  40   08 May 2019, 10:10 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 08.05.19

SPB/SFX

  • IRDa commissioning ongoing. 
  • CSS. Limit switches re cabling is ongoing. For the next run the old configuration will still be used. RB and MS will meet to make sure the system can be safely (from the component point of view) operated. ==> Solved.
  • Comment from AS: Trigger test with pulse on demand was not succesfull due to missing karabo devices and issues with configuration. For the final fix 10 minutes of beamtine has to be taken from SPB/SFX. This will be agreed with the intrument.

FXE

  • Delay servo stages have been commissioned. Right now only one stage is being used.  

SQS

  • Integration of the photonic science camera is progressing. Status not clear.
  • MPODS power supplies are behaving strangely. CY will ahve a look.
  • The pnCCD is supposed to be used next week. SQS want to use channels dedicate to other components and work out a temporary solution. AE requested the list of channels to be used but no answer has been received so far. Also, proper CRDs to start preparing the propoer implementation of the controls is still missing.

SCS

  • Part of the uTCA system will need to be installed in the hutch (it was planned for the rackroom). Discussion channel is open with AE.

 MID

  • Servo motors require fw updates. Being agreed with AE.
  • Loop 7 update is being coordinated for this week between MS and UBoesemberg.

HED

  • For Loop 6 and 8, as well as smaract stages AE is waiting the go ahead from HED to switch on the Beckhoff modules. 

OPT Lasers

  • Laser beam has to be deivered to SCS in 2 weeks. Fw has to be uploaded in the PLCs. AE got the fw export and should upload it by friday this week.
  • There is the request to make the timing signal independent between the SASEs. Will be discussed offline with AE. It should be possible in the winter shutdown.

XRO

XPD

VAC

DET

  • Karabo 2.4.1. improves the pipieline stability. The deployment is strongly suggested to MID and SPB. ==> Deployment schedule for next week monday.

AE

ITDM

EET

  • GDB cables have been completely produced and are bein installed this week. 
  • Schedule for the Loop 10 and 11 cables installation is confirmed. IN KW25 would be possible to bring the loop up.

CAS

SRP

TS

AoB

  • Presentation showing the MPS schedule  is attached and is showing when the emergency power off system will be triggered. The Beckhoff modules shut down is being organized by AE. It is noted that the instruments should organize the temporary power supply for the vacuum system.
Attachment 1: Technical_Integration_Meeting_07.05.2019_-_Copy.pptx
  41   10 May 2019, 10:52 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.00

SPB/SFX

  • IRDa commissioning successful. A. Mancuso thanked all the people involved in the project. 
  • The gear ratio of the CSS is unclear but this was already known and discussed with SPB/SFX
  • Mirrors motors had some issues (ELMO motors), they are already been fixed.
  • Adam and Alexis are discussing internally when the next loops will be needed. The info goes then to AE.
  • NReimers will take care of asking TSchön for temporary power lines for the vaccum pumps during the MPS tests in the summer shutdown.

FXE

SQS

  • MPODS power supplies are behaving strangely. Almost fixed by CY.
  • The pnCCD is supposed to be used next week. SQS want to use channels dedicate to other components and work out a temporary solution. AE requested the list of channels to be used but no answer has been received so far. Also, proper CRDs to start preparing the propoer implementation of the controls is still missing.==> info still missing. AV will ask TBaumann again. Also the DAQ for the pnCCD is not prepared at all.

SCS

  • Part of the uTCA system will need to be installed in the hutch (it was planned for the rackroom). Discussion channel is open with AE.

 MID

  • Nano motors require fw updates. Being agreed with AE, but with low priority.
  • Today there will be a meeting for the implementation of the AGIPD quadrant motion
  • Karabo integration of the SDL: kick off meeting took place yesterday between CAS and MID. - The migration of equipment listed in point 5 to Karabo 2.4.x should be completed by end of first week of summer shutdown (KW24) by CAS. MID should then validate the resulting system performance. Prototypes of the middle layer devices will be prepared by CAS while the component is not here. SDL is expected to be delivered in November. Cables and electronics should also be installed in November (WS)

HED

  • Smaract stages will be commisisoned today. MS support needed.
  • Loop 6 VAC modules will be connected to the loops in 2 weeks. For now the controls remain local.

OPT Lasers

  • Laser beam has to be deivered to SCS in 2 weeks. Fw has to be uploaded in the PLCs. AE got the fw export and should upload it by friday this week. ==> Loops should be started on monday.

XRO

  •  HED had radiation damages on the Mono1 cristals.  REasons are being investigated. One possibility is the accidental focus of the beam on the cristal. There is usually a macro to avoid that but it was foung not working by MV. To be checked.
  • Guesthouse civil contruction is starting soon and MV is in contact with TS concerning vibrations in the tunnels. 

XPD

VAC

DET

AE

ITDM

  • Test for DSSC DAQ started yesterday.

EET

CAS

  • Karabo 2.4.1. improves the pipieline stability. The deployment is strongly suggested to MID and SPB. ==> Deployment schedule for next week monday.
  • Krzysztof, Steffen and Hugo aligned and  concluded that 2.4.1 is backwards compatible with 2.4.0 deployed already on the PCL (DAQ) machines. This setup is, indeed, already running on FXE since 29.04 (Monday).

SRP

TS

AoB

  42   13 May 2019, 11:24 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.30

SPB/SFX

  • The gear ratio of the CSS is unclear but this was already known and discussed with SPB/SFX ==> AL is working on it toghter with AE.

FXE

  • Karabo for Jungfrau detector has been udpated and works fine. For the LPD some issues were reported but SH commented that the problems arise from the fact that the signal FXE was trying to detect is very low, potentially close to the HW limit od the detector

SQS

  • MPODS power supplies are behaving strangely (1 channel trips, but the power supply does not send any error message). TB and CY to have a look.
  • The pnCCD is supposed to be used next week. Meeting after the dispatch meeting with AE, CAS, ITDM(!) to coordinate the efforts.

SCS

 MID

  • Mono needs cooling. Issue will be attacked today/tomorrow.
  • 2 crates for the remote contro of vacuum compoennts are required to run in the intrument. CY wants to be present. There are difficulties finding a suitable time slot both for MS and CY. To be addressed offline.

HED

  • Smaract stages behave strangely. AE support required.

OPT Lasers

  • Crates will be switched on today. Meeting JE/OPT lasers today at 11 to coordinate the efforts.

XRO

 

XPD

VAC

DET

  • Updated pipeline in SPB has been installed today.
  • SCS DSSC took the first images (without beam)

AE

ITDM

EET

CAS

SRP

TS

AoB

  43   15 May 2019, 12:53 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 15.05.19

SPB/SFX

  • Nano KB mirrors and CSS controls are OK
  • Digitizers have been requested. HW needs to be installed and set up and the timeline has to be clarified betweek BF and SPB. Not possible to have them running on short notice.
  • Comment from AS: Trigger Test with pulse on demand to test the conditional trigger (5Hz like operation) is done, but failed to deliver a real conditional trigger. The Karabo device is adapted to switch between the present mode and conditional trigger from Karabo (although some issue were identified). The X2Timer configuration still need adjustment, BF is on it.

FXE

  • Re shuffling of PLC CPUs drawers will occur during the next winter shutdown.

SQS

  • MPODS power supplies are behaving strangely. CY will have a look.
  • pnCCD: Commissioning should start today. Maxi cage for interlocks will be installed today by SQS.

SCS

  • Det. DAQ test ongoing.

 MID

  • Axes for users operation being commissed
  • Communication between VAC and AE concerning the electronics for the cryo coolers - heaters has to be improved since AE was not involved during the last ZZ intervention on monday. MD will discuss later today with NJ.

HED

  • Loop 6 can be operated in its completeness by middle of next week.
  • Laser beam has to be deivered to SCS in 2 weeks. Fw has to be uploaded in the PLCs. HW is ready, commissioning has to start.
  • There is the request to make the timing signal independent between the SASEs. Will be discussed offline with AE. It should be possible in the winter shutdown. ==> BF is talking to the involved people.

XRO

XPD

VAC

DET

  • Karabo 2.4.1. improves the pipieline stability. The deployment is strongly suggested to MID and SPB. ==> Pipeline for SPB has been deployed. Minor issues being addressed. MID has to folllow.

AE

ITDM

EET

  • Schedule for the Loop 10 and 11 of HED cables installation is confirmed. IN KW25 would be possible to bring the loop up.

CAS

SRP

TS

AoB

  44   17 May 2019, 10:47 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.00

SPB/SFX

  • ADC have been requested. HW should be already installed (SPB to check). BF will discuss with SPB how to proceed.

FXE

  • LPD is running.

SQS

  • MPODS power supplies are behaving strangely (1 channel trips, but the power supply does not send any error message). CY following it up but the priority is now with the DSSC (working on powering sequence. To be then adopted later also for other detectors.
  • The pnCCD is being set up. AE will be required to help for axes commisisoning next week.Some issues with electronics to read data have been solved. Tests to understand the reasons of the issues are being performed by AE.

SCS

 MID

  • Setting up next weeks experiments. Some equipment that the users are bringing have to be integrated. This may couse some delays.
  • 2 crates for the remote contro of vacuum compoennts are required to run in the intrument. CY wants to be present. There are difficulties finding a suitable time slot both for MS and CY. To be addressed offline.==> done, interlock tests have to be scheduled by MID.

HED

  • Epix card died. Workaround using some MID infrastructure has been proposed. Risks will be presented by HED ( Sebastian Goede) to MID and a decision has to be taken by the group leaders.

OPT Lasers

​​XRO

 

XPD

VAC

DET

  • Updated pipeline in SPB has been updated yesterday. Seems to work. MID probably will be updated today. Has to be discussed offline with ITDM.

​​AE

ITDM

  • DSSC DAQ was basically not commissioned due to lack of time (although scheduled). Now the detector cannot be oprated. More time has to be scheduled for DAQ commissioning. Meanwhile test on the VETO system are being performed. This would help to save much less data (200 images/train with VETO instead of 800 images/train).

EET

CAS

SRP

TS

AoB

  45   20 May 2019, 10:02 Gerd WellenreutherGeneralInformationStatus report after dispatch meeting Monday 20.5. 09.30

SPB/SFX

  • are working on achieving a good focus @ 6 keV, which currently is not as good as expected.
  • Digitizers are ready, have been tested by CAS ==> to be be installed / integrated probably next week
  • Different GUIs were reporting varying values for STATUS on different clients / machines ==> ARound will make sure a proper description of the issue (which machines, which clients, when, ...) will be brought to the attention of the proper people @ CAS.

FXE

  • The Karabo FAI went well, FXE thanks explicitly for the support received.

SQS

  • The pnCCD is being set up. AE will be required to help for axes commisisoning next week. ==> this should happen today.

SCS

  • MTeichmann attended, fresh from vacation, nothing to report, everything is "awesome".

 MID

  • Commissioning the cryomanipulator. Had to use a couple of work arounds in order to align it with the beam (travel range issues it appears).
  • The AGIPD Julabo chiller failed on Saturday, it has to be sent in. Meetings this mornings should clarify what other options remain to support the user experiments as planned.

HED

  • User experiment went very well.
  • Currently commissioning ion pumps in the optics hutch
  • Starting on Wednesday loop 6 is to be commisioned (exp. hutch components) together with AE

OPT Lasers

​​XRO

XPD

VAC

DET

  • Question to ITDM: Did the crash of git on Saturday affect the calibration database (there were apparently issues @ FXE for 2 hours) ==> No. If there would have been problems, they would not have resolved with nobody doing anything, the system requires manual intervention. So most probably the problem was somewhere else...

​​AE

  • SCS had a problem with the fast ADC, was fixed Friday. Did this gave further problems during the weekend ==> MTeichmann to check.

ITDM

EET

CAS

SRP

TS

AoB

  46   22 May 2019, 09:58 Gerd WellenreutherGeneralInformationMinutes of the Technical integration meeting 22.05.19

FXE

SPB/SFX

  • XTD2 attenuator appears to be damaged.
  • Beam at lower energies look disturbed, SPB/SFX will contact XRO.
  • Digitizers have been requested. HW needs to be installed and set up and the timeline has to be clarified betweek BF and SPB. ==> next week

SQS

  • pnCCD: testing the 5 axis of motion. 3 are working, but there are problems, the wiring of the cables is now being checked.

SCS

  • Some issues are noticed regarding the triggering of the detector, but BF is on it

 MID

  • Due to the failed chiller, the user experiment had to be cancelled.
  • As a consequence, time is available to commision other hardware. ==> to be clarified with AE which activities can be supported.
  • Integration of the LDM: Safety document is needed.

HED

  • Loop 6 being commissioned.
  • Loop 1 was updated, parameters got lost. :-(
  • Detector issues regarding Epix 100: First some HW + assistance from MID was provided to get the detector running. By now, the HED-owned HW for the Epix 10K is being used.

XRO

XPD

VAC

DET

AE

  • Loop priorities for HED and MID are needed.
  • AE reminds everybody to contact TSchoen if power is required during the middle of June, e.g. in order to keep the vacuum running.

ITDM

EET

CAS

SRP

  • A safety walkthrough for SASE2 was done. Several installations are in conflict with the safety regulations regarding e.g. electrical installations. Detailed minutes will be provided. SRP will also involve TS / Süleyman Arslan.

TS

AoB

  47   24 May 2019, 11:01 Gerd WellenreutherGeneralInformationStatus report after dispatch meeting Friday 24.5. 09.00

SPB/SFX

  • are working on achieving a good focus @ 6 keV, which currently is not as good as expected. ==> This is understood now, those were higher harmonics, too many absorbers in the beam. Absorber still shows some structure, though
  • Digitizers are ready, have been tested by CAS ==> to be be installed / integrated probably next week ==> according to Adrian probably Monday, to be confirmed with AE (Bruno + Hamed)
  • Different GUIs were reporting varying values for STATUS on different clients / machines ==> ARound will make sure a proper description of the issue (which machines, which clients, when, ...) will be brought to the attention of the proper people @ CAS. ==> CAS is aware.
  • Data from motor + camera was taken to correlate motion data. ==> still has to be understood with help of DET and ITDM.
  • AGIPD quadrant motion is needed in summer in order to align the detector in order to record data at low scattering angles / closely around the beam center. ==> is scheduled for summer shutdown

FXE

SQS

SCS

  • First light was seen on the DSSC!

MID

  • AGIPD control server is dead ==> to be replaced by a spare by ITDM / Janusz

HED

OPT Lasers

​​XRO

XPD

VAC

DET

  • pnCCD integration is progressing at SQS, testing taking data with the DAQ.
  • MID-chiller issue: chiller will return in next week.
  • Increasing amount of problems and sufferings due to unreliability of gitlab

​​AE

ITDM

EET

CAS

  • OCD-call regarding device communication: The polling-intervall epsilon was set too small, such that the client became flooded and turned unresponsive.

SRP

TS

AoB

  • Shutdown planning now includes MKK, which includes some activities concerning cooling water. Please check, email was sent to readiness.

  48   27 May 2019, 10:35 Gerd WellenreutherGeneralInformationStatus report after dispatch meeting Monday 27.5. 09.30

SPB/SFX

  • Digitizers are ready, have been tested by CAS ==> to be be installed / integrated probably next week ==> according to Adrian probably Monday, to be confirmed with AE (Bruno + Hamed) ==> is confirmed to be today
  • Different GUIs were reporting varying values for STATUS on different clients / machines ==> ARound will make sure a proper description of the issue (which machines, which clients, when, ...) will be brought to the attention of the proper people @ CAS. ==> CAS is aware. ==> CAS has a suspect.
  • There appears to be an issue with recorded / stored values vs. values shown in the client of motors moving. CAS shall receive a proper + detailed description of the issue.

FXE

  • Tool to save motor positions is not working reliably. ==> CAS + AE have different tools on different levels. There is not automatic / global restoring of for example motor positions from the CAS-side available. BUT in the shutdown motor position should not be lost, unless there is a true power outage also affecting the CPUs.
  • Problems with the PP-laser have been reported.

SQS

SCS

MID

  • Request to have the same kind of feedback as implemented at FXE ==> will require HW changes, to be done during the summer shutdown, and work by CAS in order to adapt the procedure from FXE.

HED

  • According to KS the Smaract-stages are to be checked with AE
  • Interlock definitions would be needed by Wednesday ==> MS is on it.
  • Last weeks issues regarding the epix were probably caused by the DAQ.

OPT Lasers

​​XRO

XPD

VAC

DET

  • The DSSC underwent successful readout test, more DAQ-test to come.
  • The pnCCD saw first visible light, working now on the delay / timing.

​​AE

ITDM

EET

CAS

  • A Hotfix 2.4.2 is provided by CAS, which should fix some issues related to the XGM.

SRP

TS

AoB

  49   29 May 2019, 10:30 Gerd WellenreutherGeneralInformationMinutes of the Technical integration meeting 29.05.19

FXE

SPB/SFX

  • XTD2 attenuator appears to be damaged. ==> Request to VAC: is it possible to exchange the attenuators in the summer shutdown? LBatchelor might have spares.
  • Digitizers have been installed
  • Bunch number is reported to have jumped from 1 --> 150, report to be provided by SPB/SFX so CAS can investigate.
  • Top priority: Testing new camera + DAQ interface along with motor positions recording @ 10Hz

SCS

  • Currently running + supporting the user experiment

SQS

 MID

  • Integration of the LDM: Safety document is needed. ==> This is needed ASAP!!!
  • Further commissioning is ongoing

HED

  • Loop 6 being commissioned. ==> done

VAC

  • Preparing for Shutdown

XRO

  • Preparing for Shutdown

XPD

DET

EEE

  • Loop priorities for HED and MID are needed.
  • AE reminds everybody to contact TSchoen if power is required during the middle of June, e.g. in order to keep the vacuum running.

CAS

  • Supported / tested measurements of gain curves in SASE1
  • Next week: Testing of correlator
  • Karabo Hotfix 2.4.2 was released, new week testing of 2.5. commences
  • Progress regarding InfluxDB etc. was achieved and reported, e.g. to readiness mailing list

ITDM

SRP

TS

AoB

  • No Dispatch on Friday due to the bridge day!
  50   03 Jun 2019, 12:57 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30

SPB/SFX

  • No major issues.

FXE

  • Tool to save motor positions is not working reliably. ==> CAS + AE have different tools on different levels. There is not automatic / global restoring of for example motor positions from the CAS-side available. BUT in the shutdown motor position should not be lost, unless there is a true power outage also affecting the CPUs. ==> Issues are being addressed.

​​SQS

  • Plan for this week is to combine the use of pnCCD and cluster source and make proper mesurements. The CCD measured already X-Rays in 10 Hz mode.

SCS

  • No Major issues

MID

  • No Major issues

HED

  • Beam drifts on the minute scale. The issue could be minimised with a karabo routine in use at FXE (mirrors feedback).
  • Dark images acquired with the jungfrau were not correct due to overheating. It has to be checked by HED whether the issue was solved.
  • Request to trigger the epix and jungfrau detectors via pulse on demand feature and scan tool. Motoaki will ask Daniel and Bruno and discuss the details.

OPT Lasers

​​XRO

XPD

VAC

DET

  • No major issues.

​​AE

ITDM

  • Issue about cooling failure in the lab floor in XHQ is being discussed between KWrona and LKersting

EET

CAS

 

AoB

  51   05 Jun 2019, 09:59 Gerd WellenreutherGeneralInformationMinutes of the Technical integration meeting 05.06.2019

FXE

SPB/SFX

  • few days of beamtime remaining, no particular issues
  • preparing for emergency power off
  • preparing shutdown activities with EEE

SCS

  • beamtime, no particular issues.
  • preparing for shutdown
  • XGM is supposed to run even despite the emergency power off ==> M. Teichmann is in contact with T. Schoen (TS)

SQS

  • beamtime, first scattering images taken using the pnCCD!
  • preparing for shutdown, in particular some cabling together with EEE

 MID

  • Integration of the LDM: Safety document is needed. ==> This is needed ASAP!!! ==> THIS IS STILL NEEDED!!!

HED

  • CAS was able to follow up regarding the request for test of triggering / pulse on demand from this Monday. HED was kind of lucky, CAS would appreciate some further notice next time...
  • Due to missing endswitches / interlock conditions, some YAG-screens have been burnt. HED would like to try to get this fixed in the tunnels and the hutches still in this shutdown by installing endswitches etc., to be negotiated with EEE
  • The bias teeth(???) used by HED are not being supplied any more, new ones are not performing ==> to be checked with other instruments / EEE, Sato-san was suggested as another expert to ask.

Optical lasers

  • everything fine, thanks for the support!

VAC

  • Requested to see the first pump + valve of SPB/SFX ==> to be clarified by VAC, SPB/SFX + EEE

XRO

XPD

DET

EEE

CAS

ITDM

SRP

  • From SBP/SFX: Currently, it is not clear what to do if one of the Pandoras goes off. This apparently happened @ FXE on the night from Sat.-Sunday, and it took 12 hours to fix it.

TS

  • From CAS: TS should not rely on email alerts to monitor the cooling of the servers running for example the email services...

AoB

  52   07 Jun 2019, 11:53 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.00

FXE

SPB/SFX

  • few days of beamtime remaining, no particular issues
  • preparing for emergency power off
  • preparing shutdown activities with EEE

SCS

  • XGM (VAC part) is supposed to run even despite the emergency power off ==> M. Teichmann is in contact with T. Schoen (TS)

SQS

  • preparing for shutdown, in particular some cabling together with EEE. Ongoing.

 MID

  • Integration of the LDM: Safety document is needed. ==> This is needed ASAP!!! ==> SRP is informed and JH will follow the issue up.

HED

  • Due to missing endswitches / interlock conditions, some YAG-screens have been burnt. HED would like to try to get this fixed in the tunnels and the hutches still in this shutdown by installing endswitches etc., to be negotiated with EEE ==> Only softwere limit switches can be implemented. EEE will follow it up.
  • The bias tee used by HED are not being supplied any more, new ones are not performing ==> to be checked with other instruments / EEE, Sato-san was suggested as another expert to ask.

Optical lasers

VAC

  • Requested to see the first pump + valve of SPB/SFX ==> to be clarified by VAC, SPB/SFX + EEE ==> The VAC OK signal has to be used as interlock signal. EEE on it.

XRO

XPD

DET

EEE

  • Improvement of the communication concering loop updates with the XRO has to be achieved. The idea is to approach the problem in 2 stages. In the first stage a time table with the loops update will be distributed by EEE and agreed with the component responsibles. Due to that, the responsibles have to be clarified. The GLs have been already informed. In the second stage EEE will try to automate the notification system when an update is required.

CAS

  • 2.5.0 being developed. 

ITDM

SRP

  • From SBP/SFX: Currently, it is not clear what to do if one of the Pandoras goes off. This apparently happened @ FXE on the night from Sat.-Sunday, and it took 12 hours to fix it.

TS

  • From CAS: TS should not rely on email alerts to monitor the cooling of the servers running for example the email services...

AoB

  53   12 Jun 2019, 12:40 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 12.06.19

FXE

SPB/SFX

SCS

SQS

MID

  • Integration of the LDM: Safety document is needed. ==> This is needed ASAP!!! ==> J. Hallmann is now back and he is in contact with SRP ti finalize the documentation. The statement from MID is that until the documents are finalized no automatic movement of the detector is foreseen.

​HED

  • Due to missing endswitches / interlock conditions, some YAG-screens have been burnt. HED would like to try to get this fixed in the tunnels and the hutches still in this shutdown by installing endswitches etc., to be negotiated with EEE ==> Software limit switches can be implemented already next week if the definitions are delivered to EEE by the end of this week.

Optical lasers

​VAC

  • Requested to see the first pump + valve of SPB/SFX ==> definitions still needed by EEE

XRO

XPD

DET

EEE

  • Improvement of the communication concering loop updates with the XRO has to be achieved. Mails have been sent by PGessler to the STGL and by NJardon to the relevant people. Loops updates already planned for next week in SASE2. Coordination with the involved people ongoing.

CAS

ITDM

SRP

  • From SBP/SFX: Currently, it is not clear what to do if one of the Pandoras goes off. This apparently happened @ FXE on the night from Sat.-Sunday, and it took 12 hours to fix it. Update from SRP: Occasionally Pandoras trigger radiation alarms. It is not clear why. One possibility is that this is caused by electronic noise. Discussions with D3 are ongoing. Right now an expert is needed to reboot the system since it is not a simple off/on procedure, but data has to be analysed. There is a a document in preparation by SRP/D3 that will allow more people to be able to perform this procedure, but it is not ready yet. A side note is that there is no OCD agreement in place for these experts and the reboot is done on the best effort level.

TS

​AoB

  54   14 Jun 2019, 10:47 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.00

FXE

SPB/SFX

  • Getting ready for the shutdown. No relevant issues.

SCS

SQS

  • PLCs have been switched off. Parameters have been saved.
  • GATT loop update will happen on tuesday. The schedule of the other loop updates are being agreed with EEE.

 MID

​​HED

  • Due to missing endswitches / interlock conditions, some YAG-screens have been burnt. Software limit switches will be implemented probably next week. Definitions have been provided by Karen Appel to EEE.
  • Instrument PLCs also switched off.

Optical lasers

VAC

XRO

  • HED mono has been opened and the crystal analized. The crystal shows radiation damages. XRO is discussing with HED to understand how to proceed. Since it its not yet clear why the damages happened, it would probably make sense to continue using the same cristal sending the beam to a different region.

XPD

DET

EEE

  • PLC Powering down in SPB SFX is being performed today.
  • Several loop updates are being planned and organized.

CAS

  • Gain curve device has been commissioned with and approved by L. Samoylova.
  • New structure for the CAS contacts to the instruments has been prepared by HSantos. He will send a mail around with the details.

ITDM

AoB

  55   17 Jun 2019, 10:43 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.30

FXE

  • Floor is being re-worked. Experiment hutch is not accessible until Wednesday. After that only accessible for walk until next Monday. 

SPB/SFX

SCS

SQS

  • It was asked by TBaumann when is the power coming back. It should be on Thursday.  The details must be asked to TSchön. AV will ask TS to send a mail to readiness when the power is back in a stable way.

 MID

  • Updates in the tunnel being agreed with EEE. CRLs should be updated today and the MOV loop latest on Wednesday.

​​HED

Optical lasers

VAC

XRO

XPD

DET

EEE

  • During the power down a heating up of the uTCAs was observed, in the XHEXP1 as well as tunnels. The reason is not clear. Now the situation is back to normal. ITDM checks the situation in the servers racks.

CAS

  • Deployment schedule for Karabo 2.5.0. has been discussed in CAS . Deployment is foreseen to start on the 1st week of July.

ITDM

AoB

  56   19 Jun 2019, 10:55 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 19.06.19

FXE

SPB/SFX

  • No major issues
  • Starting from the end of this week to the beginning of next week the hutch will not be accessible because of works on the AGIPD.

SCS

  • No big issues

SQS

MID

  • Integration of the LDM: Risk assessment has been finalized and uploaded in the IPW system. Next steps: SRP will review it and forward it to A.Madsen for the signature. PGessler is in the loop. JHallmann will call for a meeting with all the parties involved (e.g. EEE) in the implementation once the risk assessment has been signed by AM.

HED

  • Due to missing endswitches / interlock conditions, some YAG-screens have been burnt. HED would like to try to get this fixed in the tunnels and the hutches still in this shutdown by installing endswitches etc., to be negotiated with EEE ==> Software limit switches can be implemented already next week if the definitions are delivered to EEE by the end of this week. ==> definitions still missing.
  • Loop 11 being set up by EEE

Optical lasers

  • SASE1 timing system will be updated today.

VAC

  • Requested to see the first pump + valve of SPB/SFX ==> definitions still needed by EEE

XRO

  • Installation of the cooling system for the M1 mirror in SASE2 has been completed.
  • SASE1 XTD2 M1 being addressed now. 

XPD

DET

EEE

  • The timing uTCA will be switched off on the 24.06 between 9 am and 5 pm. No train ID and timing wil be available.

CAS

  • Release cycle for the next Karabo version in progress.

ITDM

  • New version of the Jddd should be used. Details will be forwarded to the readiness mailing list as soon as available.

SRP

  • From SBP/SFX: Currently, it is not clear what to do if one of the Pandoras goes off. This apparently happened @ FXE on the night from Sat.-Sunday, and it took 12 hours to fix it. Update from SRP: Occasionally Pandoras trigger radiation alarms. It is not clear why. One possibility is that this is caused by electronic noise. Discussions with D3 are ongoing. Right now an expert is needed to reboot the system since it is not a simple off/on procedure, but data has to be analysed. There is a a document in preparation by SRP/D3 that will allow more people to be able to perform this procedure, but it is not ready yet. A side note is that there is no OCD agreement in place for these experts and the reboot is done on the best effort level. ==> Z.Ansari will be also able soon to reboot the system. No additioanl news.
  • Test panel to test the different alarms will be mounted in the hall soon.
  • After the safety walk in SPB/SFX some issues have been found (e.g. concerning the Biolab, Rackroom) and forwarded to A. Mancuso. SRP and AMancuso will follow the issues up.
  • Racks in HED outside the rackroom. They are too high and the top cannot be reached. SRP/JE/SRP will follow the issue up.

TS

AoB

  57   19 Jun 2019, 16:33 ITDM AdminGeneralInformationRe: running jdd panels in control rooms

Regarding the recent announcements from doocs/jddd people about running jddd application I post here a short summary:
- running jddd with oracle java 8 via java webstart will be no longer possible as of 10.07.19
- on all control PCs in the instruments control rooms, BKR and exflgateway the new jddd was already in use since March, as described in the previous entry
- today the jddd was updated to version 2.12.10-2, which includes openjdk-12 (control PCs will be automatically updated during night)

On Windows 10 you can install Jddd using Software Shop (Netinstall).

Best, 

Janusz
 

ITDM Admin wrote:

​​​​​On all PCs in the control rooms including BKR and also on the exflgateway there is a new version of jddd installed which is working with openjdk-11.
It is worth to mention that the old javaws from old oracle java 8 is deprecated and it is not recommended running jddd panels using old way, like
javaws jddd-run.jnlp

The recommended way, is to run it on the control PC (if you are in the control room), you don't need to login to exflgateway and start it there anymore, although this is also possible.

To start a svn repository selection window just run
jddd-run

To start a panel of a given name from http repository just type for instance
jddd-run -http XFELMainTaskbar.xml

To start a panel from svn repository just type for instance
jddd-run -file XFELMainTaskbar.xml
 

In case of question contact it-support@xfel.eu

Best

Janusz

 

  58   21 Jun 2019, 10:13 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.00

FXE

SPB/SFX

  • An AC device in the control room leaks. TBartsch has been informed.
  • Some issues with pumps going off during the power glitch yesterday have occured.
  • Power has come back after the interlock tests.
  • Loops updates are being coordinated with EEE. No major issues.
  • Detectors has been moved in the new position. MOV tests will follow and pumping down the system is foreseen for middle of next week.

SCS

SQS

  • Power back. Testing of equipment ongoing.
  • Loop9. PLCs are reachable but not the temrinals. EEE will check.
  • Interlock communication issue. EEE will reboot the master loop.
  • Some Harting connectors have to be plugged in the modules. NRennhack will discuss the details with EEE.

 MID

​​HED

Optical lasers

VAC

XRO

XPD

DET

EEE

  • Due to the power glitch yesterday some uTCA crates in the rackrooms had problems (despite the redundant power lines). This was caused by the firmware not being able to deal with these type of instabilities of the mail power line. The crates are now working again and a new version of the fw will be updated to avoid these issues in the future. In addition, the uTCA crates in the hutches do not get redundant power lines, this means that they went off  and should be checked to make sure they are working properly.

CAS

  • Tests of Karabo 2.5.0. are ongoing (integration PLC/DAQ). HS will give a report on Monday about the tests and the preliminary deployment schedule.

ITDM

  • Some servers require fw updates. JS will send a mail to readiness@xfel.eu with the details.

AoB

  59   24 Jun 2019, 09:53 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30

FXE

  • CRLs mainteinance has been completed.

SPB/SFX

  • Some power sockets are not active. NReimers will contact TS.
  • Detectors has been moved in the new position. MOV tests have started. Tomorrow detector modules will be swapped.

SCS

SQS

  • Some Harting connectors have been plugged in the modules. TB will make sure NRennhack informed JEilers. 1 beckhoff module has still to be modified (according to a CR not yet implemented)
  • Some labels are not correct. NR is discussing with EEE
  • AVC3000 leak controller from Pfeiffer. EEE will release the controls today.
  • Vacuum interlocks. BB is working on it this week.

MID

  • Schutdown activities basically on schedule
  • Bias system tests have been done
  • This week R. Schaffer and J.Hallmann will work on the ALAS
  • Quadrant motion system test will start this week. ASilenzi is the product owner.
  • For next week vacuum interlock tests are foreseen

​​HED

  • It is not clear whether the tunnels are accessible or not. They should not be accessible. SK asks SRP and AGaller.
  • This week cooling system works for the M2 are being executed. Hi res mono will follow.

Optical lasers

VAC

XRO

  • M1  in XTD6 is closed and pumped (10^-7 mbar range). How to proceed with the second mirror is being discussed 
  • XTD2 SA1 M1n works have been initiated. Now stopped because of the interlock tests. Will resume next WE.
  • Self seeding mono in XTD1 is now closed and pumping but the vacuum level is not satisfactory.
  • After the last Karabo restart some devices are not working and this should be fixed before the end of the shutdown. Robert is the contact person in CAS and will follow the issue up.

XPD

DET

EEE

  • Timing will not be available due to maintenance until 5pm, as announced last week.

CAS

  • Tests of Karabo 2.5.0. are ongoing (integration PLC/DAQ). 

ITDM

  • AoB