ID |
Date |
Author |
Location |
Severity |
Subject |
Text |
|
482
|
02 Mar 2018, 14:36 |
Adriano Violante | General | Information | Status and plans after SASE1 Status/SASE3 Readiness Meeting 02.03. | Photon
Run Coordinator (N. G. Kujala):
SASE1
|
|
483
|
05 Mar 2018, 11:07 |
Adriano Violante | XHEXP | Information | Status report after dispatch meeting 09.30 |
SPB
Last night the beam disappeared |
|
484
|
05 Mar 2018, 16:37 |
Adriano Violante | General | Information | Details on SPB issues reported in the dispatch meetings | Below some clarifications from R. Bean
on the issues reported in today's dispatch
meeting: |
|
485
|
07 Mar 2018, 11:14 |
Adriano Violante | General | Information | Status report after dispatch meeting 09.30 | SPB:
Monday morning Karabo failed.
It was not possible to operate anything. |
|
486
|
12 Mar 2018, 08:18 |
Adriano Violante | General | Information | Status and plans after SASE1 Status/SASE3 Readiness Meeting 09.03 | Photon Run Coordinator (L. Samoylova):
Commissioning during |
|
487
|
12 Mar 2018, 13:18 |
Adriano Violante | General | Information | Status report after dispatch meeting 09.30 | SPB (Weinhausen):
During the night there
was an interlock issue. The fast shutter |
|
488
|
14 Mar 2018, 10:06 |
Adriano Violante | General | Information | Status report after dispatch meeting 09.30 | SPB (Weinhausen/Round/Mancuso):
Again on the fast valve was
triggering the MPS interlock system. For |
|
489
|
19 Mar 2018, 08:42 |
Adriano Violante | General | Information | Status and plans after SASE1 Status/SASE3 Readiness Meeting 16.03.. | Photon Run Coordinator (H. Sinn):
1.) SASE1: User experiment SPB
could be finished sucussfully after several |
|
490
|
19 Mar 2018, 10:24 |
Adriano Violante | General | Information | Status report after dispatch meeting 09.30 | No new issues to be discussed where reported
by any groups.
The status and issues reported |
|
491
|
21 Mar 2018, 10:02 |
Adriano Violante | General | Information | Status report after dispatch meeting 09.30 | SPB
On monday there was an issue with
a detector related PLC due to misconnection |
|
493
|
26 Mar 2018, 13:10 |
Adriano Violante | General | Information | Status report after dispatch meeting 09.30 | General
Due to the triggering of the emergency
power off in FXE caused by electrical works |
|
495
|
28 Mar 2018, 15:22 |
Adriano Violante | General | Information | Status report after dispatch meeting 09.30 | SPB
Sample delivery installed.
Tonight will be commissioned. Experiment |
|
500
|
09 Apr 2018, 11:50 |
Adriano Violante | XHEXP | Information | Emergency off test in SPB/FXE - Update | Due to some delay in the installation of
some necessary cables, the emergency power
off test foreseen for today 06.04. in the |
|
501
|
09 Apr 2018, 14:25 |
Adriano Violante | General | Information | Status report after dispatch meeting 13:00 | General
Emergency off test in SPB is shifted.
Date to be agreed on Friday. FXE test stays |
|
502
|
09 Apr 2018, 14:37 |
Adriano Violante | General | Information | Karabo deployment dates | FYI
Below
the E-Mail from Hugo Santos with the Karabo |
|
503
|
11 Apr 2018, 13:48 |
Adriano Violante | General | Information | Status report after dispatch meeting 13:00 | SPB
Detector z motion would
be needed. AE checks the status of the crate. |
|
504
|
12 Apr 2018, 15:34 |
Adriano Violante | General | Information | Water cooling mointenance by MKK done | Die Arbeiten an der Kühlwassersteuerung
konnten innerhalb des genannten
Zeitraums abgeschlossen werden, |
|
505
|
13 Apr 2018, 07:50 |
Adriano Violante | General | Information | Karabo 2.2.3 installation | Hi all, for your information below a message
from Chris Youngman concerning Karabo 2.2.3
installations in SASE3. |
|
507
|
13 Apr 2018, 09:40 |
Adriano Violante | XHEXP | Information | Emergency off test in SPB/FXE | Emergency power test will be performed
at the following dates:
FXE - Mon. 16.04. |
|
508
|
13 Apr 2018, 13:01 |
Adriano Violante | XHEXP | Information | Dates TÜV Test SASE3 Intelrocks | Interlock systems SASE3 - TÜV test
The pre test by D3 will be held
on 20.06. |
|