ID |
Date |
Author |
Location |
Severity |
Subject |
Text |
|
410
|
01 Nov 2017, 11:24 |
Adriano Violante | XHEXP | Information | Status after 9.30 dispatch meeting | Instruments
SPB:
When
PLC loops are restarted, still many device |
|
419
|
13 Nov 2017, 09:45 |
Adriano Violante | General | Information | Status after 9.30 dispatch meeting | General
No user operation.
During
the week end the accelerator was not able |
|
426
|
29 Nov 2017, 09:56 |
Adriano Violante | General | Information | Status after 9.30 dispatch meeting | General
Preparation for the user's
run starting tomorrow (until 7:00 Tuesday |
|
429
|
06 Dec 2017, 13:46 |
Adriano Violante | General | Information | Status report after dispatch meeting 13:00 | General:
Shutdown started.
Instruments
SPB:
AGIPD |
|
450
|
15 Jan 2018, 13:56 |
Adriano Violante | General | Information | Status report after dispatch meeting 13:00 |
SPB:
- The exchange
of the mc and mfpga boards has been done
and some problems were found. The boards |
|
451
|
17 Jan 2018, 13:54 |
Adriano Violante | General | Information | Status report after dispatch meeting 13:00 |
SPB:
- one mfpga
board was found malfunctioning and was replaced
with the old one. Concerning the mc the new |
|
456
|
22 Jan 2018, 13:28 |
Adriano Violante | General | Information | Status report after dispatch meeting 13:00 | General remarks:
Stable beam only to be
expected starting from 1.03. for SASE1 instruments |
|
458
|
24 Jan 2018, 14:48 |
Adriano Violante | General | Information | Status report after dispatch meeting 13:00 | SPB/SFX:
Preparing D.02 for mirrors
installation (next 2 weeks no access to D.02)
Karabo |
|
463
|
29 Jan 2018, 14:51 |
Adriano Violante | General | Information | Status report after dispatch meeting 13:00 | SPB/SFX:
Problems with data loggers
==> no statements about the past.
Loop |
|
465
|
31 Jan 2018, 14:56 |
Adriano Violante | General | Information | Status report after dispatch meeting 13:00 | SPB/SFX:
Fixing of Karabo scenes
ongoing
Loop 5 need to be updated |
|
467
|
05 Feb 2018, 09:11 |
Adriano Violante | General | Information | Status and plans after SASE1 Status/SASE3 Readiness Meeting 02.02. | SPB
- Loops update OK
- Issue with SmarACT controllers. |
|
468
|
05 Feb 2018, 13:18 |
Adriano Violante | General | Information | Status report after dispatch meeting 09.30 | SPB
- MIrrors installation (2 horizontal
mirrors) in D.02 has started |
|
469
|
07 Feb 2018, 09:47 |
Adriano Violante | General | Information | Status report after dispatch meeting 09.30 | SPB/SFX
- An AGIPD crate providing power
broke down and has been fixed already by |
|
470
|
12 Feb 2018, 08:46 |
Adriano Violante | General | Information | Status and plans after SASE1 Status/SASE3 Readiness Meeting 09.02. | General
"In the beginning of this
meeting SM congratulated the whole staff |
|
471
|
12 Feb 2018, 10:03 |
Adriano Violante | General | Information | Status report after dispatch meeting 09.30 | SPB
During operation Karabo
crashed. As soon as detector is being operated |
|
472
|
14 Feb 2018, 14:21 |
Adriano Violante | General | Information | Status report after dispatch meeting 09.30 | SPB
MIddle layer karabo devices
are responsible for the det. Karabo problems. |
|
Draft
|
16 Feb 2018, 15:44 |
Adriano Violante | General | Information | Status and plans after SASE1 Status/SASE3 Readiness Meeting 16.02. | Photon
Run Coordinator Report to Readiness Meeting
The |
|
475
|
19 Feb 2018, 09:56 |
Adriano Violante | General | Information | Status report after dispatch meeting 09.30 | SPB
KB chamber being
pumped down
interaction |
|
477
|
21 Feb 2018, 10:55 |
Adriano Violante | General | Information | Status report after dispatch meeting 09.30 | SPB
KB chamber being pumped
down
Smaract commissioning ongoing
Coordinate |
|
481
|
28 Feb 2018, 10:55 |
Adriano Violante | General | Information | Status report after dispatch meeting 09.30 | SPB:
Ion pumps running in the
Mirror chamber. Vacuum level OK to run.
D.02 |
|