ID Date Author Location Severity Subject Text Attachments
  54   14 Jun 2019, 10:47 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.00FXE

SPB/SFX


Getting ready for the shutdown.
  
  53   12 Jun 2019, 12:40 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 12.06.19 FXE

SPB/SFX

SCS
  
  52   07 Jun 2019, 11:53 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.00FXE

SPB/SFX


few days of beamtime remaining,
  
  51   05 Jun 2019, 09:59 Gerd WellenreutherGeneralInformationMinutes of the Technical integration meeting 05.06.2019FXE

SPB/SFX


few days of beamtime
  
  50   03 Jun 2019, 12:57 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30SPB/SFX


No major issues.


FXE


Tool to save motor positions
  
  49   29 May 2019, 10:30 Gerd WellenreutherGeneralInformationMinutes of the Technical integration meeting 29.05.19 FXE

SPB/SFX


XTD2 attenuator appears
  
  48   27 May 2019, 10:35 Gerd WellenreutherGeneralInformationStatus report after dispatch meeting Monday 27.5. 09.30 SPB/SFX


Digitizers are ready, have
been tested by CAS ==> to be be installed
  
  47   24 May 2019, 11:01 Gerd WellenreutherGeneralInformationStatus report after dispatch meeting Friday 24.5. 09.00SPB/SFX


are working on achieving
a good focus @ 6 keV, which currently is
  
  46   22 May 2019, 09:58 Gerd WellenreutherGeneralInformationMinutes of the Technical integration meeting 22.05.19FXE

SPB/SFX


XTD2 attenuator
  
  45   20 May 2019, 10:02 Gerd WellenreutherGeneralInformationStatus report after dispatch meeting Monday 20.5. 09.30SPB/SFX


are working on achieving
a good focus @ 6 keV, which currently is
  
  44   17 May 2019, 10:47 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.00SPB/SFX


ADC have been requested.
HW should be already installed (SPB to check).
  
  43   15 May 2019, 12:53 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 15.05.19 SPB/SFX


Nano KB mirrors and CSS
controls are OK
Digitizers have
  
  42   13 May 2019, 11:24 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.30SPB/SFX


The gear ratio of the CSS
is unclear but this was already known and
  
  41   10 May 2019, 10:52 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.00SPB/SFX


IRDa commissioning
successful. A. Mancuso thanked all the people
  
  40   08 May 2019, 10:10 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 08.05.19 SPB/SFX


IRDa commissioning
ongoing. 
CSS. Limit switches
 Technical_Integration_Meeting_07.05.2019_-_Copy.pptx 
  39   06 May 2019, 10:20 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30SPB/SFX


IRDa commissioning
ongoing. 
For this week AGIPD
  
  38   03 May 2019, 14:07 Adriano ViolanteGeneralInformationReport after dispatch meeting 9:00SPB/SFX


IRDa commissioning
ongoing. First images have been taken with
  
  37   29 Apr 2019, 10:04 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30SPB/SFX


IRDa commissioning
ongoing. Focus (<5um) in the second interaction
  
  36   26 Apr 2019, 12:28 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.00SPB/SFX


IRD commissioning ongoing.
CRL
motors being tested. --> Mechanical issue
  
  35   24 Apr 2019, 10:05 Gerd WellenreutherGeneralInformationMinutes of the Technical integration meeting 24.04.19 SPB/SFX


SPB/SFX is preparing for
the upcoming beamtime.
CRL motors
  