing to report.

XRO:
- Not present.

LAS:
- SA1 and SA2 PP-lasers are fine;
- In SA3 still ongoing due to small problem of missing train-IDs in ADC cards. Consequently, no DAQ data can be taken for SCS and SQS. 
Nevertheless, the laser is ready for SCS use (not yet available to SQS). 

UNSYS:
- ZZ for the cell36/SA1 took place on Monday. The problem related to a coupler (spare parts are available and were replaced). It is fixed.

SPB:
- Start with data collection. Aside from detector, no other issues.

FXE:
- Nothing to report.

MID:
- All fine.

HED:
- Not present.

SCS:
- A problem was found on Monday regarding the door interlock. 
Zunaira A. comments that during a hutch search training it was found that a switch off (red button /panic switch) was pressed and did not release the magnet locks.
SRP has contacted a company and they have to come in to fix it. 
Zunaira A. sends another instruction to SCS staff in how to proceed in case of emergencies (one has to open door manually).

SQS:
- Nothing to report. Panic button at SQS works normally.
ELOG V3.1.4-7c3fd00